Commitments (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended
Nov. 30, 2011
Estimated time period for commissioning after restart of construction, in months 24
Incurred capital cost excluding capitalized interest $ 335.0
Interest costs incurred related to the project 51.1
Capital expenditure excluding capitalized interest 324.3
Minimum [Member]
 
Expected total capital cost of project excluding capitalized interest 365
Maximum [Member]
 
Expected total capital cost of project excluding capitalized interest $ 375