4. Commitments

During October 2007, we commenced construction on a project to expand our Hunter, Texas cement plant. In May 2009 we temporarily halted construction on the project because we believed that economic and market conditions made it unlikely that cement demand levels in Texas at that time would permit the new kiln to operate profitably if the project was completed as originally scheduled. We resumed construction in October 2010. The total capital cost of the project is expected to be between $365 million and $375 million, excluding capitalized interest, and commissioning is expected to begin within 24 months of the restart of construction. As of November 30, 2011, we have incurred approximately $335.0 million, excluding capitalized interest of approximately $51.1 million related to the project, of which $324.3 million has been paid.