17. Legal Proceedings
12 Months Ended
May 31, 2024
Notes  
17. Legal Proceedings:

17.  Legal Proceedings:

 

The Company has been named as a third-party defendant in an action captioned Board of Managers of the 432 Park Condominium, et al. v. 56th and Park (NY) Owner LLC, et al. (the “Action”).

The Action was filed on or about September 23, 2021. In the Action, the Board of Managers of 432 Park Condominium (the “Owner”), a condominium association for a high-rise condominium building (the “Building”) located at 432 Park Avenue in New York, N.Y., asserts a claim against the condominium sponsor, 56th and Park (NY) Owner LLC (the “Sponsor”) for damages arising from construction and design defects to the residential and commercial units at the Building.

The Sponsor subsequently filed a third-party complaint against LendLease Construction (US) LMB (“LendLease”) and other parties involved in the Building’s design. As to LendLease, the third-party complaint alleges breach of a construction management contract between LendLease and the Sponsor and negligence arising from purported failure to perform under the contract, and seeks indemnification against any damages asserted against the Sponsor by the Owner.

LendLease subsequently initiated a third-party complaint seeking indemnification from entities with whom LendLease had contracted for the supply of materials and services in connection with construction of the Building. The third-party complaint also names the Company as a third-party defendant based upon a contract between the Company and LendLease to supply 16 Viscous Damping Devices that were incorporated into a Tuned Mass Damper system designed by a third party to limit accelerations of the Building during wind events. The Company has timely filed and served an answer denying the allegations in LendLease’s third party complaint.

The Action, and all of the related third-party actions, are pending in the Commercial Division of the Supreme Court, New York County.

 

On June 17, 2024, the Court entered a scheduling order directing that the parties complete discovery by July 31, 2025 and file dispositive motions by October 17, 2025.

 

In view of the limited discovery to date, it is not possible to determine the likelihood of an unfavorable outcome or to quantify a potential loss.