Regulatory - Additional Information (Detail)
$ in Millions
3 Months Ended
Dec. 12, 2017
USD ($)
MW
Sep. 27, 2017
USD ($)
$ / kWac
MW
Mar. 31, 2018
USD ($)
Sep. 30, 2017
USD ($)
Dec. 31, 2017
USD ($)
Oct. 31, 2013
USD ($)
Public Utilities General Disclosures [Line Items]            
Storm damage reserve           $ 56
Regulatory assets     $ 418   $ 433  
Regulatory liabilities     $ 1,285   1,285  
PGS [Member]            
Public Utilities General Disclosures [Line Items]            
Settlement agreement, approval date     Feb. 07, 2017      
Regulatory liabilities     $ 2      
Tax Reform And Storm Settlement            
Public Utilities General Disclosures [Line Items]            
O&M expense and regulatory liability     $ 19      
Hurricane Irma [Member]            
Public Utilities General Disclosures [Line Items]            
Storm restoration costs       $ 103    
Hurricane Irma [Member] | Storm Reserve [Member]            
Public Utilities General Disclosures [Line Items]            
Storm restoration costs       92    
Hurricane Irma [Member] | O&M Expenses [Member]            
Public Utilities General Disclosures [Line Items]            
Storm restoration costs       4    
Hurricane Irma [Member] | Capital Expenditures [Member]            
Public Utilities General Disclosures [Line Items]            
Storm restoration costs       $ 7    
Solar Project Cost Recovery [Member]            
Public Utilities General Disclosures [Line Items]            
Settlement agreement, extended terms   four years through 2021        
Settlement agreement, approval date   Nov. 06, 2017        
Cost cap of project | $ / kWac   1,500        
Solar generation capacity investments   $ 850        
Impact of tax reform through reduction in base revenue days   120 days        
Solar Project Cost Recovery [Member] | Last Tranche [Member]            
Public Utilities General Disclosures [Line Items]            
Solar energy capacity | MW   50        
Solar Project Cost Recovery [Member] | First Two Tranches [Member]            
Public Utilities General Disclosures [Line Items]            
Solar energy capacity | MW   400        
Maximum cost to be constructed to build last tranche | $ / kWac   1,475        
Solar Project Cost Recovery [Member] | Effective September 1, 2018 [Member]            
Public Utilities General Disclosures [Line Items]            
Solar energy capacity | MW 145          
Estimated revenue requirements $ 24          
Storm Restoration Cost Recovery [Member]            
Public Utilities General Disclosures [Line Items]            
Minimum cost recovery period     12 months      
Replenishment reserve for recovery of cost           $ 56
Storm Reserve [Member]            
Public Utilities General Disclosures [Line Items]            
Regulatory assets     $ 46   $ 47