12. Commitments and Contingencies

Legal Contingencies

From time to time, TECO Energy and its subsidiaries are involved in various legal, tax and regulatory proceedings before various courts, regulatory commissions and governmental agencies in the ordinary course of its business. Where appropriate, accruals are made in accordance with accounting standards for contingencies to provide for matters that are probable of resulting in an estimable loss. While the outcome of such proceedings is uncertain, management does not believe that their ultimate resolution will have a material adverse effect on the company’s results of operations, financial condition or cash flows.

Legal Proceedings

In November 2010, heavy equipment operated at a road construction site being conducted by Posen Construction, Inc. struck a natural gas line causing a rupture and ignition of the gas and an outage in the natural gas service to Lee and Collier counties, Florida. In December 2010, two commercial PGS customers filed a purported class action in Lee County Circuit Court, Florida against PGS on behalf of PGS commercial customers affected by the outage, seeking damages for loss of revenue and other costs related to the gas outage. Posen Construction, Inc., the company conducting construction at the site where the incident occurred, is also a defendant in the action. In June 2013, the court denied the plaintiffs’ motion for class certification and dismissed the plaintiffs’ underlying claim against PGS. The Court’s order is now final and not appealable. PGS filed suit in April 2011 against Posen Construction, Inc. in Federal Court for the Middle District of Florida to recover damages for repair and restoration relating to the incident and Posen Construction, Inc. counter-claimed against PGS alleging negligence. In the first quarter of 2014, the parties entered into a settlement agreement that resolves the claims of the parties. In addition, the suit filed in November 2011 by the Posen Construction, Inc. employee operating the heavy equipment involved in the incident in Lee County Circuit Court against PGS, Posen Construction, Inc. and a PGS contractor involved in the project, seeking damages for his injuries, also remains pending.

In addition, three former or inactive TEC employees are maintaining a suit against TEC in Hillsborough County Circuit Court, Florida for personal injuries allegedly caused by exposure to a chemical substance at one of TEC’s power stations. The suit was originally filed in 2002, and the trial judge allowed the plaintiffs to seek punitive damages in connection with their case. In the first quarter of 2014, the attorneys for the plaintiffs withdrew from representation. A trial is expected sometime in 2014.

The company believes the claims in each of the pending actions described above in this item are without merit and intends to defend each matter vigorously. The company is unable at this time to estimate the possible loss or range of loss with respect to these matters.

Environmental Protection Agency Section 114 Letter

On Feb. 11, 2013, TEC received an information request from the EPA under Section 114(a) of the CAA seeking documents and other information concerning the compliance status of its sulfuric acid plant at its Polk Power Station in Polk County, Florida with the “New Source Review” requirements of the CAA. The request received by TEC appears to be part of a broader EPA national enforcement initiative focusing on sulfuric acid plants. TEC cannot predict at this time what the scope of this matter will ultimately be or the range of outcomes, and therefore it is not able to estimate the possible loss or range of loss, if any, with respect to this matter. TEC responded with the requested information on April 26, 2013 and has not received any response from the EPA on this matter.

Environmental Protection Agency Administrative Order

In December 2010, Clintwood Elkhorn Mining Company, a subsidiary of TECO Coal, received an Administrative Order from the EPA relating to the discharge of wastewater associated with inactive mining operations in Pike County, Kentucky. A consent agreement and final order with the EPA with respect to this matter became effective on July 23, 2013, the costs associated with which were not material to the financial results or financial position of TECO Energy.

Superfund and Former Manufactured Gas Plant Sites

TEC, through its Tampa Electric and Peoples Gas divisions, is a PRP for certain superfund sites and, through its Peoples Gas division, for certain former manufactured gas plant sites. While the joint and several liability associated with these sites presents the potential for significant response costs, as of Dec. 31, 2013, TEC has estimated its ultimate financial liability to be $40.4 million, primarily at PGS. This amount has been accrued and is primarily reflected in the long-term liability section under “Other” on the Consolidated Balance Sheets. The environmental remediation costs associated with these sites, which are expected to be paid over many years, are not expected to have a significant impact on customer prices.

The estimated amounts represent only the portion of the cleanup costs attributable to TEC. The estimates to perform the work are based on TEC’s experience with similar work, adjusted for site-specific conditions and agreements with the respective governmental agencies. The estimates are made in current dollars, are not discounted and do not assume any insurance recoveries.

In instances where other PRPs are involved, most of those PRPs are creditworthy and are likely to continue to be creditworthy for the duration of the remediation work. However, in those instances that they are not, TEC could be liable for more than TEC’s actual percentage of the remediation costs.

Factors that could impact these estimates include the ability of other PRPs to pay their pro-rata portion of the cleanup costs, additional testing and investigation which could expand the scope of the cleanup activities, additional liability that might arise from the cleanup activities themselves or changes in laws or regulations that could require additional remediation. Under current regulations, these costs are recoverable through customer rates established in subsequent base rate proceedings.

 

Long-Term Commitments

TECO Energy has commitments under long-term leases, primarily for building space, capacity payments, office equipment and heavy equipment. Total rental expense for these leases, included in “Regulated operations and maintenance – Other”, “Operation & maintenance other expense – Mining related costs” and “Operation & maintenance other expense – Other” on the Consolidated Statements of Income for the years ended Dec. 31, 2013, 2012 and 2011, totaled $7.6 million, $8.1 million and $10.2 million, respectively. The following is a schedule of future minimum lease payments with non-cancelable lease terms in excess of one year and capacity payments under PPAs at Dec. 31, 2013:

 

Future Minimum Lease and Capacity Payments

                    

(millions)

   Capacity
Payments
     Operating
Leases
     Total  

Year ended Dec. 31:

        

2014

   $ 14.8       $ 5.0       $ 19.8   

2015

     14.9         3.9         18.8   

2016

     14.6         2.6         17.2   

2017

     9.9         2.4         12.3   

2018

     10.1         2.2         12.3   

Thereafter

     0.0         13.4         13.4   
  

 

 

    

 

 

    

 

 

 

Total future minimum payments

   $ 64.3       $ 29.5       $ 93.8   
  

 

 

    

 

 

    

 

 

 

Guarantees and Letters of Credit

TECO Energy accounts for guarantees in accordance with the applicable accounting standards. Upon issuance or modification of a guarantee the company determines if the obligation is subject to either or both of the following:

 

    Initial recognition and initial measurement of a liability, and/or

 

    Disclosure of specific details of the guarantee.

Generally, guarantees of the performance of a third party or guarantees that are based on an underlying (where such a guarantee is not a derivative) are likely to be subject to the recognition and measurement, as well as the disclosure provisions. Such guarantees must initially be recorded at fair value, as determined in accordance with the interpretation.

Alternatively, guarantees between and on behalf of entities under common control or that are similar to product warranties are subject only to the disclosure provisions of the interpretation. The company must disclose information as to the term of the guarantee and the maximum potential amount of future gross payments (undiscounted) under the guarantee, even if the likelihood of a claim is remote.

A summary of the face amount or maximum theoretical obligation under TECO Energy’s letters of credit and guarantees as of Dec. 31, 2013 are as follows:

 

Guarantees-TECO Energy

                                  
(millions)                  After (1)             Liabilities Recognized  

Guarantees for the Benefit of:

   2014      2015-2018      2018      Total      at Dec. 31, 2013  

TECO Coal

              

Fuel purchase related (2)

   $ 0.8       $ 0.7       $ 4.0       $ 5.5       $ 1.5   

Other subsidiaries

              

Guaranty under sale agreement (3)

     0.0         5.0         0.0         5.0         5.0   

Fuel sales and transportation (2)

     10.0         0.0         91.8         101.8         0.1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

   $ 10.8       $ 5.7       $ 95.8       $ 112.3       $ 6.6   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Letters of Credit-Tampa Electric Company

                                  
(millions)                  After (1)             Liabilities Recognized  

Letters of Credit for the Benefit of:

   2014      2015-2018      2018      Total      at Dec. 31, 2013  

Tampa Electric (2)

   $ 0.0       $ 0.0       $ 0.7       $ 0.7       $ 0.1   

 

(1) These letters of credit and guarantees renew annually and are shown on the basis that they will continue to renew beyond 2018.
(2) The amounts shown are the maximum theoretical amounts guaranteed under current agreements. Liabilities recognized represent the associated obligation of TECO Energy under these agreements at Dec. 31, 2013. The obligations under these letters of credit and guarantees include net accounts payable and net derivative liabilities.
(3) The liability recognized relates to an indemnification provision for an uncertain tax position at TCAE that was provided for in the purchase agreement. See Note 19 for additional information.

 

Financial Covenants

In order to utilize their respective bank credit facilities, TECO Energy, TECO Finance and TEC must meet certain financial tests as defined in the applicable agreements. In addition, TECO Energy, TECO Finance, TEC, and the other operating companies have certain restrictive covenants in specific agreements and debt instruments. At Dec. 31, 2013, TECO Energy, TECO Finance, TEC, and the other operating companies were in compliance with all required financial covenants.

Tampa Electric Company [Member]
 
Commitments and Contingencies

9. Commitments and Contingencies

Legal Contingencies

From time to time, TEC and its subsidiaries are involved in various legal, tax and regulatory proceedings before various courts, regulatory commissions and governmental agencies in the ordinary course of its business. Where appropriate, accruals are made in accordance with accounting standards for contingencies to provide for matters that are probable of resulting in an estimable loss. While the outcome of such proceedings is uncertain, management does not believe that their ultimate resolution will have a material adverse effect on the company’s results of operations, financial condition or cash flows.

Legal Proceedings

In November 2010, heavy equipment operated at a road construction site being conducted by Posen Construction, Inc. struck a natural gas line causing a rupture and ignition of the gas and an outage in the natural gas service to Lee and Collier counties, Florida. In December 2010, two commercial PGS customers filed a purported class action in Lee County Circuit Court, Florida against PGS on behalf of PGS commercial customers affected by the outage, seeking damages for loss of revenue and other costs related to the gas outage. Posen Construction, Inc., the company conducting construction at the site where the incident occurred, is also a defendant in the action. In June 2013, the court denied the plaintiffs’ motion for class certification and dismissed the plaintiffs’ underlying claim against PGS. The Court’s order is now final and not appealable. PGS filed suit in April 2011 against Posen Construction, Inc. in Federal Court for the Middle District of Florida to recover damages for repair and restoration relating to the incident and Posen Construction, Inc. counter-claimed against PGS alleging negligence. In the first quarter of 2014, the parties entered into a settlement agreement that resolves the claims of the parties. In addition, the suit filed in November 2011 by the Posen Construction, Inc. employee operating the heavy equipment involved in the incident in Lee County Circuit Court against PGS, Posen Construction, Inc. and a PGS contractor involved in the project, seeking damages for his injuries, also remains pending.

In addition, three former or inactive TEC employees are maintaining a suit against TEC in Hillsborough County Circuit Court, Florida for personal injuries allegedly caused by exposure to a chemical substance at one of TEC’s power stations. The suit was originally filed in 2002, and the trial judge allowed the plaintiffs to seek punitive damages in connection with their case. In the first quarter of 2014, the attorneys for the plaintiffs withdrew from representation. A trial is expected sometime in 2014.

TEC believes the claims in each of the pending actions described above in this item are without merit and intends to defend each matter vigorously. TEC is unable at this time to estimate the possible loss or range of loss with respect to these matters.

Environmental Protection Agency Section 114 Letter

On Feb. 11, 2013, TEC received an information request from the EPA under Section 114(a) of the CAA seeking documents and other information concerning the compliance status of its sulfuric acid plant at its Polk Power Station in Polk County, Florida with the “New Source Review” requirements of the CAA. The request received by TEC appears to be part of a broader EPA national enforcement initiative focusing on sulfuric acid plants. TEC cannot predict at this time what the scope of this matter will ultimately be or the range of outcomes, and therefore it is not able to estimate the possible loss or range of loss, if any, with respect to this matter. TEC responded with the requested information on April 26, 2013 and has not received any response from the EPA on this matter.

Superfund and Former Manufactured Gas Plant Sites

TEC, through its Tampa Electric and Peoples Gas divisions, is a PRP for certain superfund sites and, through its Peoples Gas division, for certain former manufactured gas plant sites. While the joint and several liability associated with these sites presents the potential for significant response costs, as of Dec. 31, 2013, TEC has estimated its ultimate financial liability to be $40.4 million, primarily at PGS. This amount has been accrued and is primarily reflected in the long-term liability section under “Other” on the Consolidated Balance Sheets. The environmental remediation costs associated with these sites, which are expected to be paid over many years, are not expected to have a significant impact on customer prices.

The estimated amounts represent only the portion of the cleanup costs attributable to TEC. The estimates to perform the work are based on TEC’s experience with similar work, adjusted for site-specific conditions and agreements with the respective governmental agencies. The estimates are made in current dollars, are not discounted and do not assume any insurance recoveries.

In instances where other PRPs are involved, most of those PRPs are creditworthy and are likely to continue to be creditworthy for the duration of the remediation work. However, in those instances that they are not, TEC could be liable for more than TEC’s actual percentage of the remediation costs.

Factors that could impact these estimates include the ability of other PRPs to pay their pro-rata portion of the cleanup costs, additional testing and investigation which could expand the scope of the cleanup activities, additional liability that might arise from the cleanup activities themselves or changes in laws or regulations that could require additional remediation. Under current regulations, these costs are recoverable through customer rates established in subsequent base rate proceedings.

Long-Term Commitments

TEC has commitments under long-term leases, primarily for building space, capacity payments, office equipment and heavy equipment. Total rental expense for these leases, included in “Regulated operations & maintenance – Other” on the Consolidated Statements of Income for the years ended Dec. 31, 2013, 2012 and 2011, totaled $2.3 million, $2.2 million and $2.2 million, respectively. The following is a schedule of future minimum lease payments with non-cancelable lease terms in excess of one year and capacity payments under PPAs at Dec. 31, 2013:

 

Future Minimum Lease and Capacity Payments

                    

(millions)

   Capacity
Payments
     Operating
Leases
     Total  

Year ended Dec. 31:

        

2014

   $ 14.8       $ 2.3       $ 17.1   

2015

     14.9         2.3         17.2   

2016

     14.6         2.2         16.8   

2017

     9.9         2.2         12.1   

2018

     10.1         2.2         12.3   

Thereafter

     0.0         13.4         13.4   
  

 

 

    

 

 

    

 

 

 

Total future minimum payments

   $ 64.3       $ 24.6       $ 88.9   
  

 

 

    

 

 

    

 

 

 

Guarantees and Letters of Credit

TEC accounts for guarantees in accordance with the applicable accounting standards. Upon issuance or modification of a guarantee the company determines if the obligation is subject to either or both of the following:

 

    Initial recognition and initial measurement of a liability, and/or

 

    Disclosure of specific details of the guarantee.

Generally, guarantees of the performance of a third party or guarantees that are based on an underlying (where such a guarantee is not a derivative) are likely to be subject to the recognition and measurement, as well as the disclosure provisions. Such guarantees must initially be recorded at fair value, as determined in accordance with the interpretation.

Alternatively, guarantees between and on behalf of entities under common control or that are similar to product warranties are subject only to the disclosure provisions of the interpretation. The company must disclose information as to the term of the guarantee and the maximum potential amount of future gross payments (undiscounted) under the guarantee, even if the likelihood of a claim is remote.

At Dec. 31, 2013, TEC was not obligated under guarantees, but had $0.7 million of letters of credit outstanding.

 

Letters of Credit - Tampa Electric Company

                                  

(millions)

Letters of Credit for the Benefit of:

   2014      2015-2018      After (1)
2018
     Total      Liabilities Recognized
at Dec. 31, 2013
 

Tampa Electric (2)

              

Letters of credit

   $ 0.0       $ 0.0       $ 0.7       $ 0.7       $ 0.1   
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

(1) These letters of credit renew annually and are shown on the basis that they will continue to renew beyond 2018.
(2) The amounts shown are the maximum theoretical amounts guaranteed under current agreements. Liabilities recognized represent the associated obligation of TEC under these agreements at Dec. 31, 2013. The obligations under these letters of credit include net accounts payable and net derivative liabilities.

Financial Covenants

In order to utilize their respective bank credit facilities, TEC must meet certain financial tests as defined in the applicable agreements. In addition, TEC has certain restrictive covenants in specific agreements and debt instruments. At Dec. 31, 2013, TEC was in compliance with all required financial covenants.