Note 12. Commitments and Contingencies

Commitments

We have entered into long-term commitments to purchase CO2 that are either non-cancelable or cancelable only upon the occurrence of specified future events.  The commitments continue for up to 9 years.  The price we will pay for CO2 generally varies depending on the amount of CO2 delivered and the price of oil.  Once all commitments have commenced, our annual commitment under these contracts could range from $14 million to $33 million per year, assuming a $60 per Bbl NYMEX oil price.

We are party to long-term contracts that require us to deliver CO2 to our industrial CO2 customers at various contracted prices. Based upon the maximum amounts deliverable as stated in the industrial contracts, we estimate that we may be obligated to deliver up to 770 Bcf of CO2 to these customers over the next 15 years. The maximum volume required in any given year is approximately 257 MMcf/d, which we judge to be minor given the size of our Jackson Dome proved CO2 reserves at December 31, 2019, our current production capabilities and our projected levels of CO2 usage for our own tertiary flooding program.

Litigation

We are involved in various lawsuits, claims and regulatory proceedings incidental to our businesses. While we currently believe that the ultimate outcome of these proceedings, individually and in the aggregate, will not have a material adverse effect on our financial position, results of operations or cash flows, litigation is subject to inherent uncertainties.  We accrue for losses from litigation and claims if we determine that a loss is probable and the amount can be reasonably estimated.

Riley Ridge Helium Supply Contract Claim

As part of our 2010 and 2011 acquisitions of the Riley Ridge Unit and associated gas processing facility that was under construction, the Company assumed a 20-year helium supply contract under which we agreed to supply the helium separated from the full well stream by operation of the gas processing facility to a third-party purchaser, APMTG Helium, LLC (“APMTG”).  The helium supply contract provides for the delivery of a minimum contracted quantity of helium, with liquidated damages payable if specified quantities of helium are not supplied in accordance with the terms of the contract. The liquidated damages are capped at an aggregate of $46.0 million over the term of the contract.

As the gas processing facility has been shut-in since mid-2014 due to significant technical issues, we have not been able to supply helium under the helium supply contract. In a case filed in November 2014 in the Ninth Judicial District Court of Sublette County, Wyoming, APMTG claimed multiple years of liquidated damages for non-delivery of volumes of helium specified under the helium supply contract. The Company claimed that its contractual obligations were excused by virtue of events that fall within the force majeure provisions in the helium supply contract.

On March 11, 2019, the trial court entered a final judgment that a force majeure condition did exist, but the Company’s performance was excused by the force majeure provisions of the contract for only a 35-day period in 2014, and as a result the Company should pay APMTG liquidated damages and interest thereon for those time periods from contract commencement to the close of evidence (November 29, 2017). The Company’s position continues to be that its contractual obligations have been and continue to be excused by events that fall within the force majeure provisions of the helium supply contract, so the Company has appealed the trial court’s ruling to the Wyoming Supreme Court. Briefing for the appeal by the Company and APMTG is currently expected to be completed in late May or early June, after which oral arguments will be scheduled and heard prior to the Wyoming Supreme Court entering its judgment on the appeal. The timing and outcome of this appeal process is currently unpredictable, but at this time is anticipated to extend over the next nine to twelve months.

Absent reversal of the trial court’s ruling on appeal, the Company anticipates total liquidated damages would equal the $46.0 million aggregate cap under the helium supply contract plus $5.2 million of associated costs (through December 31, 2019), for a total of $51.2 million, which is included in “Other liabilities” in our Consolidated Balance Sheets as of December 31, 2019, and $49.4 million of which was accrued in the fourth quarter of 2018. The Company currently has a $32.8 million letter of credit posted as security in this case as part of the appeal process.

Other Contingencies

We are subject to audits for various taxes (income, sales and use, and severance) in the various states in which we operate, and from time to time receive assessments for potential taxes that we may owe.  In the past, settlement of these matters has not had a material adverse financial impact on us, and currently we have no material assessments for potential taxes.

We are subject to various possible contingencies that arise primarily from interpretation of federal and state laws and regulations affecting the oil and natural gas industry.  Such contingencies include differing interpretations as to the prices at which oil and natural gas sales may be made, the prices at which royalty owners may be paid for production from their leases, environmental issues and other matters.  Although we believe that we have complied with the various laws and regulations, administrative rulings
and interpretations thereof, adjustments could be required as new interpretations and regulations are issued.  In addition, production rates, marketing and environmental matters are subject to regulation by various federal and state agencies.