Regulatory Matters REGULATORY MATTERS
Regulation
DTE Electric and DTE Gas are subject to the regulatory jurisdiction of the MPSC, which issues orders pertaining to rates, recovery of certain costs, including the costs of generating facilities and regulatory assets, conditions of service, accounting, and operating-related matters. DTE Electric is also regulated by the FERC with respect to financing authorization, wholesale electric market activities, certain affiliate transactions, the acquisition and disposition of certain generation and other facilities, and, in conjunction with the NERC, compliance with mandatory reliability standards. Regulation results in differences in the application of generally accepted accounting principles between regulated and non-regulated businesses.
The Registrants are unable to predict the outcome of any unresolved regulatory matters discussed herein. Resolution of these matters is dependent upon future MPSC and FERC orders and appeals, which may materially impact the Consolidated Financial Statements of the Registrants.
Regulatory Assets and Liabilities
DTE Electric and DTE Gas are required to record Regulatory assets and liabilities for certain transactions that would have been treated as revenue or expense in non-regulated businesses. Continued applicability of regulatory accounting treatment requires that rates be designed to recover specific costs of providing regulated services and be charged to and collected from customers. Future regulatory changes could result in the discontinuance of this accounting treatment for Regulatory assets and liabilities for some or all of the Registrants' businesses and may require the write-off of the portion of any Regulatory asset or liability that was no longer probable of recovery through regulated rates. Management believes that currently available facts support the continued use of Regulatory assets and liabilities and that all Regulatory assets and liabilities are recoverable or refundable in the current regulatory environment.
The following are balances and a brief description of the Registrants' Regulatory assets and liabilities at December 31:
DTE EnergyDTE Electric
2021202020212020
Assets(In millions)
Recoverable pension and other postretirement costs
Pension$1,372 $1,938 $1,056 $1,477 
Other postretirement costs53 165 27 108 
Recoverable undepreciated costs on retiring plants667 664 667 664 
Fermi 2 asset retirement obligation613 645 613 645 
Enhanced Tree Trimming Program deferred costs189 119 189 119 
Recoverable Michigan income taxes163 176 133 142 
Accrued PSCR/GCR revenue160 100 142 100 
Energy Waste Reduction incentive79 62 63 49 
Recoverable income taxes related to AFUDC equity68 64 61 54 
Deferred environmental costs51 57  — 
Unamortized loss on reacquired debt51 55 38 41 
Customer360 deferred costs46 51 46 51 
Nuclear Performance Evaluation and Review Committee Tracker39 55 39 55 
Non-service pension and other postretirement costs25 21  — 
Energy Waste Reduction20 19  — 
Other recoverable income taxes16 19 16 19 
Transitional Reconciliation Mechanism8 11 8 11 
Other57 33 38 28 
3,677 4,254 3,136 3,563 
Less amount included in Current Assets(195)(129)(168)(123)
$3,482 $4,125 $2,968 $3,440 
DTE EnergyDTE Electric
2021202020212020
Liabilities(In millions)
Refundable federal income taxes$2,117 $2,255 $1,729 $1,827 
Removal costs liability679 831 283 410 
Negative other postretirement offset150 122 106 86 
Non-service pension and other postretirement costs110 78 54 36 
Incremental tree trim surge90 — 90 — 
COVID-19 voluntary refund30 30 30 30 
Energy Waste Reduction27 15 27 15 
Renewable energy13 21 13 21 
Other46 50 43 25 
3,262 3,402 2,375 2,450 
Less amount included in Current Liabilities(156)(39)(154)(18)
$3,106 $3,363 $2,221 $2,432 
As noted below, certain Regulatory assets for which costs have been incurred have been included (or are expected to be included, for costs incurred subsequent to the most recently approved rate case) in DTE Electric's or DTE Gas' rate base, thereby providing a return on invested costs (except as noted). Certain other Regulatory assets are not included in rate base but accrue recoverable carrying charges until surcharges to collect the assets are billed. Certain Regulatory assets do not result from cash expenditures and therefore do not represent investments included in rate base or have offsetting liabilities that reduce rate base.
ASSETS
Recoverable pension and other postretirement costs — Accounting standards for pension and other postretirement benefit costs require, among other things, the recognition in Other comprehensive income of the actuarial gains or losses and the prior service costs that arise during the period but are not immediately recognized as components of net periodic benefit costs. DTE Electric and DTE Gas record the impact of actuarial gains or losses and prior service costs as Regulatory assets since the traditional rate setting process allows for the recovery of pension and other postretirement costs. The asset will reverse as the deferred items are amortized and recognized as components of net periodic benefit costs. Refer to Note 20 to the Consolidated Financial Statements, "Retirement Benefits and Trusteed Assets," for additional information regarding the changes in pension and other postretirement costs for the period and the impact on Regulatory assets.(a)
Recoverable undepreciated costs on retiring plants — Deferral of estimated remaining balances associated with coal power plants expected to be retired by the end of 2022. Amounts also include $73 million for the remaining undepreciated cost of the River Rouge power plant, which was retired in 2021 and approved for securitization and recovery in the MPSC's June 2021 order. Refer to the "2021 Securitization Filing" section below for additional information.
Fermi 2 asset retirement obligation — Obligation for Fermi 2 decommissioning costs. The asset captures the timing differences between expense recognition and current recovery in rates and will reverse over the remaining life of the related plant.(a)
Enhanced Tree Trimming Program deferred costs — The MPSC approved the deferral of costs for a tree trimming surge through 2022, aimed at reducing the number and duration of customer interruptions.  The MPSC also approved the securitization and recovery of up to $157 million of these costs in their June 2021 order. Refer to the "2021 Securitization Filing" section below for additional information. Additional tree trim surge costs are expected to be recovered through future securitization filings. DTE Electric also requested continued deferral of tree trimming surge costs through 2024 in its January 21, 2022 rate case filing, with an MPSC order expected in November 2022.
Recoverable Michigan income taxes — The State of Michigan enacted a corporate income tax resulting in the establishment of state deferred tax liabilities for DTE Energy's utilities.  Offsetting Regulatory assets were also recorded as the impacts of the deferred tax liabilities will be reflected in rates as the related taxable temporary differences reverse and flow through current income tax expense.
Accrued PSCR/GCR revenue — Receivable for the temporary under-recovery of and carrying costs on fuel and purchased power costs incurred by DTE Electric which are recoverable through the PSCR mechanism and temporary under-recovery of and carrying costs on gas costs incurred by DTE Gas which are recoverable through the GCR mechanism.
Energy Waste Reduction incentive — DTE Electric and DTE Gas operate MPSC approved energy waste reduction programs designed to reduce overall energy usage by their customers. The utilities are eligible to earn an incentive by exceeding statutory savings targets. The utilities have consistently exceeded the savings targets and recognize the incentive as a Regulatory asset in the period earned.(a)
Recoverable income taxes related to AFUDC equity — Accounting standards for income taxes require recognition of a deferred tax liability for the equity component of AFUDC.  A Regulatory asset is required for the future increase in taxes payable related to the equity component of AFUDC that will be recovered from customers through future rates over the remaining life of the related plant.
Deferred environmental costs — The MPSC approved the deferral of investigation and remediation costs associated with DTE Gas' former MGP sites. Amortization of deferred costs is over a ten-year period beginning in the year after costs were incurred, with recovery (net of any insurance proceeds) through base rate filings.(a)
Unamortized loss on reacquired debt — The unamortized discount, premium, and expense related to debt redeemed with a refinancing are deferred, amortized, and recovered over the life of the replacement issue.
Customer360 deferred costs — The MPSC approved the deferral and amortization of certain costs associated with implementing Customer360, an integrated software application that enables improved interface among customer service, billing, meter reading, credit and collections, device management, account management, and retail access. Amortization of deferred costs over a 15-year amortization period began after the billing system was put into operation during the second quarter of 2017. The deferred costs are recorded as Regulatory Assets at DTE Electric and DTE Gas receives an intercompany charge for their proportionate share of amortization expense.
Nuclear Performance Evaluation and Review Committee Tracker — Deferral and amortization of certain costs associated with oversight and review of DTE Electric's nuclear power generation program, including safety and regulatory compliance, nuclear leadership, nuclear facilities, and operational and financial performance, pursuant to MPSC authorization. Deferrals are amortized over a five-year period with recovery through base rate filings.
Non-service pension and other postretirement costs — Upon adoption of ASU 2017-07 on January 1, 2018, certain non-service pension and other postretirement costs are no longer capitalized into Property, Plant & Equipment. Such costs may be recorded to Regulatory assets for ratemaking purposes and recovered as amortization expense based on the composite depreciation rate for plant-in-service.
Energy Waste Reduction — Receivable for the under-recovery of energy waste reduction costs incurred by DTE Gas which are recoverable through a surcharge.(a)
Other recoverable income taxes — Income tax receivable from DTE Electric's customers representing the difference in property-related deferred income taxes and amounts previously reflected in DTE Electric's rates. This asset will reverse over the remaining life of the related plant.
Transitional Reconciliation Mechanism — The MPSC approved the recovery of the deferred net incremental revenue requirement associated with the transition of PLD customers to DTE Electric's distribution system effective July 1, 2014. Annual reconciliations are filed and surcharges are implemented to recover approved amounts.
________________________________________________
(a)Regulatory assets not earning a return or accruing carrying charges.
LIABILITIES
Refundable federal income taxes — In December 2017, the TCJA was enacted and reduced the corporate income tax rate, effective January 1, 2018. DTE Electric and DTE Gas remeasured deferred taxes, resulting in a reduction to deferred tax liabilities, to reflect the impact of the TCJA on the cumulative temporary differences expected to reverse after the effective date. Regulatory liabilities were also recorded to offset the impact of the deferred tax remeasurement reflected in rates.
Removal costs liability — The amounts collected from customers to fund future asset removal activities in excess of removal costs incurred.
Negative other postretirement offset — DTE Electric and DTE Gas' negative other postretirement costs are not included as a reduction to their authorized rates; therefore, DTE Electric and DTE Gas are accruing a Regulatory liability to eliminate the impact on earnings of the negative other postretirement expense accrual. The Regulatory liabilities will reverse to the extent DTE Electric and DTE Gas' other postretirement expense is positive in future years.
Non-service pension and other postretirement costs Upon adoption of ASU 2017-07 on January 1, 2018, certain non-service pension and other postretirement cost activity is no longer credited to Property, Plant & Equipment. Such costs may be recorded to Regulatory liabilities for ratemaking purposes and refunded through credits to amortization expense based on the composite depreciation rate for plant-in-service.
Incremental tree trim surge — One-time voluntary refund to be administered by investing in tree trimming, incremental to the Enhanced Tree Trimming Program, without seeking future cost recovery. Refer to the “2020-2021 Accounting Applications” section below for additional information regarding the refund.
COVID-19 voluntary refund — One-time refund obligation owed to DTE Electric customers due to certain sales increases driven by the COVID-19 pandemic. Amortization of the liability will be used to offset the cost of service related to new plant, beginning January 1, 2022 and continuing until the earlier of the implementation of new base rates or December 31, 2022.
Energy Waste Reduction — Amounts collected in rates in excess of energy waste reduction costs incurred by DTE Electric.
Renewable energy — Amounts collected in rates in excess of renewable energy expenditures.
2020-2021 Accounting Applications
On July 9, 2020, the MPSC approved DTE Electric's request to accelerate amortization of the portion of its refundable federal income taxes regulatory liability related to non-plant accumulated deferred income tax balances that resulted from the TCJA. DTE Electric was authorized to increase amortization by $102 million beginning in May 2021, which would fully amortize this portion of the liability by the end of 2021 instead of April 2033. The accelerated amortization would not impact customer rates and would allow DTE Electric to defer its next rate case filing previously set for July 2020 to March 2021.
On February 26, 2021, DTE Electric filed an additional application requesting a delay in the accelerated amortization approved in the 2020 application. DTE Electric requested delaying the start of amortization from May 2021 to December 1, 2021, which would fully amortize these balances by the end of 2022 and allow DTE Electric to further defer its next rate case filing. The accounting application was approved by the MPSC on April 8, 2021.
On August 31, 2021, DTE Electric filed an accounting application with the MPSC requesting approval of a one-time voluntary refund of $70 million collected in 2021 associated with the unexpected customer usage patterns due to the COVID-19 pandemic. This refund will be administered by investing in additional tree trimming without seeking future cost recovery. Such efforts would serve to improve customer reliability without impacting rates, thus providing an affordability benefit to customers. These investments will be incremental to the Tree Trim Surge expenses previously authorized by the MPSC.
On November 4, 2021, the MPSC issued an order authorizing the one-time accounting and a regulatory liability for a minimum of $70 million. In that order, the MPSC directed DTE Electric to file a letter before December 31, 2021 indicating the amount of the final regulatory liability it planned to record.
On December 27, 2021, DTE Electric submitted a letter to the MPSC substantiating that a regulatory liability of $90 million would be recorded. On December 28, 2021, the MPSC Staff confirmed that DTE Electric complied with the requirements set forth in the November 4th order. Accordingly, DTE Electric recognized the regulatory liability of $90 million and will relieve the liability as the additional tree trim expenses are incurred during 2022-2023. If the full $90 million is not spent by the end of 2023, DTE Electric will provide refunds to customers via bill credits for any shortage.
2021 Securitization Filing
On March 26, 2021, DTE Electric filed an application requesting a financing order approving the securitization financing of $184 million of qualified costs related to the net book value of the River Rouge generation plant and tree trimming surge program costs. The filing requested recovery of these qualifying costs from DTE Electric's customers.
A final MPSC financing order was issued on June 23, 2021 authorizing DTE Electric to proceed with the issuance of securitization bonds for qualified costs of up to $236 million, increased for the inclusion of deferred income taxes. The financing order further authorized customer charges for the timely recovery of the debt service costs on the securitization bonds and other ongoing qualified costs. Securitization financing is expected to occur in March 2022.
2021 Gas Rate Case Filing
DTE Gas filed a rate case with the MPSC on February 12, 2021 requesting an increase in base rates of $195 million based on a projected twelve-month period ending December 31, 2022. The requested increase in base rates was primarily due to an increase in net plant resulting from infrastructure investments and operating and maintenance expenses. The rate filing also requested an increase in return on equity from 9.9% to 10.25% and included projected changes in sales and working capital. On December 9, 2021, the MPSC issued an order approving an annual revenue increase of $84 million for services rendered on or after January 1, 2022 and a return on equity of 9.9%.
2022 Electric Rate Case Filing
DTE Electric filed a rate case with the MPSC on January 21, 2022 requesting an increase in base rates of $388 million based on a projected twelve-month period ending October 31, 2023. The requested increase in base rates is primarily due to an increase in net plant resulting from generation and distribution investments, as well as related increases to depreciation and property tax expenses. The rate filing also requested an increase in return on equity from 9.9% to 10.25% and includes projected changes in sales. A final MPSC order in this case is expected in November 2022.