XML 72 R14.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Matters (Notes)
3 Months Ended
Mar. 31, 2014
Public Utilities, General Disclosures [Abstract]  
Regulatory Matters
REGULATORY MATTERS

Refundable Revenue Decoupling/ Deferred Gain Amortization

In September 2012, the MPSC approved DTE Electric's accounting application to defer for future amortization the gain resulting from the reversal of the Company's $127 million regulatory liability associated with the operation of the RDM. The approved application provided for the amortization of the regulatory liability to income, at a monthly rate of approximately $10.6 million, beginning January 2014. On April 1, 2014, the MPSC approved DTE Electric's accounting application to suspend the amortization of the RDM regulatory liability as of June 30, 2014 and to complete the amortization over the period January 2015 to June 2015. If DTE Electric's base rates are increased prior to July 1, 2015, the Company will cease amortization and refund to customers the remaining unamortized balance of the regulatory liability.

PSCR Proceedings

The PSCR process is designed to allow DTE Electric to recover all of its power supply costs if incurred under reasonable and prudent policies and practices. DTE Electric's power supply costs include fuel and related transportation costs, purchased and net interchange power costs, nitrogen oxide and sulfur dioxide emission allowances costs, urea costs, transmission costs and MISO costs. The MPSC reviews these costs, policies and practices for prudence in annual plan and reconciliation filings.

2012 PSCR Year — In March 2013, DTE Electric filed the 2012 PSCR reconciliation calculating a net under-recovery of approximately $87 million that includes an under-recovery of approximately $148 million for the 2011 PSCR year. The reconciliation includes purchased power costs related to the manual shutdown of our Fermi 2 nuclear power plant in June 2012 caused by the failure of one of the plant's two non-safety related feed-water pumps. The plant was restarted on July 30, 2012, which restored production to nominal 68% of full capacity. In September 2013, the repair to the plant was completed and production was returned to full capacity. DTE Electric was able to purchase sufficient power from MISO to continue to provide uninterrupted service to our customers. Certain intervenors in the reconciliation case have challenged the recovery of up to $32 million of the Fermi-related purchased power costs. Resolution of this matter is expected in 2014.

2013 PSCR Year — In March 2014, DTE Electric filed the 2013 PSCR reconciliation calculating a net over-recovery of $54 million that includes an under-recovery of $87 million for the 2012 PSCR year.