XML 121 R94.htm IDEA: XBRL DOCUMENT v2.4.0.6
Accounting for Suspended Exploratory Wells (Details Textual) (USD $)
In Millions, unless otherwise specified
Dec. 31, 2011
Project
Y
Well
Dec. 31, 2010
Project
Dec. 31, 2009
Project
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total $ 1,877 $ 2,299 $ 1,871
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 47 53 46
Expected period for decision on the recognition of proved reserves 3    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 1,877 2,299 1,871
Capitalized Exploratory Well Costs Associated with project sanction approved and construction in progress, with initial recognition of proved reserves expected upon reaching economic producibility 111    
Total number of exploratory wells that have been capitalized for period greater Than one year 161    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 47 53 46
Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 1    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 1    
Drilling Activity [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 939    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 939    
Drilling Activity [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 26    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 26    
No Drilling Activity [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 938    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 938    
No Drilling Activity [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 21    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 21    
Development Concept Under Review by Government [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 283    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 283    
Development Concept Under Review by Government [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 5    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 5    
Miscellaneous Activities [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 14    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 14    
Miscellaneous Activities [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 2    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 2    
Reviewing Development Alternatives [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 322    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year 322    
Reviewing Development Alternatives [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 6    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 6    
Undergoing Front End Engineering and Design with Final Investment Decision Expected [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized Exploratory Well Costs that Have Been Capitalized for Period Greater than One Year, Total 208    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Exploratory well costs capitalized for a period greater than one year $ 208    
Undergoing Front End Engineering and Design with Final Investment Decision Expected [Member] | Project [Member]
     
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 7    
Undergoing front-end engineering and design with final investment decision expected in three years 3    
Accounting for Suspended Exploratory Wells (Textual) [Abstract]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year 7