Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 2,823 $ 2,673 $ 2,604
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project [1] 39 51 51
Expected period for decision on the recognition of proved reserves 5 years    
Capitalized exploratory well costs that have been capitalized for period greater than one year, number of wells | Well 165    
Drilling Activity [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 1,662    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 20    
No Drilling Activity [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 1,161    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 19    
Undergoing Front End Engineering and Design with Final Investment Decision Expected [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 190    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 2    
Undergoing front-end engineering and design with final investment decision expected in three years 4 years    
Development Concept Under Review by Government [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 99    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 1    
Reviewing Development Alternatives [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Capitalized exploratory well costs that have been capitalized for period greater than one year | $ $ 814    
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 7    
Miscellaneous Activities for Projects with Smaller Amounts Suspended [Member]      
Projects with Exploratory Well Costs Capitalized for More than One Year [Line Items]      
Number of projects with exploratory well costs that have been capitalized for a period greater than one year | Project 9    
Capitalized exploratory well costs that are approved and construction in progress | $ $ 58    
[1] Certain projects have multiple wells or fields or both.