Aggregate future minimum rental payments required under all non-cancelable operating leases at March 31, 2020 are as follows:
Year 
April 1, 2020 to December 31, 2020$2,430  
20212,318  
20221,768  
20231,385  
2024629  
2025234  
Thereafter599  
Total minimum lease payments$9,363  
The Company’s Verona, Missouri facility, while held by a prior owner, was designated by the EPA as a Superfund site and placed on the National Priorities List in 1983, because of dioxin contamination on portions of the site. Remediation was conducted by the prior owner under the oversight of the EPA and the Missouri Department of Natural Resources. While the Company must maintain the integrity of the capped areas in the remediation areas on the site, the prior owner is responsible for completion of any further Superfund remedy. The Company is indemnified by the sellers under its May 2001 asset purchase agreement covering its acquisition of the Verona, Missouri facility for potential liabilities associated with the Superfund site.
From time to time, the Company is a party to various litigation, claims and assessments.  Management believes that the ultimate outcome of such matters will not have a material effect on the Company’s consolidated financial position, results of operations, or liquidity.