Schedule of minimum future lease payments, by fiscal year

The minimum future lease payment, by fiscal year, as of June 30, 2012 is as follows:

 

Fiscal Year 

 

Amount

 

2013 (nine months remaining)

 

226,102

 

2014

 

320,080

 

2015

 

108,303

 

Total

 

$

654,485

Equipment leases with General Electric Capital Corporation
 
Commitments and contingencies  
Schedule of minimum future lease payments, by fiscal year

Our minimum future equipment lease payments with General Electric Capital Corporation as of June 30, 2012, by fiscal year, are as follows:

 

Fiscal Year 

 

Amount

 

2013 (nine months remaining)

 

76,405

 

2014

 

8,488

 

Total

 

$