The Company is involved from time to time in various litigations, claims and administrative proceedings arising out of the ordinary conduct of its business. Amounts recorded for identified contingent liabilities are estimates, which are reviewed periodically and adjusted to reflect additional information when it becomes available. Subject to the uncertainties inherent in estimating future costs for contingent liabilities, management believes that any liability which may result from these legal matters would not have a material adverse effect on the Company's business or financial condition.
Environmental
The Company is subject to a broad range of federal, foreign, state and local laws and regulations relating to pollution and protection of the environment. The Company believes that it is currently in substantial compliance with applicable environmental requirements and does not currently anticipate any material adverse effect on its operations, financial or competitive position as a result of its efforts to comply with environmental requirements. Some risk of environmental liability is inherent, however, in the nature of the Company’s business and, accordingly, there can be no assurance that material environmental liabilities will not arise.
Equipment Lease Agreement
In the third quarter of 2011, the Company's state-of-the-art spunmelt line in Waynesboro, Virginia commenced commercial production. The plant expansion increased capacity to meet demand for nonwoven materials in the hygiene and healthcare applications in the U.S. The line was principally funded by a seven year equipment lease with a capitalized cost of $53.6 million. From the commencement of the lease to its fourth anniversary date, the Company will make annual lease payments of $8.3 million. From the fourth anniversary date to the end of the lease term, the Company's annual lease payments may change, as defined in the lease agreement. The aggregate future lease payments under the agreement, subject to adjustment, are expected to approximate $58 million. The lease includes covenants, events of default and other provisions that requires the Company to maintain certain financial ratios and other requirements.
Providência Tax Claims
Total consideration paid for the acquisition of Providência includes $47.9 million of deferred purchase price (the "Deferred Consideration"). The Deferred Consideration accretes at a rate of 9.5% per annum compounded daily, which shall be paid to the selling stockholders to the extent certain existing and potential tax claims of Providência ("Providência Tax Claims") are resolved in Providência's favor. At September 27, 2014, the outstanding balance of the Deferred Consideration was $44.8 million. If the Company incurs actual tax liability with respect to the Providência Tax Claims, the amount of the Deferred Purchase Price owed to the selling stockholders will be reduced by the amount of such actual tax liability. The Company will be responsible for any actual tax liability in excess of the Deferred Purchase Price. The Deferred Consideration is reflected on the Consolidated Balance Sheet as a noncurrent liability as the settlement of existing and potential claims is expected to be greater than one year.
Financing Obligation
As a result of the acquisition of Fiberweb, the Company acquired a manufacturing facility in Old Hickory, Tennessee, the assets of which included a utility plant used to generate steam for use in its manufacturing process. Upon completion of its construction in 2011, the utility plant was sold to a unrelated third-party and subsequently leased back by Fiberweb for a period of 10 years. The transaction was appropriately accounted for by Fiberweb under International Financial Reporting Standards ("IFRS") as a sale-leaseback whereby the assets were excluded from the balance sheet and monthly lease payments were recorded as rent expense.
The Company determined that current accounting guidance under GAAP disallowed sale-leaseback treatment if there was continuing involvement with the property. As a result, the transaction is not accounted for as a sale-leaseback, but as a direct financing lease under GAAP, recognizing the assets as part of property, plant and equipment and a related financing obligation as a long-term liability. Cash payments to the lessor are allocated between interest expense and amortization of the financing obligation. At the end of the lease term, the Company will recognize the sale of the utility plant, however, no gain or loss will be recognized as the financing obligation will equal the expected carrying value of the assets. At September 27, 2014, the outstanding balance of the financing obligation was $18.9 million, which is included in Other noncurrent liabilities in the Consolidated Balance Sheets.