XML 45 R33.htm IDEA: XBRL DOCUMENT v3.8.0.1
Rate Matters (Details) - USD ($)
$ in Millions
1 Months Ended 9 Months Ended 12 Months Ended
Oct. 31, 2017
Aug. 31, 2017
Nov. 30, 2016
Sep. 30, 2017
Dec. 31, 2015
Dec. 31, 2014
PUCT Proceeding - Appeal of the Texas 2015 Electric Rate Case Decision            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Requested Rate Increase (Decrease), Amount           $ 42.1
PUCT Proceeding - Texas 2017 Electric Rate Case            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Requested Rate Increase (Decrease), Amount   $ 66.4        
Public Utilities, Requested Rate Increase (Decrease), Percentage   7.10%        
Public Utilities, Number of Months in Test Year   12 months        
Public Utilities, Number of Months in Test Year which are Estimated   3 months        
Public Utilities, Requested Return on Equity, Percentage   10.25%        
Public Utilities, Requested Rate Base, Amount   $ 1,900.0        
Public Utilities, Requested Equity Capital Structure, Percentage   53.97%        
NMPRC Proceeding - New Mexico 2016 Electric Rate Case            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Requested Rate Increase (Decrease), Amount     $ 41.4      
Public Utilities, Requested Rate Increase (Decrease), Percentage     10.90%      
Public Utilities, Requested Return on Equity, Percentage     10.10%      
Public Utilities, Requested Rate Base, Amount     $ 832.0      
Public Utilities, Requested Equity Capital Structure, Percentage     53.97%      
Public Utility Commission of Texas (PUCT) | PUCT Proceeding - Appeal of the Texas 2015 Electric Rate Case Decision            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Approved Rate Decrease, Net of Rate Case Expenses         $ 4.0  
Subsequent Event | PUCT Proceeding - Texas 2017 Electric Rate Case            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Revised Requested Rate Increase $ 54.6          
Public Utilities, Revised Requested Rate Increase, Percentage 5.80%          
Public Utilities, Rate Case Expenses Addressed in Separate Proceeding $ 4.4          
Public Utilities, Revised Incremental revenue request 69.2          
Transmission Cost Recovery Factory (TCRF) Rider | Subsequent Event | PUCT Proceeding - Texas 2017 Electric Rate Case            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Rider Conversion to Base Rates [1] $ 14.6          
SPS | Southwest Power Pool (SPP) | SPP Open Access Transmission Tariff Upgrade Costs            
Public Utilities, General Disclosures [Line Items]            
Public Utilities, Billed Charges For Transmission Service Upgrades     $ 12.8      
Public Utilities, Length of Payment Period Requested, In Years       5 years    
Public Utilities, Monthly Billed Charges For Transmission Service Upgrades       $ 0.5    
[1] (a) The roll-in of the TCRF rider revenue into base rates will not have an impact on customer bills or total revenue as these costs are already being recovered through the rider. SPS can request another TCRF rider after the conclusion of this rate case to recover transmission investments subsequent to June 30, 2017.