XML 26 R14.htm IDEA: XBRL DOCUMENT v3.8.0.1
Rate Matters
9 Months Ended
Sep. 30, 2017
Public Utilities, General Disclosures [Abstract]  
Rate Matters
Rate Matters

Except to the extent noted below, the circumstances set forth in Note 10 to the financial statements included in SPS’ Annual Report on Form 10-K for the year ended Dec. 31, 2016 and in Note 5 to SPS’ Quarterly Report on Form 10-Q for the quarterly periods ended March 31, 2017 and June 30, 2017, appropriately represent, in all material respects, the current status of other rate matters, and are incorporated herein by reference.

Pending Regulatory Proceedings — Public Utility Commission of Texas (PUCT)

Appeal of the Texas 2015 Electric Rate Case Decision — In 2014, SPS had requested an overall retail electric revenue rate increase of $42.1 million. In 2015, the PUCT approved an overall rate decrease of approximately $4.0 million, net of rate case expenses. In April 2016, SPS filed an appeal, with the Texas State District Court, of the PUCT’s order that had denied SPS’ request for rehearing on certain items in SPS’ Texas 2015 electric rate case related to capital structure, incentive compensation and wholesale load reductions. In March 2017, the Travis County District Court denied SPS’ appeal.  In April 2017, SPS appealed the District Court’s decision to the Court of Appeals.

Texas 2017 Electric Rate Case — In August 2017, SPS filed a $66.4 million, or 7.1 percent, retail electric, non-fuel base rate increase case in Texas with each of its Texas municipalities and the PUCT. The request was based on the 12-month period ended June 30, 2017, with the final three months based on estimates, a requested return on equity (ROE) of 10.25 percent, a Texas retail electric rate base of approximately $1.9 billion and an equity ratio of 53.97 percent.

In October 2017, SPS revised its request to $54.6 million, or 5.8 percent, which reflects updated actual results. In addition, approximately $4.4 million of rate case expenses was bifurcated into a separate docket.

The following table summarizes SPS’ revised rate increase request:
Revenue Request (Millions of Dollars)
 
 
Incremental revenue request
 
$
69.2

Transmission Cost Recovery Factor (TCRF) revenue conversion to base rates (a)
 
(14.6
)
  Net revenue increase request
 
$
54.6


(a)
The roll-in of the TCRF rider revenue into base rates will not have an impact on customer bills or total revenue as these costs are already being recovered through the rider. SPS can request another TCRF rider after the conclusion of this rate case to recover transmission investments subsequent to June 30, 2017.

Key dates in the procedural schedule are as follows:
Intervenors’ direct testimony — Feb. 22, 2018;
PUCT Staff direct testimony — March 1, 2018;
PUCT Staff and intervenors’ cross-rebuttal testimony — March 22, 2018;
SPS’ rebuttal testimony — March 23, 2018;
Hearings — April 10 - 20, 2018; and
Statutory deadline — Aug. 31, 2018.

The final rates are expected to be effective retroactive to Jan. 23, 2018 through a customer surcharge. A PUCT decision is expected in the third quarter of 2018.

Pending Regulatory Proceeding — New Mexico Public Regulation Commission (NMPRC)

New Mexico 2016 Electric Rate Case — In November 2016, SPS filed an electric rate case with the NMPRC seeking an increase in base rates of approximately $41.4 million, representing a total revenue increase of approximately 10.9 percent. The rate filing was based on a requested ROE of 10.1 percent, an equity ratio of 53.97 percent, an electric rate base of approximately $832 million and a future test year ending June 30, 2018.

In April 2017, the NMPRC dismissed SPS’ rate case. In May 2017, SPS filed a notice of appeal to the New Mexico Supreme Court. A decision from the New Mexico Supreme Court is not expected until the second or third quarter of 2018.

SPS plans to file another base rate case by November 2017 utilizing a historic test year ending June 2017.

Pending Regulatory Proceeding — Federal Energy Regulatory Commission (FERC)

Southwest Power Pool, Inc. (SPP) Open Access Transmission Tariff (OATT) Upgrade Costs — Under the SPP OATT, costs of participant-funded, or “sponsored,” transmission upgrades may be recovered from other SPP customers whose transmission service depends on capacity enabled by the upgrade.  The SPP OATT has allowed SPP to charge for these upgrades since 2008, but SPP had not been charging its customers for these upgrades.  In July 2016, the FERC granted SPP’s request for a waiver to allow SPP to recover the charges not billed since 2008.  In November 2016, SPP billed SPS a net amount, for the period from 2008 through August 2016, of $12.8 million for these charges, to be paid over a five-year period commencing November 2016. SPP is also billing SPS ongoing charges of approximately $0.5 million per month. On the retail level, in October 2016, SPS filed applications for deferred accounting and future recovery of related costs in New Mexico and Texas.  In December 2016, SPS’ New Mexico application was consolidated with its base rate case, but the NMPRC dismissed that rate case in April 2017. SPS will seek recovery of these SPP charges in its next New Mexico base rate case by November 2017. In March 2017, SPS withdrew its Texas application and is now seeking to recover these SPP charges in its pending rate case filed in August 2017.

In October 2017, SPS filed a complaint against SPP regarding the amounts billed on and after November 2016 asserting that SPP has assessed upgrade charges to SPS even where SPS’ transmission service was not dependent upon the upgrade as required by the SPP OATT.  If SPS’ complaint results in additional charges or refunds, SPS will seek to recover or refund the differential in future rate proceedings. Also in October 2017, SPP made adjustments to its previous calculations of upgrade charges to SPP customers, and the impact was immaterial to SPS.