Commitments and Contingencies

Except to the extent noted below and in Note 5, Notes 10 and 11 to the financial statements in SPS’ Annual Report on Form 10-K for the year ended Dec. 31, 2014, appropriately represent, in all material respects, the current status of commitments and contingent liabilities and are incorporated herein by reference. The following include commitments, contingencies and unresolved contingencies that are material to SPS’ financial position.

Purchased Power Agreements (PPAs)

Under certain PPAs, SPS purchases power from independent power producing entities that own natural gas fueled power plants for which SPS is required to reimburse natural gas fuel costs, or to participate in tolling arrangements under which SPS procures the natural gas required to produce the energy that it purchases. These specific PPAs create a variable interest in the associated independent power producing entity.

SPS had approximately 827 megawatts (MW) of capacity under long-term PPAs as of March 31, 2015 and Dec. 31, 2014, with entities that have been determined to be variable interest entities. SPS has concluded that these entities are not required to be consolidated in its financial statements because it does not have the power to direct the activities that most significantly impact the entities’ economic performance. These agreements have expiration dates through 2033.

Environmental Contingencies

Environmental Requirements

Water and Waste
Coal Ash Regulation SPS’s operations are subject to federal and state laws that impose requirements for handling, storage, treatment, and disposal of solid waste.  On April 17, 2015, the U.S. Environmental Protection Agency (EPA) published a final rule regulating the management and disposal of coal combustion byproducts (coal ash) as a nonhazardous waste.  SPS’s costs to manage and dispose of coal ash will not significantly increase under the new rule.

Air
Cross-State Air Pollution Rule (CSAPR) — CSAPR addresses long range transport of particulate matter (PM) and ozone by requiring reductions in sulfur dioxide (SO2) and nitrous oxide (NOx) from utilities in the eastern half of the United States, including Texas, using an emissions trading program.

In August 2012, the United States District Court of Appeals for the District of Columbia Circuit (D.C. Circuit) vacated the CSAPR and remanded it back to the EPA. The D.C. Circuit stated the EPA must continue administering the Clean Air Interstate Rule (CAIR) pending adoption of a valid replacement. In April 2014, the U.S. Supreme Court reversed and remanded the case to the D.C. Circuit. The Supreme Court held that the EPA’s rule design did not violate the Clean Air Act (CAA) and that states had received adequate opportunity to develop their own plans. Because the D.C. Circuit overturned the CSAPR on two over-arching issues, there are many other issues the D.C. Circuit did not rule on that will now need to be considered on remand. An opinion is expected late summer 2015. In October 2014, the D.C. Circuit granted the EPA’s request to begin to implement CSAPR by imposing its 2012 compliance obligations starting in January 2015. While the litigation continues, the EPA will administer the CSAPR in 2015.

Multiple changes to the SPS system since 2011 will substantially reduce estimated costs of complying with the CSAPR. These include the addition of 700 MW of wind power, the construction of Jones Units 3 and 4, reduced wholesale load, new PPAs, installation of NOx combustion controls on Tolk Units 1 and 2 and completion of certain transmission projects. As a result, SPS estimates compliance with the CSAPR in 2015 will cost approximately $7 million. CSAPR compliance in 2015 is not expected to have a material impact on the results of operations, financial position or cash flows.

Regional Haze Rules — The regional haze program is designed to address widespread haze that results from emissions from a multitude of sources. In 2005, the EPA amended the best available retrofit technology (BART) requirements of its regional haze rules, which require the installation and operation of emission controls for industrial facilities emitting air pollutants that reduce visibility in certain national parks and wilderness areas. In its first regional haze state implementation plan (SIP), Texas identified the SPS facilities that will have to reduce SO2, NOx and PM emissions under BART and set emissions limits for those facilities.

Harrington Units 1 and 2 are potentially subject to BART. Texas developed a SIP that finds the CAIR equal to BART for electric generating units (EGUs). As a result, no additional controls beyond CAIR compliance would be required. In May 2012, the EPA deferred its review of the SIP in its final rule allowing states to find that CSAPR compliance meets BART requirements for EGUs. In December 2014, the EPA proposed to approve the BART portion of the SIP, with the exception that the EPA would substitute CSAPR compliance for Texas’ reliance on CAIR. The EPA currently plans to issue its final rule in August 2015.

In May 2014, the EPA issued a request for information under the CAA related to SO2 control equipment at Tolk Units 1 and 2. In December 2014, the EPA proposed to disapprove the reasonable progress portions of the SIP and instead adopt a Federal Implementation Plan. For SPS, the EPA proposed to require dry scrubbers on both Tolk units to reduce SO2 emissions to help achieve reasonable progress goals the EPA would establish for Texas and Oklahoma national parks and wilderness areas. As proposed, the dry scrubbers would need to be installed and operating within five years of the EPA’s final action, currently expected in August 2015. SPS filed comments in April 2015, opposing the proposal. Whether dry scrubbers are required is dependent on the EPA’s final decision. If required, they would cost approximately $600 million, with an annual operating cost of approximately $10.4 million.

Legal Contingencies

SPS is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss. For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on SPS’ financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.

Employment, Tort and Commercial Litigation

Exelon Wind (formerly John Deere Wind) Complaint  Several lawsuits in Texas state and federal courts and regulatory proceedings have arisen out of a dispute concerning SPS’ payments for energy and capacity produced from the Exelon Wind subsidiaries’ projects. There are two main areas of dispute. First, Exelon Wind claims that it established legally enforceable obligations (LEOs) for each of its 12 wind facilities in 2005 through 2008 that require SPS to buy power based on SPS’ forecasted avoided cost as determined in 2005 through 2008. Although SPS has refused to accept Exelon Wind’s LEOs, SPS accepts that it must take energy from Exelon Wind under SPS’ PUCT-approved Qualifying Facilities (QF) Tariff. Second, Exelon Wind has raised various challenges to SPS’ PUCT-approved QF Tariff, which became effective in August 2010. On Jan.16, 2015, Exelon Wind filed motions to dismiss or notices of non-suits for its state and federal lawsuits regarding the QF tariff, and for its state and federal lawsuits and regulatory proceedings regarding the LEOs. Later in January, the PUCT and state and federal courts issued orders dismissing the cases. On April 28, 2015, Exelon Wind filed a notice of withdrawal of its complaint regarding the LEOs, which will become effective on May 13, 2015. The only remaining proceeding is pending before the FERC, and involves the QF Tariff.

SPS believes the likelihood of loss in these proceedings is remote based primarily on existing case law and while it is not possible to estimate the amount or range of reasonably possible loss in the event of an adverse outcome, SPS believes such loss would not be material based upon its belief that it would be permitted to recover such costs, if needed, through its various fuel clause mechanisms. No accrual has been recorded for this matter.