XML 131 R58.htm IDEA: XBRL DOCUMENT v3.25.4
RATE MATTERS
12 Months Ended
Dec. 31, 2025
Regulated Operations [Abstract]  
RATE MATTERS RATE MATTERS
The disclosures in this note apply to all Registrants unless indicated otherwise.

The Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions.  Rate matters can have a material impact on net income, cash flows and possibly financial condition.  The Registrants’ recent significant rate orders and pending rate filings are addressed in this note.

AEP Texas Rate Matters (Applies to AEP and AEP Texas)

AEP Texas Interim Transmission and Distribution Rates

Through December 31, 2025, AEP Texas’ cumulative revenues from transmission and distribution interim base rate increases that are subject to review are estimated to be approximately $118 million. A base rate review could result in a refund to customers if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition.

Texas Legislation

On June 20, 2025, Texas House Bill 5247 (HB 5247) was signed into law by the Governor of Texas and became effective. The bill establishes a UTM for qualifying electric utilities to file annual interim rate adjustments for cost recovery of certain transmission and distribution capital expenditures. On June 27, 2025, AEP Texas filed with the PUCT notice of qualification and election to follow the new methodology as permitted by HB 5247. Qualifying electric utilities under HB 5247 consist of utilities that: (a) operate solely in ERCOT, (b) have been identified by the PUCT as having responsibility for constructing transmission infrastructure as part of ERCOT’s Permian Basin Reliability Plan and (c) make annual capital expenditures in transmission and distribution that exceed 300% of annual depreciation. Based on those requirements, AEP Texas is a qualifying electric utility and SWEPCo is not a qualifying electric utility.

The UTM permits a qualifying electric utility to defer all or a portion of costs associated with its eligible transmission and distribution capital investments, including depreciation expense and carrying costs, as a regulatory asset. The tracking mechanism is available through 2035 and is an alternative to the existing capital tracking mechanisms in Texas. As a result of the new legislation, AEP Texas deferred approximately $56 million of eligible costs through December 2025 as a regulatory asset.

2025 UTM Filing

In October 2025, AEP Texas submitted its first filing with the PUCT seeking recovery of eligible costs through the UTM established by HB 5247. This filing combined three recovery mechanisms (Interim Transmission Cost of Service and Distribution Cost Recovery Factor capital trackers and the Transmission Cost Recovery Factor) into a single filing. The capital tracker incremental revenue requirement, inclusive of the items outlined in the January 2026 brief, sought in this filing is $100 million, including a request to recover, over a 12-month period, $38 million of eligible costs related to UTM deferrals and $2 million of eligible costs related to the System Resiliency Plan deferrals, both inclusive of equity carrying charges through the July 2025 test year period end. In November 2025, an intervenor proposed a $31 million reduction to the UTM deferral balance. The filing is currently undergoing a paper hearing and in January 2026 the parties filed briefs reiterating their position. A resolution is expected in the first half of 2026. Investments included in the UTM and the existing capital tracker filings remain subject to prudency review in the utility’s next base rate review before the PUCT. If any of these deferred costs are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

APCo and WPCo Rate Matters (Applies to AEP and APCo)

ENEC (Expanded Net Energy Cost) Filings

In January 2024, the WVPSC issued an order resolving APCo’s and WPCo’s ( the Companies) 2021-2023 ENEC cases. In the order, the WVPSC: (a) disallowed $232 million in ENEC under-recovered costs as of February 28, 2023 ($136 million related to APCo) and (b) approved the recovery of $321 million of ENEC under-recovered costs as of February 28, 2023 ($174 million related to APCo) plus a 4% debt carrying charge rate over a ten-year recovery period starting September 1, 2024.
In February 2024, the Companies filed briefs with the West Virginia Supreme Court (WVSC) to initiate an appeal of the January 2024 order. Following arguments that were held in September 2024, the WVSC issued a November 2024 opinion affirming in part and reversing in part the WVPSC’s January 2024 ENEC order. The WVSC remanded the ENEC case to the WVPSC to afford the Companies an opportunity to examine, analyze, rebut and refute the calculation of the $232 million disallowance.

In March 2025, the WVPSC entered an order in the Companies’ 2021-2023 ENEC remand cases further describing its calculations of the ordered $232 million disallowance. In June 2025, the Companies submitted direct testimony on remand supporting a reduction to the WVPSC’s previously-ordered disallowance of at least $179 million.

In August 2025, WVPSC staff and an intervening party submitted testimony recommending the continued disallowance of $232 million of ENEC under-recovered costs as of February 28, 2023, with the intervening party recommending that the WVPSC consider a larger disallowance based on alleged imprudence of coal procurement.

A hearing on the 2021-2023 ENEC remand cases was held in October 2025. If any additional 2021-2023 ENEC costs are not recoverable or refunds are ordered, it would reduce future net income and cash flows and impact financial condition.

In April 2024, the Companies submitted their 2024 ENEC update case proposing a $58 million annual increase in ENEC rates when compared to existing ENEC rates. The Companies proposed that this ENEC rate change would: (a) become effective September 1, 2024, (b) include a $20 million annual increase in ENEC rates related to the period ending February 29, 2024 and the forecast period September 2024 through August 2025 and (c) include a $38 million annual increase in ENEC rates for the recovery of $321 million of ENEC under-recovered costs as of February 28, 2023, over a ten-year period, plus a 4% debt carrying charge rate. In August 2024, the WVPSC issued an order approving the requested $38 million annual increase effective September 1, 2024. In March 2025, the WVPSC issued an order approving the requested $20 million annual increase effective March 11, 2025.

In April 2025, the Companies submitted their 2025 ENEC update filing proposing a $72 million annual increase in ENEC rates. In September 2025, the WVPSC issued an order on the Companies’ 2025 ENEC update filing approving an annual ENEC revenue requirement increase of $70 million with no change in ENEC rates charged to customers. The WVPSC ordered this ENEC customer rate increase to occur upon securitization which is expected in the first half of 2026 as further described in the “2025 West Virginia Securitization Filing” section below. The WVPSC denied an intervenor-recommended ENEC under-recovery disallowance of $19 million.

Virginia Fuel Adjustment Clause (FAC) Review

In 2023, APCo submitted its annual fuel cost filing with the Virginia SCC. Interim Virginia FAC rates were implemented in November 2023. In APCo's 2022 Virginia fuel update filing, the Virginia SCC ordered the Virginia Staff to commence an audit of APCo’s fuel costs for the years ended December 31, 2019, 2020, 2021 and 2022. The Virginia Staff analyzed APCo’s 2019 through 2022 fuel procurement activities and concluded the procurement practices were reasonable and prudent and recommended no disallowances. In May 2024, the Virginia SCC issued an order approving the audit of APCo’s 2019 and 2020 fuel costs but concluded that the review of APCo fuel costs for 2021 and 2022 should remain open for further evaluation as part of APCo’s 2024 fuel cost filing.

In September 2024, APCo submitted its annual Virginia fuel cost filing with the Virginia SCC proposing no change in annual APCo Virginia FAC rates charged to customers for the period November 2024 through October 2025. In January 2025, an intervening party recommended a minimum fuel under-recovery disallowance of $20 million related to alleged imprudent operations of Amos and Mountaineer generating units during October 2021 and November 2021. There were no other recommended disallowances by intervenors or Virginia Staff regarding APCo’s historical period Virginia fuel under-recovery balance through October 31, 2024. Virginia Staff also recommended that the Virginia SCC close APCo’s open review periods related to 2021 and 2022 Virginia fuel costs with no cost disallowances. A hearing was held in May 2025. In June 2025, the Hearing Examiner issued a report recommending that the Virginia SCC order: (a) no change in annual APCo Virginia FAC rates for the period November 2024 through October 2025, (b) no cost disallowances for APCo’s Virginia FAC review period ending October 31, 2024 and (c) no cost disallowances for APCo’s 2021 and 2022 Virginia fuel cost review periods. In December 2025, the Virginia SCC issued an order approving the recommendations of the Hearing Examiner.
2024 West Virginia Base Rate Case

In November 2024, APCo and WPCo (the Companies) filed a request with the WVPSC for a net $251 million annual increase in base rates based upon a proposed 10.8% ROE and a proposed capital structure of 52% debt and 48% common equity. The requested net annual increase in base rates excludes the Companies’ proposed $94 million annual Modified Rate Base Cost (MRBC) surcharge update proposed to be effective in a separate proceeding and the existing $21 million annual Mitchell Base Rate Surcharge that are both proposed to be rolled into base rates upon the Companies’ anticipated 2025 change in base rates. The Companies’ proposed base rate increase includes recovery of approximately $118 million in previously deferred major storm expenses over a three-year period plus a carrying charge on the deferral balance, capital structure changes including an increase in ROE, an increase in depreciation expense related to proposed changes in depreciation rates and increased capital investments and increases in distribution and generation operation and maintenance expenses.

The Companies’ November 2024 West Virginia base rate filing also included two sets of alternative frameworks to simplify rates and customer bills and provide predictable future rate increases. The Companies’ first framework includes: (a) securitization, (b) approval of a major storm expense recovery and tracking mechanism and (c) freezing of OATT revenues in the ENEC. This framework includes securitization in a concurrent proceeding of approximately $2.4 billion of West Virginia jurisdictional assets. Securitization of those items could reduce the Companies’ combined requested increase in annual base rates to $37 million. See the “2025 West Virginia Securitization Filing” section below for additional information.

The Companies also submitted an alternative ratemaking proposal that includes: (a) a separate surcharge that would allow the Companies up to a 3% annual increase in overall West Virginia rates for four consecutive years on April 1st of each year after the implementation of base rates in this case, (b) the elimination of all of the Companies’ existing West Virginia jurisdictional surcharges except for the ENEC, with the revenues of these eliminated riders rolled into base rates and (c) the creation of a new West Virginia jurisdictional environmental and new generation surcharge. This alternative proposal would allow the Companies to submit a base rate case filing in advance of and in lieu of the annual April 1st 3% increase and would require the Companies to submit a base rate case filing at the end of the proposed four-year period.

In August 2025, the WVPSC issued an order on the Companies’ base case filing. The WVPSC’s order: (a) approved a combined annual base rate revenue requirement increase of $76 million ($67 million related to APCo) based on a 9.25% ROE and a capital structure of 56% debt and 44% equity, (b) included recovery of $24 million of previously deferred storm costs with no carrying charges, with future securitization of these deferred storm costs as described in the “2025 West Virginia Securitization Filing” section below, (c) included a decrease in the base rate revenue requirement related to a WVPSC-ordered decrease in depreciation rates, (d) required the Companies to recover the monthly level of this base rate increase through current ENEC rates, (e) effectively terminated the Companies’ MRBC, Mitchell Base Rate and Vegetation Management surcharges upon the approved change in base rates revenue requirement with these surcharges rolled into base rates, (f) stipulated that the Companies’ proposals related to the inclusion of a stand-alone NOLC deferred tax asset in rate base will be addressed in a future proceeding upon the Companies’ receipt of a PLR from the IRS and (g) approved the Companies’ requested West Virginia jurisdictional environmental and new generation surcharge but did not approve the Companies’ proposed storm tracking mechanism, annual 3% surcharge increase and freezing of OATT revenues in the ENEC. In September 2025, the Companies filed a petition for reconsideration with the WVPSC to explain the financial consequences of the order and seek clarification on certain issues.

West Virginia Modified Rate Base Cost (MRBC) Surcharge Update Filing

In March 2024, APCo and WPCo (the Companies) submitted an annual MRBC surcharge update filing with the WVPSC requesting a $32 million annual increase in the Companies’ combined MRBC rates. The MRBC is an infrastructure investment tracker that allows limited cost recovery related to capital investments between the Companies’ West Virginia jurisdictional base rate cases. WVPSC staff and an intervening party recommended revenue requirement disallowances in written and verbal testimony and briefs for certain ratemaking issues used to develop the Companies’ proposed MRBC rates, including the West Virginia jurisdictional effect of state deferred income taxes, NOLCs and AROs.

The WVPSC’s August 2025 order on the Companies’ West Virginia base case filing, as described in the “2024 West Virginia Base Rate Case” section above, approved the termination of the MRBC and the transition of MRBC rates into base rates. The WVPSC did not rule on MRBC refunds proposed by WVPSC Staff and an intervening party related to NOLCs and other issues as these issues will be addressed in a future filing. The WVPSC’s August 2025 base case order stipulated that the Companies’ proposals related to the inclusion of a stand-alone NOLC deferred tax asset in rate base will be addressed in a future proceeding upon the Companies’ receipt of a PLR from the IRS.

If any refund liabilities are imposed by the WVPSC, it could reduce future net income and cash flows and impact financial condition.
2025 West Virginia Securitization Filing

In March 2025, APCo and WPCo (the Companies) requested to finance, through the issuance of securitization bonds, approximately $2.4 billion of West Virginia jurisdictional undepreciated property balances and regulatory assets including: (a) $321 million of the Companies’ remaining combined unrecovered ENEC balances, (b) $1.7 billion of undepreciated West Virginia jurisdictional plant balances as of December 31, 2022 for the Amos, Mitchell and Mountaineer Plants, (c) $237 million of environmental costs previously approved for recovery through a separate West Virginia surcharge and (d) $118 million of West Virginia jurisdictional deferred major storm operation and maintenance costs.

In August 2025, the WVPSC issued an interim order stating that it will approve the Companies’ future securitization of the generation plant assets, ENEC under-recovery balances, environmental costs and deferred storm operation and maintenance costs.

In September 2025, and as directed by the WVPSC in the August 2025 interim order described above, the Companies submitted an updated proposed financing order that reflected additional ENEC under-recovery balances for costs incurred in 2025 and additional storm operation and maintenance deferral balances for the impacts of Hurricane Helene and winter storms Blair, Harlow and Jett. WPCo forecasted CCR and ELG amounts below related to the Mitchell Plant are subject to change based on the fourth quarter 2025 KPSC order approving the settlement agreement on KPCo’s June 2025 CPCN filing that would allow KPCo to continue taking a 50% share of energy and capacity from the Mitchell Plant to serve KPCo customers beyond December 31, 2028. See “Mitchell Plant Filing for Certificate of Public Convenience and Necessity” section below for additional information. In February 2026, WPCo requested that the WVPSC grant any additional authorizations necessary to enable WPCo to reflect the holdings and impact of the December 2025 KPSC order or make a determination that no such authorizations are required. All amounts in the table below are subject to further review in a future final securitization financing order that the Companies expect will be issued by the WVPSC in 2026. See the summarization of the proposed securitization items in the table below:

Proposed Securitized ItemsAPCoWPCoTotal
(in millions)
Undepreciated Utility Plant Balances of Amos, Mitchell and Mountaineer (as of December 31, 2022)
$1,145 $559 $1,704 
ENEC Under-Recovery Regulatory Assets 167 246 413 
Forecasted Undepreciated CCR and ELG Investments of Amos, Mitchell and Mountaineer (as of November 30, 2024)
88 149 237 
Deferred Storm Other Operation and Maintenance Expense Regulatory Assets 155 158 
Upfront Financing Costs10 16 
Total$1,565 $963 $2,528 

Upon receipt of the final financing order, the Companies expect to proceed with the securitization bonds issuance process and to complete the securitization in the first half of 2026, subject to market conditions.

If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2025 Virginia Securitization Filing

In July 2025, APCo filed a request with the Virginia SCC to finance, through the issuance of proposed 20-year securitization bonds, approximately $1.4 billion of Virginia jurisdictional undepreciated property balances and a major storm operation and maintenance regulatory asset deferral balance. This proposed securitization included: (a) $1.2 billion of undepreciated Virginia jurisdictional plant balances as of December 31, 2023 for the Amos and Mountaineer Plants and (b) $141 million of Virginia jurisdictional major storm other operation and maintenance expenses deferred during the 2024-2025 biennial period. In September 2025, Virginia SCC staff submitted testimony concluding that all costs proposed by APCo for securitization are eligible for securitization in accordance with Virginia law. While also concluding that APCo’s proposed securitization of the Amos and Mountaineer Plants over 20 years offers benefits to customers through rate relief, Virginia SCC staff took no position on APCo’s proposed securitization of major storm other operation and maintenance expenses due to the apparent lack of significant benefit or cost savings for customers. In October 2025, the Hearing Examiner recommended the Virginia SCC approve the requested $1.4 billion for securitization. In November 2025, the Virginia SCC issued a financing order approving securitization of the requested $1.4 billion of Virginia jurisdictional costs. In accordance with Virginia statutory requirements and the financing order, the issuance of the securitization bonds is subject to final review by the Virginia SCC after bond
pricing. APCo expects to proceed with the securitization bond issuance process and to complete the securitization process in the first half of 2026, subject to market conditions. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

ETT Rate Matters (Applies to AEP)

2025 ETT Base Rate Case

In January 2025, ETT filed a request with the PUCT for a $57 million annual base rate increase over its adjusted test year revenues which includes interim transmission rate updates. ETT’s request was based upon a proposed 10.6% ROE with a capital structure of 55% debt and 45% common equity. The rate case sought a prudence review determination on cumulative capital additions included in interim rates. In April and May 2025, respectively, intervenors and PUCT staff submitted testimony challenging components of the proposed rate increase including up to $37 million related to increased depreciation rates and $32 million related to the proposed ROE and capital structure.

In June 2025, a unanimous and unopposed settlement was filed with the PUCT along with a motion to approve interim rates, equal to the rates specified in the settlement, effective on June 20, 2025. The settlement terms included a base rate increase of approximately $20 million, based on an ROE of 9.6% and a capital structure of 59% debt and 41% equity. The settlement also included a determination that ETT’s invested capital and rate base are prudent and properly included in rates. The motion to approve interim rates was granted in June 2025. In October 2025, the PUCT issued an order approving the June 2025 settlement. The rates approved by the order are identical to the rates approved on an interim basis.

I&M Rate Matters (Applies to AEP and I&M)

Michigan Power Supply Cost Recovery (PSCR) Reconciliation

2023 PSCR Reconciliation

In March 2024, I&M submitted its 2023 PSCR Reconciliation to the MPSC. In October 2024, MPSC staff and intervenors submitted testimony recommending PSCR cost disallowances associated with the OVEC Inter-Company Power Agreement (ICPA) and the Rockport UPA with AEGCo ranging from $3 million to $15 million. In July 2025, the MPSC issued an order resulting in a combined $3 million PSCR cost disallowance related to OVEC and Rockport UPA costs. In July 2025, the IURC issued an order on I&M’s Resource Adequacy Rider update filing approving I&M’s proposed capacity resource adjustments, including prospective recovery of OVEC capacity, energy and associated costs that were previously assigned to I&M Michigan retail customers starting with the June 2025-May 2026 PJM delivery year.

2024 PSCR Reconciliation

In March 2025, I&M submitted its 2024 PSCR Reconciliation to the MPSC. In October 2025, MPSC staff and intervenors submitted testimony recommending PSCR cost disallowances associated with the OVEC ICPA and the Rockport UPA with AEGCo ranging from $259 thousand to $14 million. A hearing on I&M’s 2024 PSCR Reconciliation was held in December 2025 and an MPSC order is expected in the second quarter of 2026. Any future disallowances ordered by the MPSC on I&M’s 2024 PSCR Reconciliation could reduce future net income and cash flows and impact financial condition.

Indiana Earnings Test

I&M is required by Indiana law to submit an earnings test evaluation for the most recent one-year and five-year periods as part of I&M’s semi-annual Indiana FAC filings. These earnings test evaluations require I&M to include a credit in the FAC factor computation for periods in which I&M earned above its authorized return for both the one-year and five-year periods. The credit is determined as 50% of the lower of the one-year or five-year earnings above the authorized level. Management believes its financial statements adequately address the impact of Indiana earnings test requirements previously established by the IURC. If future IURC orders require that I&M provide credits in the FAC factor computation in excess of established earnings test requirements, it could reduce future net income and cash flows and impact financial condition.

In January 2025, I&M submitted its FAC filing and earnings test evaluation for the period ended November 2024. I&M proposed an over-earnings credit to customers for the earnings test period ending November 2024 of $21 million. In April 2025, the IURC issued an order approving the $21 million customer credit.
In July 2025, I&M submitted its FAC filing and earnings test evaluation for the period ended May 2025. I&M proposed an over-earnings credit to customers for the earnings test period ending May 2025 of $35 million. In October 2025, the IURC issued an order approving the $35 million customer credit.

In February 2026, I&M submitted its FAC filing and earnings test evaluation for the period ended November 2025. I&M proposed an over-earnings credit to customers for the earnings test period ending November 2025 of $53 million based on requested modifications to jurisdictional cost allocations to more accurately reflect I&M’s cost to serve Indiana retail customers. An IURC order approving I&M’s proposed jurisdictional cost allocation modifications and as-filed over-earnings credit would increase future net income and cash flows and impact financial condition.

KPCo Rate Matters (Applies to AEP)

Investigation of the Service, Rates and Facilities of KPCo

In June 2023, the KPSC issued an order directing KPCo to show cause why it should not be subject to Kentucky statutory remedies, including fines and penalties, for failure to provide adequate service in its service territory. The KPSC’s show cause order did not make any determination regarding the adequacy of KPCo’s service. In July 2023, KPCo filed a response to the show cause order demonstrating that it has provided adequate service. In December 2023 and February 2024, KPCo and certain intervenors filed testimony with the KPSC. A hearing with the KPSC was previously scheduled to occur in June 2024. The hearing was postponed and has not yet been rescheduled. If any fines or penalties are levied against KPCo relating to the show cause order, it could reduce future net income and cash flows and impact financial condition.

2023 Kentucky Base Rate and Securitization Case

In June 2023, KPCo filed a request with the KPSC for a $94 million net annual increase in base rates based upon a proposed 9.9% ROE with the increase to be implemented no earlier than January 2024. In conjunction with its June 2023 filing, KPCo further requested to finance through the issuance of securitization bonds, approximately $471 million of regulatory assets. KPCo’s proposal did not address the disposition of its 50% interest in Mitchell Plant, which will be addressed in the future. See “Mitchell Plant Filing for Certificate of Public Convenience and Necessity” section below for additional information.

In November 2023, KPCo filed an uncontested settlement agreement with the KPSC, that included an annual base rate increase of $75 million, based upon a 9.75% ROE. Settlement parties agreed that the KPSC should approve KPCo’s securitization request, and that the approximate $471 million of regulatory assets requested for securitization are comprised of prudently incurred costs.

In January 2024, the KPSC issued an order modifying the November 2023 uncontested settlement agreement and approving an annual base rate increase of $60 million based upon a 9.75% ROE effective with billing cycles starting mid-January 2024. The order reduced KPCo’s base rate revenue requirement by $14 million to allow recovery of actual test year PJM transmission costs instead of KPCo’s requested annual level of costs based on PJM 2023 projected transmission revenue requirements. In February 2024, KPCo filed an appeal with the Commonwealth of Kentucky Franklin Circuit Court (Circuit Court), challenging among other aspects of the order, the $14 million base rate revenue requirement reduction. In January 2025, the Circuit Court issued an order agreeing with KPCo’s appeal and remanded this issue back to the KPSC with instructions to enter an order, within 30 days, which includes setting rates to allow KPCo to recover the $14 million of annual PJM transmission costs effective upon KPCo's January 2024 implementation of updated base rates. In March 2025, the KPSC issued a rehearing order that approved rates for the prospective collection of test year PJM transmission costs beginning in February 2025 but denied KPCo’s request to defer and recover the historical PJM transmission costs of approximately $16 million incurred from January 2024 through the February 2025 update in base rates. In April 2025, KPCo filed an appeal with the Circuit Court for a motion to enforce in response to the KPSC’s denial to recover PJM transmission costs incurred from January 2024 through the implementation of new rates. In September 2025, the Circuit Court issued an order granting KPCo’s motion to enforce. In October 2025, the KPSC issued an order approving recovery of the $16 million of PJM transmission costs, with debt and equity carrying charges starting September 15, 2025 on the remaining PJM transmission costs to be recovered, through a rider. The rider was effective with the first billing cycle in November 2025 and will be in place for 22 months.

In June 2025, KPCo issued $478 million of securitization bonds to recover $500 million of regulatory assets, including $311 million of plant retirement costs, $79 million of deferred storm costs related to 2020, 2021, 2022 and 2023 major storms, $56 million of under-recovered purchased power rider costs, $51 million of deferred purchased power expenses and $3 million of issuance-related expenses, including KPSC advisor expenses. The net bond proceeds of $478 million also included $6 million for non-utility issuance costs and a $29 million offset for net present value of return on accumulated deferred income taxes related to KPCo’s securitized plant retirement costs as ordered by the KPSC.
Mitchell Plant Filing for Certificate of Public Convenience and Necessity

KPCo and WPCo each own a 50% undivided interest in the 1,560 MW coal-fired Mitchell Plant. In July 2021, the KPSC rejected KPCo’s ELG compliance plan for KPCo’s 50% ownership share of ELG investments at the Mitchell Plant that would allow KPCo to take capacity and energy to serve customers beyond December 31, 2028. As a result of this order, and pursuant to September 2022 resolutions under the existing Mitchell Plant Operating Agreement, WPCo funded 100% of the Mitchell Plant ELG investments that have been placed in service. In addition, WPCo also paid for a greater than 50% share of certain non-ELG capital investments made at Mitchell Plant which will continue to be used in the operation of Mitchell Plant beyond 2028.

In June 2025, KPCo filed a request with the KPSC for a CPCN to make investments necessary to reflect: (a) a 50% share of the Mitchell Plant ELG Project and (b) a 50% share of non-ELG capital investments. KPSC approval of these investments would allow KPCo to continue taking a 50% share of energy and capacity from the Mitchell Plant to serve KPCo customers beyond December 31, 2028. KPCo proposed to recover the estimated $78 million investment in the ELG Project through KPCo’s existing Environmental Surcharge and requested recovery of an estimated $60 million of Mitchell Plant non-ELG capital investments through its 2025 Kentucky Base Rate Case filing. See “2025 Kentucky Base Rate Case” section below for additional information.

In November 2025, KPCo and an intervening party submitted a settlement agreement that recommended the approval of KPCo’s proposed Mitchell Plant CPCN and use of KPCo’s Environmental Surcharge to recover Mitchell Plant ELG project costs through 2040. The settlement agreement further recommended granting KPCo authority to defer the depreciation expense and carrying costs associated with Mitchell Plant non-ELG capital investments to a regulatory asset until it can be reflected in rates. The recovery mechanism for Mitchell Plant non-ELG capital investments will be addressed in KPCo’s 2025 Kentucky Base Rate Case filing. See “2025 Kentucky Base Rate Case” section below for additional information.

In December 2025, the KPSC issued an order approving the settlement agreement, the Mitchell Plant CPCN and recovery of ELG capital investments through the Environmental Surcharge. The KPSC’s order imposes annual reporting requirements to review capital investment costs at the Mitchell Plant.

To operate in accordance with KPSC and WVPSC directives related to Mitchell Plant ELG investments, KPCo and WPCo expect to utilize existing authority under the Mitchell Plant Operating Agreement to revise billing procedures resulting in equal allocation of costs. In February 2026, WPCo requested that the WVPSC grant any additional authorizations necessary to enable WPCo to reflect the holdings and impact of the December 2025 KPSC order or make a determination that no such authorizations are required. As of December 31, 2025, the net book value of KPCo’s share of the Mitchell Plant, before cost of removal and including CWIP and inventory, and prior to the effect of revised billing procedures expected under the Mitchell Plant Operating Agreement to comply with the KPSC’s December 2025 order, was $523 million.

2025 Kentucky Base Rate Case

In August 2025, KPCo filed a request with the KPSC for a $96 million net annual increase in base rates based upon a proposed 10% ROE and a proposed capital structure of 53.9% debt and 46.1% common equity, to be implemented no earlier than March 2026. Among other changes, the filing proposed a $10 million increase in PJM transmission costs, a $9 million increase due to load loss and a $6 million increase in depreciation rates.

The proposed annual rate increase also included a $20 million annual revenue requirement related to KPCo’s investment in the Mitchell Plant. See “Mitchell Plant Filing for Certificate of Public Convenience and Necessity” section above for additional information. As part of this filing, KPCo requested a new generation rider to recover the remaining net book value of KPCo’s non-environmental investment in the Mitchell Plant that KPCo historically recovered through base rates. If the generation rider is approved, the $20 million would be removed from the requested revenue requirement increase and would be collected through the rider. Additionally, KPCo is pursuing securitization legislation that would allow KPCo to securitize the remaining net book value of the Mitchell Plant. If the securitization of the remaining Mitchell Plant net book value is successful, collection of costs through the generation rider would cease.
In January 2026, KPCo and certain intervening parties submitted a settlement agreement with the KPSC proposing a $77 million annual increase in Kentucky retail rates, including: (a) a $59 million annual increase in KPCo base rates based on a 9.8% authorized ROE and a capital structure of 53.9% debt and 46.1% common equity, and (b) a new generation rider with a first year revenue requirement of $18 million based on a 9.7% authorized ROE to recover non-environmental plant investments at Mitchell Plant and all incremental capital investments after May 31, 2025 at both Mitchell Plant and Big Sandy Plant. Capital and other operation and maintenance expenses related to any new generating assets also will be eligible for inclusion in the Generation Rider, subject to KPSC approval. The settlement revenue requirement will be reduced by $25 million in the first year and $15 million in the second year through a new rider that returns certain unprotected deferred tax expenses in customer rates on a temporary basis, and then beginning in the third year, collects the deferred tax expense amounts from customers over the estimated time period that taxes are due to the IRS. The settlement agreement also proposes: (a) approval to defer all storm other operation and maintenance expenses above or below the level included in base rates, and (b) approval to defer vegetation management costs above or below the level included in base rates, capped at a total of $45 million in 2026 and $52 million in 2027. Consistent with the KPSC order in KPCo’s 2023 Kentucky Base Rate Case filing, the settlement agreement also provides that KPCo’s proposal to include a stand-alone NOLC deferred tax asset in rate base will be addressed in a future proceeding upon KPCo’s receipt of a PLR or other guidance from the IRS. A hearing was held in January 2026.

In February 2026, an intervenor filed a brief recommending that the KPSC should deny the requested rate increase. The intervenor also stated that if the KPSC were to approve a rate increase, the settlement agreement should be modified to a $40 million annual increase in KPCo base rates based on an 8.9% ROE and a capital structure of 55% debt and 45% common equity. Additionally, the brief: (a) suggests increasing the amount of the first and second year revenue requirement reductions to $49 million and $28 million, respectively, relating to the new rider proposed in the settlement agreement that returns certain unprotected deferred tax expenses in customer rates on a temporary basis, (b) proposes that KPCo should be restricted from filing to recover Mitchell Plant non-ELG capital costs, expected to result from the approved settlement agreement in the 2025 Mitchell Plant CPCN proceeding, for a minimum of three years (see “Mitchell Plant Filing for Certificate of Public Convenience and Necessity” section above for additional information) and (c) recommends that the KPSC order an independent management audit to engage outside experts to determine how KPCo can improve its service and rates.

A KPSC order is expected to be issued in the first quarter of 2026 with implementation of KPCo retail rates in March 2026. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

OVEC Cost Recovery Audits

In December 2021, as part of OVEC cost recovery audits pending before the PUCO, intervenors filed positions claiming that costs incurred by OPCo during the 2018-2019 audit period were imprudent and should be disallowed. In May 2022, intervenors filed for rehearing on the 2016-2017 OVEC cost recovery audit period claiming the PUCO’s April 2022 order to adopt the findings of the audit report were unjust, unlawful and unreasonable for multiple reasons, including the position that OPCo recovered imprudently incurred costs. In May 2023, as part of the OVEC cost recovery audits pending before the PUCO, intervenors filed positions claiming that costs incurred by OPCo during the 2020 audit period were imprudent and should be disallowed.

In August 2024, the PUCO issued orders pertaining to the OVEC cost recovery audits that: (a) denied intervenors’ application for rehearing on the 2016-2017 audit period, (b) determined costs incurred by OPCo during the 2018-2019 audit period were prudent, (c) determined costs incurred by OPCo during the 2020 audit period were prudent and (d) recommended no disallowances for any mentioned audit period in question. In September 2024, intervenors filed for rehearing on the 2018-2019 and 2020 OVEC cost recovery audit periods claiming the PUCO’s August 2024 orders to adopt the findings of the audit reports were unjust, unlawful and unreasonable for multiple reasons, including the position that OPCo recovered imprudently incurred costs. In October 2024, the PUCO denied the intervenors’ applications for rehearing of the 2018-2019 and 2020 audit periods. In December 2024, intervenors filed appeals with the Supreme Court of Ohio on the PUCO’s denial for rehearing. Oral arguments were conducted in December 2025 and the appeals are now fully submitted for decision.

In February and March 2025, as part of OVEC cost recovery audits pending before the PUCO, intervenors filed positions claiming that costs incurred by OPCo during the 2021-2023 audit period were imprudent and should be disallowed. Management disagrees with these claims and is unable to predict the impact of these disputes. An evidentiary hearing was held in November 2025 and post-hearing briefs were submitted in February 2026. If any costs are disallowed or refunds are ordered, it could reduce future net income and cash flows and impact financial condition.
Ohio Legislation (HB 15)

Ohio House Bill 15 (HB 15) was approved by the Ohio legislature in April 2025 and signed into law by the Governor of Ohio in May 2025. HB 15 became effective beginning August 14, 2025 and (a) alters rate-setting mechanisms by replacing ESPs with triennial base rate cases based on a three-year forecasted test period, effective with the end of OPCo’s previously approved ESP which ends in May 2028, (b) eliminates OPCo’s ability to recover from, or refund to, customers the difference between purchased power expenses from OVEC and the market revenues OPCo receives from that purchased power as of the effective date of the law and (c) repeals the statute that permits electric distribution utilities, including OPCo, to execute contracts to provide customer-sited renewable generation service such as fuel cell technology or other renewable resources prospectively.

As a result of this legislation, OPCo recorded a $24 million reduction in 2025 to its OVEC-related purchased power regulatory asset for deferred net costs that are no longer probable of future recovery. Management is unable to predict the future impact to net income, cash flows and financial condition arising from the future changes in OPCo’s rate setting mechanisms and the elimination of OPCo’s ability to recover from, or refund to, customers the difference between purchased power expenses from OVEC and the market revenues OPCo receives from that purchased power. See “OVEC” section of Note 18 for additional information.

2025 Ohio Base Rate Case

In May 2025, OPCo filed a request with the PUCO for a net $97 million annual increase in distribution base rates based upon a 10.9% ROE and a proposed capital structure of 49.1% debt and 50.9% common equity. The requested net annual increase in base rates excluded $308 million of existing annual rider revenue requirements (including the DIR) that OPCo proposed to be rolled into base rates upon the anticipated 2026 change in distribution base rates in this filing. The distribution base case filing also requests a revenue cap increase for the DIR and cost cap increase for OPCo’s existing Enhanced Service Reliability Rider (ESRR).

In October 2025, the PUCO staff filed its required report recommending a net annual decrease in distribution base rates ranging from $12 million to $28 million, based upon an ROE range of 9.33% to 9.84%. The PUCO staff recommended the exclusion of $59 million of certain utility investments and $55 million of capitalized incentives from rate base, and a reduction in employee-related expenses of $23 million. In addition, the PUCO staff recommended increases to the DIR revenue cap and ESRR cost cap that were less than OPCo’s requested increases. Responses to the PUCO staff report were submitted in November 2025 and a hearing was held in January 2026.

In January 2026, OPCo, the PUCO staff, and certain intervenors filed a settlement agreement with the PUCO. After incorporating reductions to rider rates, the settlement reflects an annual net revenue increase of $11 million based upon a 9.84% ROE while also securing a reduction in customer rates through the amortization of $82 million of deferred tax regulatory liabilities over 18 months, an item not included in the original application. The resulting overall annual revenue impact is a net decrease of $59 million. The difference between OPCo’s requested annual base rate increase and the settlement is primarily due to a reduction in the requested ROE and the resolution of various rate base and operating income issues raised in the PUCO staff report. Additionally, the agreement proposes increased revenue caps for the DIR, annual cost cap increases in the ESRR and would result in no material disallowances.

If the settlement agreement is approved by the PUCO, new base rates will go into effect 14 days after such approval. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2024 Oklahoma Base Rate Case

In January 2024, PSO filed a request with the OCC for a $218 million annual base rate increase based upon a 10.8% ROE with a capital structure of 48.9% debt and 51.1% common equity. PSO requested an expanded transmission cost recovery rider and a mechanism to recover generation costs necessary to comply with SPP’s 2023 increased capacity planning reserve margin requirements. PSO’s request includes the 155 MW Rock Falls Wind Facility and reflects recovery of Northeastern Plant, Unit 3 through 2040.

In October 2024, PSO, the OCC and certain intervenors filed a joint stipulation and settlement agreement with the OCC that included a net annual revenue increase of $120 million based upon a 9.5% ROE with a capital structure of 48.9% debt and 51.1% common equity. The agreement also allows for Rock Falls Wind Facility to be included in base rates and the deferral of certain generation-related costs necessary to comply with SPP’s 2023 increased capacity reserve margin requirements. One
intervenor opposed the joint stipulation and settlement agreement. In October 2024, a hearing was held at the OCC, and PSO implemented an interim annual base rate increase of $120 million, subject to refund pending a final order by the OCC.

In January 2025, the OCC issued a final order approving the joint stipulation and settlement agreement without modification. In February 2025, an Oklahoma state representative filed an appeal of the final order in PSO’s base rate case. The appeal does not contest the reasonableness of the rates established under the joint stipulation and settlement agreement approved without modification in the final order, but rather raises issues related to one OCC commissioner’s participation in voting on the order and the sufficiency of an OCC audit. If the appeal is successful and the OCC modifies the final order in a future proceeding, it could reduce future net income and cash flows and impact financial condition.

2026 Oklahoma Base Rate Case

In January 2026, PSO filed a request with the OCC for a $299 million annual base rate increase based upon a 10.5% ROE with a capital structure of 50.1% debt and 49.9% common equity, net of existing rider revenue and certain incremental renewable facility benefits expected to be provided to customers through riders. PSO also requested an expanded transmission cost recovery rider and a new vegetation management rider. Further, PSO is seeking approval of new large load special terms and conditions in the Large Power and Light tariff. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2020 Texas Base Rate Case

In October 2020, SWEPCo filed a request with the PUCT for a $105 million annual increase in Texas base rates based upon a proposed 10.35% ROE. The request would move transmission and distribution interim revenues recovered through riders into base rates. Eliminating these riders would result in a net annual requested base rate increase of $90 million primarily due to increased investments. SWEPCo subsequently filed a request with the PUCT lowering the requested annual increase in Texas base rates to $100 million which would result in an $85 million net annual base rate increase after moving the proposed riders to rate base.

In January 2022, the PUCT issued a final order approving an annual revenue increase of $39 million based upon a 9.25% ROE. The order also includes: (a) rates implemented retroactively back to March 18, 2021, (b) $5 million of the proposed increase related to vegetation management, (c) $2 million annually to establish a storm catastrophe reserve and (d) the creation of a rider to recover the Dolet Hills Power Station as if it were in rate base until its retirement at the end of 2021 and starting in 2022 the remaining net book value to be recovered as a regulatory asset through 2046. As a result of the final order, SWEPCo recorded a disallowance of $12 million in 2021 associated with the lack of return on the Dolet Hills Power Station. In February 2022, SWEPCo filed a motion for rehearing with the PUCT challenging several errors in the order, which include challenges of the approved ROE, the denial of a reasonable return or carrying costs on the Dolet Hills Power Station and the calculation of the Texas jurisdictional share of the storm catastrophe reserve. In April 2022, the PUCT denied the motion for rehearing. In May 2022, SWEPCo filed a petition for review with the Texas District Court seeking a judicial review of the several errors challenged in the PUCT’s final order.

2025 Arkansas Base Rate Case

In March 2025, SWEPCo filed a request with the APSC for a $114 million annual base rate increase based upon a 10.9% ROE with a capital structure of 52.3% debt and 47.7% common equity. The increase includes the Arkansas jurisdictional share of Diversion and Wagon Wheel wind facilities. SWEPCo is also electing to have its rates regulated under a Formula Rate Review mechanism.

In November 2025, an uncontested settlement agreement was filed with the APSC for an $85 million annual base rate increase based upon a 9.65% ROE with a capital structure of 55.7% debt and 44.3% common equity. The settlement agreement allowed SWEPCo to recover the Arkansas jurisdictional share of the remaining net book value of the Pirkey Plant over 10 years and earn a return of 3%, and the agreement also included a provision that the retirement of the Pirkey Plant was prudent. In January 2026, the APSC issued an order approving the settlement agreement as filed.
2025 Texas Base Rate Case

In October 2025, SWEPCo filed a request with the PUCT for a $164 million annual increase in Texas base rates based upon a 10.75% ROE and a proposed capital structure of 48% debt and 52% common equity. The request would move certain revenues recovered through riders, including interim revenues on transmission and distribution investment since the 2020 Texas Base Rate Case, into base rates resulting in a net annual rate increase of $95 million. The proposed net annual increase includes recovery of the Texas jurisdictional share of the retired Pirkey Plant through depreciation expense and requests $21 million annually to recover deferred storm costs and expand the utility’s self-insurance reserve for potential losses and damages. Intervenor and staff testimony is due in March 2026 and a hearing is scheduled for April 2026. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

PSO and SWEPCo Rate Matters (Applies to AEP, PSO and SWEPCo)

North Central Wind Energy Facilities (NCWF)

The NCWF are subject to various regulatory performance requirements, including a Net Capacity Factor (NCF) guarantee. The NCF guarantee measures in MWhs across all facilities on a combined basis for each five year period for the first thirty full years of operation. The first NCF guarantee five year period began in April 2022. Certain wind turbines experienced performance issues that prompted PSO and SWEPCo to file a lawsuit against the manufacturer, which led to an agreement between PSO and SWEPCo and the manufacturer that addressed the performance issues. If regulatory performance requirements, such as the NCF guarantee, are not met, PSO and SWEPCo may recognize a regulatory liability associated with a refund to retail customers.

FERC Rate Matters

Independence Energy Connection Project (Applies to AEP)

In 2016, PJM approved the Independence Energy Connection Project (IEC) and included it in its Regional Transmission Expansion Plan to alleviate congestion. Transource Energy has an ownership interest in the IEC, which is located in Maryland and Pennsylvania. In June 2020, the Maryland Public Service Commission approved a CPCN to construct the portion of the IEC in Maryland. In May 2021, the Pennsylvania Public Utility Commission (PAPUC) denied the IEC certificate for siting and construction of the portion in Pennsylvania. Transource Energy appealed the PAPUC ruling in Pennsylvania state court and challenged the ruling before the United States District Court for the Middle District of Pennsylvania. In May 2022, the Pennsylvania state court issued an order affirming the PAPUC decision as to state law claims. In December 2023, the United States District Court for the Middle District of Pennsylvania granted summary judgment in favor of Transource Energy, finding that the PAPUC decision violated federal law and the United States Constitution. In January 2024, the PAPUC filed an appeal of the district court’s grant of summary judgment with the United States Court of Appeals for the Third Circuit. In September 2025, the United States Court of Appeals for the Third Circuit affirmed the December 2023 district court order in favor of Transource Energy. In October 2025, the Maryland Public Service Commission approved an extension of the construction commencement deadline to May 2026. Additional regulatory proceedings before the PAPUC are expected to resume in 2026.

In September 2021, PJM notified Transource Energy that the IEC was suspended to allow for the regulatory and related appeals process to proceed in an orderly manner without breaching milestone dates in the project agreement. At that time, PJM stated that the IEC had not been canceled and remained necessary to alleviate congestion. In July 2025, PJM removed the IEC from suspended status and indicated the project going forward will be included in PJM’s models with a modified scope. PJM continues to evaluate reliability and market efficiency in the area. As of December 31, 2025, AEP’s share of IEC capital expenditures was approximately $92 million, located in Total Property, Plant and Equipment - Net on AEP’s balance sheets. The FERC has previously granted abandonment benefits for this project, allowing the full recovery of prudently incurred costs if the project is canceled for reasons outside the control of Transource Energy. If any of the IEC costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.
FERC 2021 PJM and SPP Transmission Formula Rate Challenge (Applies to all Registrant Subsidiaries except AEP Texas)

The Registrants transitioned to stand-alone treatment of NOLCs in their PJM and SPP transmission formula rates beginning with the 2022 projected transmission revenue requirements and 2021 true-up to actual transmission revenue requirements, and provided notice of this change in informational filings made with the FERC. The annual revenue requirement increase as a result of the transition to stand-alone treatment of NOLCs for transmission formula rates is shown in the table below:

20212022202320242025Total
(in millions)
$78 $68 $61 $52 $49 $308 

In January 2024, the FERC issued two orders granting formal challenges by certain unaffiliated customers related to stand-alone treatment of NOLCs in the 2021 Transmission Formula Rates of the AEP transmission owning subsidiaries within PJM and SPP. The FERC directed the AEP transmission owning subsidiaries within PJM and SPP to provide refunds with interest on all amounts collected for the 2021 rate year, and for such refunds to be reflected in the annual update for the next rate year. Accordingly, AEP transmission owning subsidiaries within PJM and SPP are providing refunds for the 2021 rate year, primarily through 2025 projected transmission revenue requirements. AEP transmission owning subsidiaries within PJM and SPP have not been directed to make cash refunds related to 2022 through 2025 rate years. As a result of the January 2024 FERC orders, the Registrants’ balance sheets reflected a liability for the probable refund of all NOLC revenues included in transmission formula rates, with interest.

In February 2024, AEPSC on behalf of the AEP transmission owning subsidiaries within PJM and SPP filed requests for rehearing. In March 2024, the FERC denied AEPSC’s requests for rehearing of the January 2024 orders by operation of law and stated it may address the requests for rehearing in future orders. In March 2024, AEPSC submitted refund compliance reports to the FERC, which preserve the non-finality of the FERC’s January 2024 orders pending further proceedings on rehearing and appeal. In April 2024, AEPSC made filings with the FERC which requested that the FERC: (a) reopen the record so that the FERC may take the IRS PLRs received in April 2024 regarding the treatment of stand-alone NOLCs in ratemaking into evidence and consider them in substantive orders on rehearing and (b) stay its January 2024 orders and related compliance filings and refunds to provide time for consideration of the April 2024 IRS PLRs. In May 2024, AEPSC filed a petition for review with the United States Court of Appeals for the District of Columbia Circuit seeking review of the FERC’s January 2024 and March 2024 decisions. In July 2024, the FERC issued orders approving AEPSC’s request to reopen the record for the limited purpose of accepting into the record the IRS PLRs and establish additional briefing procedures. In August 2024, AEPSC filed briefs with the FERC requesting the commission modify or overturn its initial orders.

In June 2025, the FERC issued two orders, partially reversing its January 2024 decisions on the basis of IRS PLRs accepted into the record, and concluding that the accelerated depreciation-related NOLC adjustments should be included in rate base and should also be included in the computation of Excess ADIT regulatory liabilities to be refunded to customers. Requests for rehearing were filed by intervenors in July 2025 and were rejected by FERC on the merits in November 2025. Intervenors have filed petitions for review of the FERC’s orders in this matter with the United States Court of Appeals for the District of Columbia Circuit. The appeals have been consolidated and are pending the establishment of a procedural schedule.

As directed by the FERC in its June 2025 order, AEP transmission owning subsidiaries within PJM and SPP submitted compliance filings in August 2025 that revised the March 2024 refund compliance reports and permit the collection of excess refunds provided to customers, with interest, in the annual update for the 2025 rate year. In October 2025, intervenors filed comments in response to the compliance filings, which remain pending before the FERC.
As a result of the June 2025 FERC orders, the Registrants recognized revenues, with interest, attributable to accelerated depreciation-related NOLCs included in transmission formula rates for years 2021 through 2025 and reduced Excess ADIT regulatory liabilities. Increases in affiliated transmission expense, which correspond to affiliated transmission revenues recognized, were deferred as an increase to regulatory assets or a reduction to regulatory liabilities on the balance sheets where management expects that expense would be collected from retail customers through authorized retail jurisdiction rider mechanisms. The table below summarizes the impact to the statements of income recorded by the Registrants in the second quarter of 2025:

AEPAEPTCoAPCoI&MOPCoPSOSWEPCo
(in millions)
Total Revenues$270 $214 $$11 $— $$27 
Purchased Electricity, Fuel and Other Consumables Used for Electric Generation(24)— (17)— — — — 
Other Operation53 — 15 (6)— 19 10 
Income (Loss) Before Income Tax Expense (Benefit)241 214 17 — (13)17 
Income Tax Expense (Benefit)(313)(203)(21)(28)— (16)(39)
Net Income554 417 29 45 — 56 
Net Income Attributable to Noncontrolling Interest55 55 — — — — — 
Earnings Attributable to Common Shareholder$499 $362 $29 $45 $— $$56 

Request to Update SWEPCo Generation Depreciation Rates (Applies to AEP and SWEPCo)

In October 2023, SWEPCo filed an application to revise its generation wholesale customer’s contracts to reflect an increase in the annual revenue requirement of approximately $5 million for updated depreciation rates and allow for the return on and of FERC customers jurisdictional share of regulatory assets associated with retired plants. In November 2023, certain intervenors filed a motion with the FERC protesting and recommending the rejection of SWEPCo’s filings. In December 2023, the FERC issued an order approving the proposed rates effective January 1, 2024, subject to further review and refund and established hearing and settlement proceedings. In October 2025, a settlement agreement was filed with the FERC. In November 2025, the settlement judge certified the settlement agreement to the FERC as an uncontested settlement. In January 2026, the FERC issued an order approving the settlement agreement. The order did not have a material impact on SWEPCo’s financial condition, results of operations or cash flows.

Transmission Agreement Cost Allocation Complaint (Applies to AEP, APCo, I&M and OPCo)

In March 2025, the KPSC and the Attorney General of Kentucky filed a complaint at the FERC against AEPSC and the AEP East Companies challenging the manner in which costs are allocated for local transmission projects pursuant to the TA. The complaint contends that certain costs allocated to KPCo are unjust, unreasonable and provide no benefit to KPCo customers. The relief requested in the complaint includes requiring a revision to the TA so that the costs for local transmission projects remain exclusively with the retail distribution service territory where the project is located unless a specific project is granted approval to establish a different cost allocation by the state commissions. Various parties have filed comments and motions to intervene. In May 2025, AEP filed a motion to dismiss and answered the complaint. In November 2025, the FERC issued an order denying the KPSC and Attorney General of Kentucky complaint. In December 2025, the KPSC and Attorney General of Kentucky requested a rehearing of the November order denying the complaint. In January 2026, the FERC issued a notice of denial of the request for rehearing by operation of law, providing the FERC with additional time to consider and decide on the merits of the request. In February 2026, the KPSC and Attorney General of Kentucky filed a petition for review of the FERC’s orders in this matter with the United States Court of Appeals for the Sixth Circuit. If the FERC orders a change in the way costs are allocated pursuant to the TA it could impact future net income, cash flows and financial condition.

FERC Audit (Applies to AEP and SWEPCo)

SWEPCo is currently under audit by FERC’s Division of Audits and Accounting. The audit is evaluating SWEPCo’s compliance with certain accounting and reporting requirements under various FERC regulations, including compliance with the approved terms, rates, and conditions of its SPP transmission formula rate mechanism. Management is unable to predict the outcome of the audit. If any refund liabilities are imposed by the FERC or any disallowances occur, it would reduce future net income and cash flows and impact financial condition.