The Company has contractual obligations and commitments primarily with regard to future purchases of aircraft, repayment of debt (see Note 6), and lease arrangements (see Note 7). During the year ended December 31, 2024, the Company entered into supplemental agreements with Boeing relating to its contractual order book for -7 and -8 aircraft. The Company's contractual order book with Boeing for -7 and -8 aircraft, which extends to 2031, was designed to support the Company's growth and fleet modernization plans, while also providing significant flexibility and optionality to manage its fleet gauge and size, including opportunities to accelerate fleet modernization efforts if growth opportunities do not materialize. The Company received 22 -8 aircraft deliveries from Boeing in 2024 and retired 34 -700 aircraft and 2 Boeing 737-800 ("-800") aircraft. In addition, during fourth quarter 2024, the Company exercised eight -7 options for delivery in 2025 and five -7 options for delivery in 2026.

Boeing continues to experience delays in fulfilling its commitments with regards to delivery of MAX aircraft to the Company, as a result of manufacturing and labor challenges, and delays in achieving FAA certification of one of its new aircraft types, the -7, for which Southwest expects to be the launch customer. During 2024, as a result of Boeing's ongoing delivery delays, the Company conservatively re-planned its capacity and delivery expectations for 2025. The Company will continue to closely monitor the ongoing aircraft delivery delays with Boeing and adjust expectations as needed.

Based on the Company's current agreement with Boeing, capital commitments associated with its firm orders as of December 31, 2024, were:
(in billions)202520262027202820292030 and thereafterTotal
Payments for capital commitments$3.4 (a)$2.0 $2.5 $2.8 $2.5 $2.8 $16.0 
(a) Capital commitments associated with the Company's firm orders in 2025 of $3.4 billion include approximately $2.1 billion primarily related to the existing scheduled 73 MAX aircraft to be delivered in 2025 and $1.3 billion related to 63 MAX aircraft (27 -7s and 36 -8s) that were contractually committed for 2024, but were not received.

Los Angeles International Airport
In April 2023, the Company executed a lease agreement with Los Angeles World Airports ("LAWA"), which owns and operates Los Angeles International Airport ("LAX"), for the ground lease and construction of a new concourse. In this agreement, the Company will manage the development, design, financing, and construction of nine new gates, along with additional features, at LAX. Construction of the concourse is estimated to not exceed $2.3 billion. During 2024, leadership met with LAWA and agreed to pause the project, with plans to restart it in 2026. The Company expects to commence construction in 2028 with construction to be completed in 2032.

Funding for this project will flow through a credit facility and the outstanding loans are expected to be paid off directly by LAWA to the credit facility at project completion, thus reimbursing the Company on all costs drawn on the credit facility. As of December 31, 2024, the credit facility has yet to be put into place and is expected to be established closer to the beginning of construction in 2028. The Company is expected to be reimbursed by the credit facility on prior payments made once in place.

Based on this agreement, the Company has determined that it does have control over the assets during this project for accounting purposes. As a result, the costs incurred to fund this project thus far, which totaled $88 million as of December 31, 2024, are included within Assets constructed for others on the accompanying Consolidated Balance Sheet.

William P. Hobby Airport

In March 2022, the Company executed a Memorandum of Agreement ("MOA") with the City of Houston, Texas (the "City") which owns William P. Hobby Airport ("Hobby") that is managed and operated by the City's Houston Airport System. Under the MOA, the Company will manage the development, design, and construction of seven new gates in Hobby's West Concourse.

The project is currently estimated to be completed in 2027 at a cost of at least $470 million. The Company is providing initial funding for the majority of the project, but is being reimbursed for such funding from the City on a monthly basis and therefore the project has not and is not expected to significantly impact the Company’s liquidity. The City plans to fund these reimbursements utilizing rates and charges collected from current and future Hobby occupants, including the Company.

Based on the MOA, as well as a terminal lease amendment expected to be finalized prior to the beginning of significant construction, the Company has determined that it does not control the assets during the construction period for accounting purposes, and thus will record the amounts funded for the project as a receivable until reimbursed by the City, and the balance is derecognized. There were no material amounts recorded in the accompanying Consolidated Balance Sheet as of December 31, 2024.

Dallas Love Field

During 2008, the City of Dallas approved the Love Field Modernization Project ("LFMP"), a project to reconstruct Dallas Love Field with modern, convenient air travel facilities. Pursuant to a Program Development Agreement with the City of Dallas and the Love Field Airport Modernization Corporation (or the "LFAMC," a Texas non-profit "local government corporation" established by the City of Dallas to act on the City of Dallas' behalf to facilitate the development of the LFMP), the Company managed this project. Major construction was effectively completed in 2014. During second quarter 2017, the City of Dallas approved using the remaining bond funds for additional terminal construction projects, which were effectively completed in 2018.

Although the City of Dallas received commitments from various sources that helped to fund portions of the LFMP project, including the FAA, the Transportation Security Administration, and the City of Dallas' Aviation Fund, the majority of the funds used were from the issuance of bonds. The Company guaranteed principal and interest payments on bonds issued by the LFAMC, of which only the "Series 2012" bonds remain outstanding. Given the Company’s guarantee associated with the Series 2012 bonds, the remaining debt service amount is considered a minimum lease payment under ASC Topic 842, Leases, and therefore remains a lease liability with a corresponding right-of-use asset within the Company’s Consolidated Balance Sheet.
As of December 31, 2024, $49 million of principal remained outstanding associated with the Series 2012 bonds. The net present values of the future principal and interest payments associated with the bonds were $52 million and $65 million as of December 31, 2024 and 2023, respectively, and were reflected as part of the Company's operating lease right–of–use assets and lease obligations in the Consolidated Balance Sheet.

Contingencies

The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business and records a liability for such claims when it is probable that a loss will be incurred and the amount is reasonably estimable.

The Company is a defendant in class action litigation asserting it has not provided paid short-term military leave to certain employees, in violation of the federal Uniformed Services Employment and Reemployment Rights Act (“USERRA”). The United States District Court for the Northern District of California previously issued an order to effectively stay the action, pending an appeal from an order by the United States District Court for the Eastern District of Washington granting summary judgment in favor of an airline in a separate case involving substantially the same claims at issue in this action. On February 1, 2023, the Ninth Circuit reversed the district court’s grant of summary judgment and remanded the separate airline case to the District Court. The Ninth Circuit’s decision may adversely affect the Company’s defenses in the USERRA proceeding and may give rise to additional litigation in this or other areas. On October 29, 2024, the Company filed a motion to decertify the class. The motion is fully briefed and a hearing on the motion is set for February 27, 2025. The Court has set a trial date of September 11, 2025. The Company is currently not able to estimate a range of possible loss with regards to the litigation to which it is a defendant.