Airport Project        
ACFO   $ 164 $ 1,768  
Assets constructed for others, net [1]   164 1,637  
Depreciation and amortization   1,219 1,201 $ 1,218
Construction obligation   164 1,701  
FLL Terminal        
Airport Project        
ACFO   0 313  
Assets constructed for others, net [1]   0 304  
Construction obligation   0 308  
LAX Terminal 1        
Airport Project        
ACFO   0 485  
Assets constructed for others, net [1]   0 459  
Construction obligation   0 476  
LAX Terminal 1.5        
Airport Project        
Expected total airport modernization project cost   479    
Contractual Obligation   176    
ACFO [2]   164 99  
Assets constructed for others, net [1],[2]   164 99  
Construction obligation [2]   164 99  
LFMP Terminal        
Airport Project        
Municipal bonds issued $ 456      
Municipal Bonds Principal Remaining   407    
ACFO   0 545  
Assets constructed for others, net [1]   0 460  
Construction obligation   0 502  
Net Present Value of Principal Remaining   444    
LFMP Parking Garage        
Airport Project        
ACFO   0 200  
Assets constructed for others, net [1]   0 200  
Construction obligation   0 200  
HOU International Terminal        
Airport Project        
ACFO [3]   0 126  
Assets constructed for others, net [1],[3]   0 115  
Construction obligation [3]   $ 0 $ 116  
[1] Net of accumulated depreciation.
[2] Project still in progress.
[3] Project completed in 2015 at Houston William P. Hobby Airport ("HOU").