Unconsolidated Joint Ventures
6 Months Ended
Jun. 30, 2019
Equity Method Investments and Joint Ventures [Abstract]  
Unconsolidated Joint Ventures Unconsolidated Joint Ventures
Liberty Property 18th & Arch LP and Liberty Property 18th & Arch Hotel, LP
On June 30, 2014, the Company entered into two joint ventures for the purpose of developing and owning the Comcast Technology Center (the “Project”) located in Philadelphia, Pennsylvania as part of a mixed-use development. The 60-story building includes 1.3 million square feet of leasable office space (the “Office”), which is substantially complete and fully occupied by Comcast Corporation, and a 219-room Four Seasons Hotel (the “Hotel”), which is nearing substantial completion and is scheduled to open to the public in August 2019. Costs for the development of the Project, exclusive of tenant-funded interior improvements, are anticipated to be approximately $968 million. As of June 30, 2019, the Company's investment in the project is $193.5 million and is reflected in investments in and advances to unconsolidated joint ventures in the Company's consolidated balance sheet. These joint ventures are part of the Company's Philadelphia reportable segment.
The two joint ventures engaged the Company as the developer of the Project pursuant to a Development Agreement by which the Company agreed, in consideration for a development fee, to be responsible for all aspects of the development of the Project and to guarantee the timely lien-free completion of construction of the Project as well as the payment, subject to certain exceptions, of any cost overruns incurred in the development of the Project. To mitigate its risk, the Company entered into guaranteed maximum price contracts (the "GMP Contracts") with a third party contractor (the "General Contractor") to construct the Project. The Company has been notified by the General Contractor that the General Contractor has incurred cost overruns comprised of amounts owed to third-party subcontractors and internal general condition costs of the General Contractor in connection with completing the Project in excess of the guaranteed maximum price payable to the General Contractor under the GMP Contracts, which guaranteed maximum price has been previously adjusted pursuant to accepted change orders. Notwithstanding the GMP Contracts, the General Contractor has generally refused to fund the cost overruns owed to third-party subcontractors, and the Company has funded, and may continue to fund, subcontractor cost overruns in compliance with its obligations under its development cost guarantee to the joint ventures. Accordingly, in periods prior to 2019, the Company accrued $69.3 million relating primarily to cost overruns that it estimated were probable of being funded to third-party subcontractors under its development cost guarantees to the joint ventures. As of June 30, 2019 and December 31, 2018, the Company's remaining accrual was $34.8 million and $67.3 million, respectively (including, in each case, estimated retainage of approximately $24 million payable to subcontractors), which accruals are included in other liabilities in the accompanying consolidated balance sheets and are reflective of amounts cumulatively funded by the Company as of those dates. The Company is accounting for the development of the Project on a variable basis as a percentage of costs incurred under the development contract. The Company recognized a loss of $60.0 million and $61.8 million for the three and six months ended June 30, 2018, respectively, in development service fee income, net of development service fee expense and other related expenses. There was no loss or gain recognized related to the Project during the three and six months ended June 30, 2019. The Company intends to pursue all remedies to recover from the General Contractor any amounts expended by the Company or the joint ventures in excess of their contractual obligations.
In addition to the costs to comply with the Company's obligations under its development cost guarantee, other claims related to the development of the Project have been asserted by the General Contractor and certain subcontractors. Should disputes with respect to these asserted claims proceed, the Company expects that it would assert claims against the General Contractor, both with respect to the claims as to which the above-described accrual has been made, as well as with respect to the additional claims described in this paragraph. There can be no assurances that amounts incurred, including as a result of such claims, will not exceed the above estimates. The Company is not able to reasonably estimate the amount of additional costs, if any, that it may incur as a result of such claims, and accordingly any potential exposure of the Company for such claims is not included within the accrual described above. Similarly, the Company is not able to reasonably estimate the amount, if any, that the Company may recover with respect to any claims it may assert against the General Contractor. If the Company were to incur additional expenses in connection with its development cost guarantee or in connection with such claims, such amounts would be accrued when they are determined to be probable of being incurred and are reasonably estimable, and could be material to the Company's results of operations in future periods. If the Company were to subsequently recover any of the cost overruns initially funded by the Company, whether pursuant to any such claims asserted by the Company or otherwise, such recoveries would be recorded when and if realized in future periods.
Liberty Washington, LP

During the three months ended June 30, 2019, the Company concluded that a property owned by this joint venture and held for sale had an indicator of impairment resulting from a decline in the Washington, DC market fundamentals. The joint venture recognized an impairment charge of $16.4 million for the three and six months ended June 30, 2019. The Company's share of this impairment charges was $4.1 million for the same periods. The impairment charge is related to the Company's DC Metro reportable segment and the Company's share is included in equity in earnings of unconsolidated joint ventures in the accompanying consolidated statements of comprehensive income. The Company determined these impairments based on estimated future discounted cash flows. This is a Level 3 fair value calculation.
Cambridge Medipark Ltd
During the three and six months ended June 30, 2019, Cambridge Medipark, Ltd (a joint venture in which the Company holds a 50% interest) recognized gains on the sale of land leasehold interests. The Company's share of these gains was $244,000 and $1.0 million for the three and six months ended June 30, 2019, respectively, compared to $1.7 million and $3.7 million, respectively, for the same periods in 2018.