XML 212 R167.htm IDEA: XBRL DOCUMENT v3.25.4
COMMITMENTS, CONTINGENCIES AND GUARANTEES - CONTRACTUAL COMMITMENTS (Details) - USD ($)
$ in Millions
12 Months Ended
Dec. 31, 2025
Dec. 31, 2024
Dec. 31, 2023
Various Capital Projects In Progress      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 $ 126    
2027 18    
2028 15    
2029 13    
2030 2    
Thereafter 26    
Total minimum payments 200    
SoCalGas | Information Technology Software Project      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2027 5    
2028 5    
2029 6    
Total minimum payments 16    
Transportation | SoCalGas      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 94    
2027 78    
2028 72    
2029 60    
2030 57    
Thereafter 66    
Total minimum payments 427    
Natural Gas Contracts      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Payments 1,284 $ 1,185 $ 4,030
Natural Gas Contracts | SoCalGas      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Payments 1,192 1,088 3,857
Storage and Transportation | Disposal Group Held-for-sale | SI Partners      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 99    
2027 100    
2028 86    
2029 221    
2030 263    
Thereafter 4,454    
Liquefied Natural Gas Contracts | Sempra Infrastructure      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 389    
2027 569    
2028 553    
2029 348    
Total minimum payments 1,859    
Payments 7 23 30
Purchased-Power Agreements      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Payments 312 326 325
Purchased-Power Agreements | SDG&E      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 113    
2027 117    
2028 122    
2029 123    
2030 123    
Thereafter 744    
Total minimum payments 1,342    
Payments 312 $ 326 $ 325
Variable payments, year one 79    
Variable payments, year two 79    
Variable payments, year three 80    
Variable payments, year four 80    
Variable payments, due year five 80    
Thereafter 361    
Infrastructure Construction And Improvements | SDG&E      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
2026 126    
2027 13    
2028 10    
2029 7    
2030 2    
Thereafter 26    
Construction projects, payable 184    
Construction Supply Agreements | SDG&E      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Construction projects, payable 93    
Nuclear Plant Maintenance | SDG&E      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Construction projects, payable 19    
Infrastructure Improvements For Natural Gas And Electric Transmission And Distribution | SDG&E      
Unrecorded Unconditional Purchase Obligation, Rolling Maturity [Abstract]      
Construction projects, payable $ 72