XML 156 R116.htm IDEA: XBRL DOCUMENT v3.6.0.2
SAN ONOFRE NUCLEAR GENERATING STATION (SONGS) - NARRATIVE (Details) - USD ($)
$ in Millions
1 Months Ended 3 Months Ended 12 Months Ended 48 Months Ended
Dec. 31, 2016
Apr. 30, 2016
Oct. 31, 2015
Dec. 31, 2015
Mar. 31, 2015
Dec. 31, 2016
Dec. 31, 2014
Dec. 31, 2016
Jointly Owned Utility Plant Interests [Line Items]                
Nuclear plant closure regulatory asset, noncurrent $ 3,414     $ 3,273   $ 3,414   $ 3,414
Nuclear decommissioning trusts 1,026     1,063   1,026   1,026
San Onofre Nuclear Generating Station (SONGS) [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Insurance recovery     $ 400          
Current authorized annual recovery amount from nuclear decommissioning trust funding   $ 4,400            
San Diego Gas and Electric Company [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Nuclear plant closure regulatory asset, current 81     107   81   81
Nuclear plant closure regulatory asset, noncurrent 998     977   998   998
Nuclear decommissioning trusts 1,026     1,063   1,026   1,026
Requested withdrawal from nuclear decommissioning trust funds 84              
Decommissioning liability 637         637   637
Cost study estimate decommissioning escalated $ 989         989   $ 989
San Diego Gas and Electric Company [Member] | Year 2013 through 2016 forecasted [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Current authorized annual recovery amount from nuclear decommissioning trust funding           218    
Amount pending regulatory clarification           $ 37    
San Diego Gas and Electric Company [Member] | San Onofre Nuclear Generating Station (SONGS) [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Ownership percentage 20.00%         20.00%   20.00%
Portion of weighted average return on preferred stock included in nuclear plant return on ratebase 50.00%         50.00%   50.00%
Return on ratebase               2.35%
Loss from plant closure, after tax (cumulative)               $ 125
Plant closure (adjustment) loss, after tax       $ 2 $ 13   $ 21  
Plant closure (adjustment) loss after settlement, after tax             $ 12  
Insurance recovery     $ 80          
Recovery allocation percentage     5.00%          
Current authorized annual recovery amount from nuclear decommissioning trust funding   $ 899            
San Diego Gas and Electric Company [Member] | San Onofre Nuclear Generating Station (SONGS) [Member] | Nuclear Plant Closure [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Nuclear plant closure regulatory asset $ 183         $ 183   183
Nuclear plant closure regulatory asset, current 31         31   31
Nuclear plant closure regulatory asset, noncurrent $ 152         $ 152   $ 152
Ratepayers [Member] | San Onofre Nuclear Generating Station (SONGS) [Member]                
Jointly Owned Utility Plant Interests [Line Items]                
Amount funded to customers through Energy Resource Recovery Account     $ 75