CALIFORNIA UTILITIES' REGULATORY MATTERS - SCHEDULE OF UTILITY PROJECTS (Details)
$ in Thousands
Dec. 31, 2015
USD ($)
Dec. 31, 2014
USD ($)
Jun. 11, 2014
USD ($)
Pipeline Safety Phase 1 [Member]      
Schedule Of Utility Projects [Line Items]      
Revised Estimated Project Cost $ 2,100,000    
Pipeline Safety Phase 1 [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Disallowed Costs Impact On Earnings After Tax 500    
Revised Estimated Project Cost 500,000    
Pipeline Safety Plan Regulatory Account 10,000   $ 100
Recovery Requested, PSEP Costs 100    
Pipeline Safety Phase 1 [Member] | Southern California Gas Company [Member]      
Schedule Of Utility Projects [Line Items]      
Disallowed Costs Impact On Earnings After Tax 3,200 $ 5,000  
Revised Estimated Project Cost 1,600,000    
Pipeline Safety Plan Regulatory Account 162,000   $ 46,000
Recovery Requested, PSEP Costs 26,800    
ORA Recommended Disallowance 11,100    
ORA Recommended Recovery 15,700    
TURN Recommended Disallowance 2,300    
TURN Recommended Recovery 24,500    
South Orange County Reliability Enhancement [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Upper Range 400,000    
Estimated Project Cost, Lower Range 350,000    
Cleveland National Forest Transmissions Projects [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Upper Range 450,000    
Estimated Project Cost, Lower Range 400,000    
South Bay Substation And Relocation [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Upper Range 175,000    
Estimated Project Cost, Lower Range 145,000    
Southern Gas System Reliability Project [Member] | Utility Subsidiaries [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Upper Range 850,000    
Estimated Project Cost, Lower Range 800,000    
Sycamore Penasquitos Transmission Project [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Upper Range 150,000    
Estimated Project Cost, Lower Range 120,000    
Revised Estimated Project Cost, Upper Range 300,000    
Revised Estimated Project Cost, Lower Range 250,000    
Electric Vehicle Charging Program [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost 103,000    
Estimated Capital Investment 59,000    
Revised Estimated Project Cost $ 45,000    
Number Of Charging Stations Requested 5,500    
Number Of Charging Stations Authorized 3,500    
Pipeline Safety And Reliability Project [Member]      
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost $ 600,000    
Wildfire Cost Recovery [Member] | San Diego Gas and Electric Company [Member]      
Schedule Of Utility Projects [Line Items]      
WEMA Balance 42,000    
Incurred Costs 2,400,000    
Requested Recovery 379,000    
Insurance Reimbursement 1,100,000    
Third Party Settlement Recoveries 824,000    
FERC Jurisdictional Rates $ 80,000    
Voluntary Shareholder Contribution, Percentage 10.00%