EX-99.19 20 eld_ex9919.htm CERTIFICATE eld_ex9919.htm

EXHIBIT 99.19

 

LAMAQUE PROJECT, QUÉBEC, CANADA

 

TECHNICAL REPORT

 

CERTIFICATE OF QUALIFIED PERSON

 

Ertan Uludag, P.Geo.

1188 Bentall 5, 550 Burrard St.

Vancouver, BC 

Tel: (604) 601-6658

Fax: (604) 687-4026

Email: ertan.uludag@eldoradogold.com

 

I, Ertan Uludag, am a Professional Geoscientist, employed as Manager, Resource Geology, of Eldorado Gold Corporation located at 1188 Bentall 5, 550 Burrard St., Vancouver in the Province of British Columbia.

 

This certificate applies to the technical report entitled Technical Report, Lamaque Project, Quebec, with an effective date of December 31st , 2021. 

 

I am a member of the Engineers & Geoscientists British Columbia (formerly the Association of Professional Engineers and Geoscientists of British Columbia). I also hold Special Authorization permit from The Ordre des géologues du Québec that is valid from September 1st, 2021, to August 31st, 2022.  I graduated from Middle East Technical University in Ankara Turkey with Bachelor of Science in Geological Engineering in July 1994.

 

I have practiced my profession continuously since 1996. I have been involved in ore control, mine geology and resource modelling work on gold, copper, zinc, lead and silver underground and open pit properties in Turkey, China, Greece, Canada and Romania, and rock mechanics in South Africa.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43-101.

 

I have visited the Lamaque Project on numerous occasions with my most recent visit occurring on February 25th to February 28th 2020.

 

I am responsible for items 14 in the technical report.

 

I am not independent of Eldorado Gold Corporation in accordance with the application of Section 1.5 of National Instrument 43-101.

 

I have read National Instrument 43-101 and Form 43-101FI and the items for which I am responsible in this report entitled, Technical Report, Technical Report, Lamaque Project, Quebec,, with an effective date of December 31st , 2021, has been prepared in compliance with same.

 

As of the effective date of the technical report, to the best of my knowledge, information and belief, the items of the technical report that I was responsible for contain all scientific and technical information that is required to be disclosed to make the technical report not misleading

 

Dated at Vancouver, British Columbia, this 31st day of March, 2022.

 

“Signed and Sealed”

 

Ertan Uludag                                                                                               

Ertan ULUDAG, P. Geo.

 

 

2021 Final Report