Investment in Unconsolidated Subsidiary (Details) (USD $)
3 Months Ended 9 Months Ended 3 Months Ended 9 Months Ended
Sep. 29, 2012
Oct. 01, 2011
Sep. 29, 2012
Oct. 01, 2011
Dec. 31, 2011
Sep. 29, 2012
Diamond Green Diesel Holdings LLC Joint Venture [Member]
Sep. 29, 2012
Diamond Green Diesel Holdings LLC Joint Venture [Member]
boe
Oct. 01, 2011
Diamond Green Diesel Holdings LLC Joint Venture [Member]
Jan. 21, 2011
Diamond Green Diesel Holdings LLC Joint Venture [Member]
Jan. 21, 2011
Diamond Green Diesel Holdings LLC Joint Venture [Member]
Valero Energy Corporation [Member]
Schedule of Equity Method Investments [Line Items]                    
Equity Method Investment, Ownership Percentage                 50.00% 50.00%
Joint Venture Potential Barrels Of Fuel Per Day             9,300      
Line of Credit Facility, Term             14 years      
Term loan facility           $ 221,300,000 $ 221,300,000      
Equity method investment committed contribution amount           93,200,000 93,200,000      
Equity method investment estimated aggregate cost of completion of facility           407,700,000 407,700,000      
Equity Method Investment Percentage Required to Pay for Cost Overruns           50.00% 50.00%      
Joint Venture Estimated Project Scope Changes           9,900,000        
Investment in the joint venture 54,424,000   54,424,000   21,733,000 54,400,000 54,400,000      
Loss from equity method investments $ 833,000 $ 170,000 $ 1,725,000 $ 1,344,000     $ 1,700,000 $ 1,300,000