Commitments and Contingencies (Details) (USD $)
3 Months Ended 3 Months Ended 0 Months Ended 0 Months Ended
Nov. 30, 2013
Aug. 31, 2013
Nov. 30, 2013
Corporate, Non-Segment [Member]
Nov. 30, 2013
Metals Recycling Business [Member]
Nov. 30, 2013
Auto Parts Business [Member]
Nov. 30, 2013
Steel Manufacturing Business [Member]
T
Nov. 30, 2013
Portland Harbor Superfund Site [Member]
Mar. 30, 2012
Portland Harbor Superfund Site [Member]
alternatives
Nov. 30, 2013
Other Metals Recycling Business Sites [Member]
Mar. 30, 2012
Minimum [Member]
Portland Harbor Superfund Site [Member]
Nov. 30, 2013
Minimum [Member]
Portland Harbor Superfund Site [Member]
potentially_responsible_party
Mar. 30, 2012
Maximum [Member]
Portland Harbor Superfund Site [Member]
Mar. 30, 2012
Lower Willamette Group [Member]
Portland Harbor Superfund Site [Member]
Mar. 30, 2012
Potential Responsible Parties [Member]
Minimum [Member]
Portland Harbor Superfund Site [Member]
Mar. 30, 2012
Potential Responsible Parties [Member]
Maximum [Member]
Portland Harbor Superfund Site [Member]
Accrual for Environmental Loss Contingencies [Roll Forward]                              
Beginning balance $ 49,794,000   $ 500,000 $ 30,520,000 $ 18,774,000   $ 1,000,000   $ 29,000,000            
Liabilities Established (Released), Net (37,000)   0 (329,000) 292,000                    
Payments and Other (10,000)   0 (10,000) 0                    
Ending balance 49,747,000   500,000 30,181,000 19,066,000 0 1,000,000   29,000,000            
Short-Term 943,000 754,000 200,000 189,000 554,000                    
Long-Term 48,804,000 49,040,000 300,000 29,992,000 18,512,000                    
Number Of Potentially Responsible Parties                     80        
Site Contingency Period Of Feasibility Study                         10 years    
Feasibility Study Investigation Costs                         100,000,000    
Site Contingency Number of Remedial Alternatives               10              
Site Contingency Least Costly Remediation Plan                           170,000,000 250,000,000
Site Contingency Most Costly Remediation Plan                           $ 1,080,000,000 $ 1,760,000,000
Site Contingency, Estimated Time Frame to Remediate                   2 years   28 years      
Annual production capacity (in tons)           950,000                  
Permit Expiration Date           Feb. 01, 2018