Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
Schedule of construction activity
The table below details the Company’s construction activity as of December 31, 2015. The information included in the table below represents management’s estimates and expectations at December 31, 2015, which are subject to change. The Company’s disclosures regarding certain projections or estimates of completion dates may not reflect actual results.
 
 
 
 
 
 
December 31, 2015
 
 
 
 
 
 
(Dollars in thousands)
 
Number of Properties
 
Estimated Completion Date
 
Construction in Progress Fundings During the Twelve Months Ended

 
Total Funded During the Twelve Months Ended

 
Total Amount Funded

 
Estimated Remaining Fundings (unaudited)

 
Estimated Total Investment (unaudited)

 
Approximate Square Feet

Construction Activity
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Birmingham, AL
 
1
 
Q4 2015 (1)
 
$

 
$
6,880

 
$
6,880

 
$
8,520

 
$
15,400

 
138,000

Austin, TX
 
1
 
Q2 2016
 
3,316

 
3,316

 
3,316

 
2,259

 
5,575

 
12,900

Nashville, TN
 
2
 
Q1 2017
 
15,479

 
17,434

 
21,818

 
29,982

 
51,800

 
294,000

Denver, CO
 
1
 
Q2 2017
 
229

 
229

 
229

 
26,271

 
26,500

 
98,000

Total
 
 
 
 
 
$
19,024

 
$
27,859

 
$
32,243

 
$
67,032

 
$
99,275

 
542,900

_____
(1) Includes $5.9 million for the addition of a 400-space parking garage which was completed in November 2015 and $9.5 million in tenant improvement allowances and commissions, a portion of which has not been completed.
Minimum lease payments for its operating leases
The Company’s future minimum lease payments for its operating leases, excluding leases that the Company has prepaid and leases in which an operator pays or fully reimburses the Company, as of December 31, 2015 were as follows (in thousands):  
2016
$
5,160

2017
5,225

2018
5,303

2019
5,399

2020
5,310

2021 and thereafter
289,686

 
$
316,083