Restructuring
9 Months Ended
Mar. 29, 2020
Restructuring and Related Activities [Abstract]  
Restructuring Restructuring
The Company has approved various operational plans that include restructuring costs. All restructuring costs are recorded in other operating expense on the consolidated statement of operations.
Corporate Restructuring
In April 2018, the Company approved a corporate restructuring plan. The purpose was to restructure and realign the Company's cost base with the long-range business strategy that was announced in February 2018. The restructuring activity was completed in the second quarter of fiscal 2019. For the three and nine months ended March 31, 2019, $0.0 million and $2.6 million was expensed relating to this corporate restructuring plan.
Factory Optimization Restructuring
In May 2019, the Company started a significant, multi-year factory optimization plan anchored by a state-of-the-art, automated 200mm capable silicon carbide and GaN fabrication facility and a large materials factory at its U.S. campus headquarters in Durham, North Carolina. As part of the plan, the Company will incur restructuring charges associated with the movement of equipment as well as disposals on certain long-lived assets.
The Company expects approximately $70.0 million in restructuring charges related to the factory optimization plan to be incurred through 2024. For the three and nine months ended March 29, 2020, the Company expensed and paid $1.1 million and $3.5 million of restructuring charges related to the factory optimization plan.
In September 2019, the Company announced its intent to build the new fabrication facility in Marcy, New York to complement the factory expansion underway at its U.S. campus headquarters in Durham, North Carolina. The Company has not started building the facility and is currently evaluating the impact of this decision on future restructuring charges.
Sales Representatives Restructuring
In July 2019, the Company realigned its sales resources as part of the Company's transition to a more focused semiconductor company. As a result, the Company recorded $0.0 million and $0.8 million in contract termination costs during the three and nine months ended March 29, 2020, of which $0.3 million is accrued in other current liabilities as of March 29, 2020.