Litigation and Regulatory Proceedings
The Company is involved in a number of litigation and regulatory proceedings (including those described below). Many of these proceedings are in early stages, and many of them seek or may seek damages and penalties, the amount of which is indeterminate. We estimate and provide for potential losses that may arise out of litigation and regulatory proceedings to the extent that such losses are probable and can be reasonably estimated. Significant judgment is required in making these estimates and our final liabilities may ultimately be materially different. Our total estimated liability in respect of litigation and regulatory proceedings is determined on a case-by-case basis and represents an estimate of probable losses after considering, among other factors, the progress of each case or proceeding, our experience and the experience of others in similar cases or proceedings, and the opinions and views of legal counsel. We account for legal defense costs in the period the costs are incurred.
July 2008 Common Stock Offering Litigation. On February 25, 2009, a putative class action was filed in the U.S. District Court for the Southern District of New York against the Company and certain of its officers and directors along with certain underwriters of the Company’s July 2008 common stock offering. The plaintiff filed an amended complaint on September 11, 2009 alleging that the registration statement for the offering contained material misstatements and omissions and seeking damages under Sections 11, 12 and 15 of the Securities Act of 1933 of an unspecified amount and rescission. The action was transferred to the U.S. District Court for the Western District of Oklahoma on October 13, 2009. Chesapeake and the officer and director defendants moved for summary judgment on grounds of loss causation and materiality on December 28, 2011, and the motion was granted as to all claims as a matter of law on March 29, 2013. Final judgment in favor of Chesapeake and the officer and director defendants was entered on June 21, 2013, and the plaintiff filed a notice of appeal on July 19, 2013 in the U.S. Court of Appeals for the Tenth Circuit. On August 8, 2014, the District Court dismissal was affirmed by the Court of Appeals, and on September 8, 2014, the plaintiff filed a petition for rehearing. We are currently unable to assess the probability of loss or estimate a range of potential loss associated with this matter.
Shareholder Derivative Litigation. A derivative action relating to the July 2008 offering filed in the U.S. District Court for the Western District of Oklahoma on September 6, 2011 is pending. Following the denial on September 28, 2012 of defendants’ motion to dismiss and pursuant to court order, nominal defendant Chesapeake filed an answer in the case on October 12, 2012. By stipulation between the parties, the case is stayed pending final resolution of the above described appeal.
A federal consolidated derivative action and an Oklahoma state court derivative action have been stayed since 2012 pending resolution of a related, previously reported putative federal securities class action. The shareholder derivative actions allege breaches of fiduciary duty, among other things, related to the former CEO’s personal financial practices and purported conflicts of interest, and the Company’s accounting for volumetric production payments. With the dismissal of the federal securities class action now affirmed, the parties have stipulated to continue the stay of the Oklahoma state court derivative action while plaintiffs pursue their claims in the federal consolidated derivative action. Plaintiffs’ consolidated amended derivative complaint was filed on October 31, 2014, and the Company intends to file a motion to dismiss by December 5, 2014.
On May 8, 2012, a derivative action was filed in the District Court of Oklahoma County, Oklahoma against the Company's directors alleging breaches of fiduciary duties and corporate waste related to the Company's officers and directors' use of the Company's fractionally owned corporate jets. On August 21, 2012, the District Court granted the Company's motion to dismiss for lack of derivative standing, and the plaintiff appealed the ruling on December 6, 2012. On May 16, 2014, the Court of Civil Appeals for the State of Oklahoma affirmed the dismissal. On July 7, 2014, plaintiffs filed a petition for writ of certiorari in the Oklahoma Supreme Court seeking review of the Court of Civil Appeals’ decision, and on October 13, 2014, the petition for certiorari was denied.
On April 10, 2014, a derivative action was filed in the District Court of Oklahoma County, Oklahoma against current and former directors and officers of the Company alleging, among other things, breach of fiduciary duties, waste of corporate assets, gross mismanagement and unjust enrichment related to the Company’s payment of shareholder dividends since October 2012. On July 2, 2014, the Company filed a motion to dismiss. The plaintiffs voluntarily dismissed the action on October 31, 2014.
Regulatory Proceedings. The Company has received, from the U.S. Department of Justice (DOJ) and certain state governmental agencies and authorities, subpoenas and demands for documents, information and testimony in connection with investigations into possible violations of federal and state antitrust laws relating to our purchase and lease of oil and gas rights in various states. The Company also has received DOJ and state subpoenas seeking information on the Company’s royalty payment practices. Chesapeake has engaged in discussions with the DOJ and state representatives and continues to respond to such subpoenas and demands.
On March 5, 2014, the Attorney General of the State of Michigan filed a criminal complaint against Chesapeake in Michigan state court alleging misdemeanor antitrust violations and attempted antitrust violations under state law arising out of the Company’s leasing activities in Michigan during 2010. On July 9, 2014, following a preliminary hearing on the complaint, as amended, the 89th District Court for Cheboygan County, Michigan ruled that one count alleging a bid-rigging conspiracy between Chesapeake and Encana Oil & Gas USA, Inc. regarding the October 2010 state lease auction would proceed to trial and dismissed claims alleging a second antitrust violation and an attempted antitrust violation. The Michigan Attorney General filed a second criminal complaint against Chesapeake in the same court on June 5, 2014 which, as amended, alleges that Chesapeake’s conduct in canceling lease offers to Michigan landowners in 2010 violated the state’s criminal enterprises and false pretenses felony statutes. On September 9, 2014, following a preliminary hearing, the Court ruled that all charges in the complaint would be tried. No trial date has been set for either matter.
Business Operations. Chesapeake is involved in various other lawsuits and disputes incidental to its business operations, including commercial disputes, personal injury claims, royalty claims, property damage claims and contract actions. With regard to contract actions, various mineral or leasehold owners have filed lawsuits against us seeking specific performance to require us to acquire their natural gas and oil interests and pay acreage bonus payments, damages based on breach of contract and/or, in certain cases, punitive damages based on alleged fraud. The Company has successfully defended a number of these failure-to-close cases in various courts, has settled and resolved other such cases and disputes and believes that its remaining loss exposure for these claims will not have a material adverse effect on our consolidated financial position, results of operations or cash flows. In addition, as described above, the Michigan Attorney General has commenced a criminal proceeding against us based on lease offers to Michigan landowners in 2010.
Regarding royalty claims, Chesapeake and other natural gas producers have been named in various lawsuits alleging royalty underpayment. The suits against us allege, among other things, that we used below-market prices, made improper deductions, used improper measurement techniques and/or entered into arrangements with affiliates that resulted in underpayment of royalties in connection with the production and sale of natural gas and NGL. The Company has resolved a number of these claims through negotiated settlements of past and future royalties and has prevailed in various other lawsuits. We are currently defending lawsuits seeking damages for royalty underpayment in various states, including cases filed by individual royalty owners and putative class actions, some of which seek to certify a statewide class. The Company also has received DOJ and state subpoenas seeking information on the Company’s royalty payment practices.
Plaintiffs have varying royalty provisions in their respective leases and oil and gas law varies from state to state. Royalty owners and producers differ in their interpretation of the legal effect of lease provisions governing royalty calculations, an issue in a putative class action filed in 2010 on behalf of Oklahoma royalty owners asserting claims dating back to 2004. In July 2014, this case was remanded to the trial court for further proceedings following the reversal on appeal of certification of a statewide class. We and the named plaintiff have participated in mediation concerning the claims asserted in the putative class action litigation. Based on analysis we and outside advisors have conducted, we have accrued a loss contingency of $100 million in the Current Quarter condensed consolidated statement of operations. Although we believe our estimate of the potential loss is reasonable, the final resolution of the Oklahoma royalty claims could differ from the amount accrued, and actual results, whether by continued litigation or settlement, could differ materially from management’s estimate.
We believe losses are reasonably possible in certain of the other pending royalty cases for which we have not accrued a loss contingency, but we are currently unable to estimate an amount or range of loss or the impact the actions could have on our future results of operations or cash flows. In Pennsylvania, two putative statewide class actions and one purported class arbitration were filed in 2014 on behalf of royalty owners asserting various claims for damages related to alleged underpayment of royalties as a result of the Company’s divestiture of substantially all of its midstream business and most of its gathering assets in 2012 and 2013. These Pennsylvania cases include claims for violation of and conspiracy to violate the federal Racketeer Influenced and Corrupt Organizations Act. Uncertainties in pending royalty cases generally include the complex nature of the claims and defenses, the potential size of the class in class actions, the scope and types of the properties and agreements involved, and the applicable production years.
Based on management’s current assessment, we are of the opinion that no pending or threatened lawsuit or dispute relating to the Company’s business operations is likely to have a material adverse effect on its future consolidated financial position, results of operations or cash flows. The final resolution of such matters could exceed amounts accrued, however, and actual results could differ materially from management’s estimates.
Environmental Contingencies
The nature of the natural gas and oil business carries with it certain environmental risks for Chesapeake and its subsidiaries. Chesapeake has implemented various policies, procedures, training and auditing to reduce and mitigate such environmental risks. Chesapeake conducts periodic reviews, on a company-wide basis, to assess changes in our environmental risk profile. Environmental reserves are established for environmental liabilities for which economic losses are probable and reasonably estimable. We manage our exposure to environmental liabilities in acquisitions by using an evaluation process that seeks to identify pre-existing contamination or compliance concerns and address the potential liability. Depending on the extent of an identified environmental concern, Chesapeake may, among other things, exclude a property from the transaction, require the seller to remediate the property to our satisfaction in an acquisition or agree to assume liability for the remediation of the property.
Commitments
Gathering, Processing and Transportation Agreements
We have contractual commitments with midstream service companies and pipeline carriers for future gathering, processing and transportation of natural gas and liquids to move certain of our production to market. Working interest owners and royalty interest owners, where appropriate, will be responsible for their proportionate share of these costs. Commitments related to gathering, processing and transportation agreements are not recorded in the accompanying condensed consolidated balance sheets; however, they are reflected as adjustments to natural gas, oil and NGL sales prices used in our proved reserves estimates.
The aggregate undiscounted commitments under our gathering, processing and transportation agreements, excluding any reimbursement from working interest and royalty interest owners or credits for third-party volumes, are presented below.
 
 
September 30, 2014
 
 
($ in millions)
2014
 
$
616

2015
 
1,852

2016
 
1,933

2017
 
1,951

2018
 
1,748

2019 - 2099
 
7,672

Total
 
$
15,772


Drilling Contracts
We have contracts with various drilling contractors, including those with SSE as discussed in Note 2, to utilize drilling services with terms ranging from three months to three years at market based pricing. These commitments are not recorded in the accompanying condensed consolidated balance sheets. As of September 30, 2014, the aggregate undiscounted minimum future payments under these drilling service commitments were approximately $449 million.
Pressure Pumping Contracts
As discussed in Note 2, in connection with the spin-off of our oilfield services business we entered into an agreement with a subsidiary of SSE related to pressure pumping services. The services agreement requires us to utilize, at market-based pricing, the lesser of (i) seven, five and three pressure pumping crews in years one, two and three of the agreement, respectively, or (ii) 50% of the total number of all pressure pumping crews working for us in all of our operating regions during the respective year. We are also required to utilize SSE pressure pumping services for a minimum number of fracture stages as set forth in the agreement. We are entitled to terminate the agreement in certain situations, including if SSE fails to provide the overall quality of service provided by similar service providers. As of September 30, 2014, the aggregate undiscounted minimum future payments under this agreement were approximately $283 million.
Drilling Commitments
We have committed to drill wells in conjunction with our CHK Cleveland Tonkawa, L.L.C. financial transaction and in conjunction with the formation of the Chesapeake Granite Wash Trust. See Noncontrolling Interests in Note 7 for discussion of these commitments.
Natural Gas and Liquids Purchase Commitments
We regularly commit to purchase natural gas and liquids from other owners in the properties we operate, including owners associated with our volumetric production payment (VPP) transactions. Production purchased under these arrangements is based on market prices at the time of production, and the purchased natural gas and liquids are resold at market prices. See Note 10 for further discussion of our VPP transactions.
Net Acreage Maintenance Commitments
Under the terms of our joint venture agreements with Total and Sinopec (see Note 10), we are required to extend, renew or replace expiring joint leasehold, at our cost, to ensure that the net acreage is maintained in certain designated areas as of future measurement dates. To date, we have satisfied our replacement commitments under the Sinopec agreement. In the Current Quarter, we settled a dispute with Total regarding our acreage maintenance obligation as of December 31, 2012 for $50 million. The payment was based on a shortfall of approximately 20,800 net acres.
Other Commitments

In July 2011, we agreed to invest $155 million in preferred equity securities of Sundrop Fuels, Inc. (Sundrop), a privately held cellulosic biofuels company based in Longmont, Colorado. We also provided Sundrop with a one-time option to require us to purchase up to $25 million in additional preferred equity securities following the full payment of the initial investment, subject to the occurrence of specified milestones. As of September 30, 2014, we had funded our $155 million commitment in full and the milestones related to Sundrop’s preferred equity call option had not been met. See Note 11 for further discussion of this investment.
As part of our normal course of business, we enter into various agreements providing, or otherwise arranging, financial or performance assurances to third parties on behalf of our wholly owned guarantor subsidiaries. These agreements may include future payment obligations or commitments regarding operational performance that effectively guarantee our subsidiaries’ future performance.
In connection with divestitures, our purchase and sale agreements generally provide indemnification to the counterparty for liabilities incurred as a result of a breach of a representation or warranty by the indemnifying party. These indemnifications generally have a discrete term and are intended to protect the parties against risks that are difficult to predict or cannot be quantified at the time of the consummation of a particular transaction. For divestitures of oil and gas properties, our purchase and sale agreements may require the return of a portion of the proceeds we receive as a result of uncured title defects.
Certain of our natural gas and oil properties are burdened by non-operating interests such as royalty and overriding royalty interests, including overriding royalty interests sold through our VPP transactions. As the holder of the working interest from which such interests have been created, we have the responsibility to bear the cost of developing and producing the reserves attributable to such interests. See Note 10 for further discussion of our VPP transactions.