XML 65 R52.htm IDEA: XBRL DOCUMENT v3.19.2
Contingencies (Details)
$ in Millions
1 Months Ended 3 Months Ended 6 Months Ended
Jul. 31, 2019
Case
Jun. 30, 2019
USD ($)
Case
Jun. 30, 2019
USD ($)
Case
Oct. 24, 2014
USD ($)
Site Contingency [Abstract]        
Consent decree paid by US government | $       $ 2.3
Silica Cases [Member]        
Loss Contingency, Information about Litigation Matters [Abstract] [Abstract]        
Number of pending cases   3 3  
Cumulative number of cases dismissed   1,493 1,493  
Number of cases dismissed     0  
Number of lawsuits settled     1  
Asbestos Cases [Member]        
Loss Contingency, Information about Litigation Matters [Abstract] [Abstract]        
Number of pending cases   71 71  
Cumulative number of cases dismissed   59 59  
Number of new cases filed   13 20  
Number of cases dismissed     2  
Number of lawsuits settled     0  
Number of cases claim liability     45  
Number of cases with no alleged exposure date     20  
Number of allege liability     22  
Asbestos Cases [Member] | Subsequent Event [Member]        
Loss Contingency, Information about Litigation Matters [Abstract] [Abstract]        
Number of new cases filed 16      
Administrative Consent Order for Contamination Associated with Historic Use of PCBs [Member]        
Site Contingency [Abstract]        
Estimated accrued remediation cost | $   $ 0.4 $ 0.4  
Administrative Consent Order for Installation of Groundwater Contamination System [Member]        
Site Contingency [Abstract]        
Estimated accrued remediation cost | $   $ 0.4 0.4  
Estimated cost of wastewater treatment upgrades, lower range | $     6.0  
Estimated cost of wastewater treatment upgrades, upper range | $     $ 8.0