XML 96 R81.htm IDEA: XBRL DOCUMENT v3.10.0.1
Litigation (Details)
$ in Millions
2 Months Ended 12 Months Ended
Feb. 15, 2019
Case
Dec. 31, 2018
USD ($)
Case
Oct. 24, 2014
USD ($)
Site Contingency [Abstract]      
Consent decree paid by US government | $     $ 2.3
Silica Cases [Member]      
Loss Contingency, Information about Litigation Matters [Abstract]      
Number of pending cases   3  
Cumulative number of cases dismissed   1,493  
Number of cases dismissed   0  
Number of lawsuits settled   1  
Asbestos Cases [Member]      
Loss Contingency, Information about Litigation Matters [Abstract]      
Number of pending cases   34  
Cumulative number of cases dismissed   57  
Number of new cases filed   14  
Number of cases dismissed   4  
Number of cases claim liability   25  
Number of allege liability   6  
Number of cases with no alleged exposure date   5  
Asbestos Cases [Member] | Subsequent Event [Member]      
Loss Contingency, Information about Litigation Matters [Abstract]      
Number of new cases filed 4    
Asbestos Cases [Member] | AMCOL International Corporation [Member]      
Loss Contingency, Information about Litigation Matters [Abstract]      
Number of allege liability   3  
Administrative Consent Order for Contamination Associated with Historic Use of PCBs [Member]      
Site Contingency [Abstract]      
Location of plant   Canaan, Connecticut  
Estimated accrued remediation cost | $   $ 0.4  
Administrative Consent Order for Installation of Groundwater Contamination System [Member]      
Site Contingency [Abstract]      
Location of plant   Adams, Massachusetts plant  
Estimated accrued remediation cost | $   $ 0.4  
Estimated cost of wastewater treatment upgrades, lower range | $   6.0  
Estimated cost of wastewater treatment upgrades, upper range | $   $ 8.0