COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS
6 Months Ended
Jun. 30, 2016
Contractors [Abstract]  
COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS

4.      COSTS AND ESTIMATED EARNINGS ON UNCOMPLETED CONTRACTS

Costs and estimated earnings in excess of billings on uncompleted contracts consist of:

 

    June 30, 2016
    U.S.        
    Government   Commercial   Total
             
Costs incurred on uncompleted Contracts   $ 371,414,845     $ 139,315,072     $ 510,729,917  
Estimated earnings     55,185,377       53,583,053       108,768,430  
Sub-total     426,600,222       192,898,125       619,498,347  
Less billings to date     377,641,991       148,244,511       525,886,502  
Costs and estimated earnings in excess of billings on uncompleted contracts   $ 48,958,231     $ 44,653,614     $ 93,611,845  

 

    December 31, 2015
    U.S.        
    Government   Commercial   Total
             
Costs incurred on uncompleted Contracts   $ 349,458,368     $ 123,078,356     $ 472,536,724  
Estimated earnings     62,718,792       49,539,299       112,258,091  
Sub-total     412,177,160       172,617,655       584,794,815  
Less billings to date     353,601,903       128,745,963       482,347,866  
Costs and estimated earnings in excess of billings on uncompleted contracts   $ 58,575,257     $ 43,871,692     $ 102,446,949  

 

The above amounts are included in the accompanying balance sheets under the following captions at June 30, 2016 and December 31, 2015:

 

    June 30, 2016   December 31, 2015
                 
Costs and estimated earnings in excess of billings on
uncompleted contracts
  $ 93,990,022     $ 102,622,387  
Billings in excess of costs and estimated earnings on
uncompleted contracts
    (378,177 )     (175,438 )
                 
Totals   $ 93,611,845     $ 102,446,949  

 

U.S. Government Contracts includes contracts directly with the U.S. Government and Government subcontracts.

Revisions in the estimated gross profits on contracts and contract amounts are made in the period in which the circumstances requiring the revisions occur. During the six months ended June 30, 2016, the effect of such revisions in total estimated contract profits resulted in a decrease to the total gross profit to be earned on the contracts of approximately $1,170,000 from that which would have been reported had the revised estimates been used as the basis of recognition of contract profits in prior years, excluding the effect of the A-10 contract. During the six months ended June 30, 2015, the effect of such revisions was a decrease to total gross profit of approximately $170,000.

Although management believes it has established adequate procedures for estimating costs to uncompleted open contracts, it is possible that additional significant costs could occur on contracts prior to completion.