XML 33 R23.htm IDEA: XBRL DOCUMENT v3.24.0.1
Electric Plant (Tables)
12 Months Ended
Dec. 31, 2023
Property, Plant and Equipment [Abstract]  
Schedule Of Net Electric Plant

Our net electric plant was composed of the following as of December 31, 2023:

 

 

 

Wildcat
Point

 

 

North
Anna

 

 

Clover

 

 

Combustion
Turbine
Facilities

 

 

Other

 

 

Total

 

 

 

(in thousands)

 

Property, plant, and equipment

 

$

881,910

 

 

$

427,567

 

 

$

706,831

 

 

$

444,241

 

 

$

105,662

 

 

$

2,566,211

 

Accumulated depreciation

 

 

(151,206

)

 

 

(283,675

)

 

 

(438,720

)

 

 

(263,802

)

 

 

(35,890

)

 

 

(1,173,293

)

Net Property, plant, and equipment

 

 

730,704

 

 

 

143,892

 

 

 

268,111

 

 

 

180,439

 

 

 

69,772

 

 

 

1,392,918

 

Nuclear fuel, at amortized cost

 

 

—

 

 

 

16,340

 

 

 

—

 

 

 

—

 

 

 

—

 

 

 

16,340

 

Construction work in progress

 

 

1,600

 

 

 

65,822

 

 

 

1,761

 

 

 

2,234

 

 

 

8,671

 

 

 

80,088

 

Net Electric Plant

 

$

732,304

 

 

$

226,054

 

 

$

269,872

 

 

$

182,673

 

 

$

78,443

 

 

$

1,489,346

 

Our net electric plant was composed of the following as of December 31, 2022:

 

 

 

Wildcat
Point

 

 

North
Anna

 

 

Clover

 

 

Combustion
Turbine
Facilities

 

 

Other

 

 

Total

 

 

 

(in thousands)

 

Property, plant, and equipment

 

$

879,319

 

 

$

418,073

 

 

$

708,240

 

 

$

441,000

 

 

$

102,803

 

 

$

2,549,435

 

Accumulated depreciation

 

 

(125,832

)

 

 

(272,036

)

 

 

(427,304

)

 

 

(254,425

)

 

 

(36,934

)

 

 

(1,116,531

)

Net Property, plant, and equipment

 

 

753,487

 

 

 

146,037

 

 

 

280,936

 

 

 

186,575

 

 

 

65,869

 

 

 

1,432,904

 

Nuclear fuel, at amortized cost

 

 

—

 

 

 

19,155

 

 

 

—

 

 

 

—

 

 

 

—

 

 

 

19,155

 

Construction work in progress

 

 

245

 

 

 

47,378

 

 

 

159

 

 

 

227

 

 

 

8,066

 

 

 

56,075

 

Net Electric Plant

 

$

753,732

 

 

$

212,570

 

 

$

281,095

 

 

$

186,802

 

 

$

73,935

 

 

$

1,508,134