Note 9 — Utility Regulatory Assets and Liabilities and Regulatory Matters
The following regulatory assets and liabilities associated with UGI Utilities are included in our Consolidated Balance Sheets at September 30:
20202019
Regulatory assets (a):  
Income taxes recoverable$124 $115 
Underfunded pension and postretirement plans175 179 
Environmental costs61 60 
Removal costs, net26 28 
Other11 14 
Total regulatory assets$397 $396 
Regulatory liabilities (a):  
Postretirement benefit overcollections$13 $15 
Deferred fuel and power refunds29 
State income tax benefits — distribution system repairs28 25 
PAPUC Temporary Rates Order31 
Excess federal deferred income taxes274 280 
Other
Total regulatory liabilities$353 $359 
(a)    Current regulatory assets are recorded in “Other current assets” on the Consolidated Balance Sheets. Regulatory liabilities are recorded in “Other current liabilities” and “Other noncurrent liabilities” on the Consolidated Balance Sheets.

Other than removal costs, UGI Utilities currently does not recover a rate of return on the regulatory assets included in the table above.

Income taxes recoverable. This regulatory asset is the result of recording deferred tax liabilities pertaining to temporary tax differences principally as a result of the pass through to ratepayers of the tax benefit on accelerated tax depreciation for state income tax purposes, and the flow through of accelerated tax depreciation for federal income tax purposes for certain years prior to 1981. These deferred taxes have been reduced by deferred tax assets pertaining to utility deferred investment tax credits. UGI Utilities has recorded regulatory income tax assets related to these deferred tax liabilities representing future revenues recoverable through the ratemaking process over the average remaining depreciable lives of the associated property ranging from 1 to approximately 65 years.
Underfunded pension and other postretirement plans. This regulatory asset represents the portion of net actuarial losses and prior service costs (credits) associated with pension and other postretirement benefits which are probable of being recovered through future rates based upon established regulatory practices. These regulatory assets are adjusted annually or more frequently under certain circumstances when the funded status of the plans is remeasured in accordance with GAAP. These costs are amortized over the average remaining future service lives of plan participants.
Environmental costs. Environmental costs principally represent estimated probable future environmental remediation and investigation costs that Gas Utility expects to incur, primarily at MGP sites in Pennsylvania, in conjunction with three remediation COAs with the PADEP, which were consolidated into one COA effective October 1, 2020. Pursuant to base rate orders, Gas Utility receives ratemaking recognition of its estimated environmental investigation and remediation costs associated with their environmental sites. This ratemaking recognition balances the accumulated difference between historical costs and rate recoveries with an estimate of future costs associated with the sites. At September 30, 2020, the period over which Gas Utility expects to recover these costs will depend upon future remediation activity. For additional information on environmental costs, see Note 17.
Removal costs, net. This regulatory asset represents costs incurred, net of salvage, associated with the retirement of depreciable utility plant. As required by PAPUC ratemaking, removal costs include actual costs incurred associated with asset retirement obligations. Consistent with prior ratemaking treatment, UGI Utilities expects to recover these costs over five years.
Postretirement benefit overcollections. This regulatory liability represents the difference between amounts recovered through rates by Gas Utility and Electric Utility and actual costs incurred in accordance with accounting for postretirement benefits. With respect to Gas Utility, postretirement benefit overcollections are generally being refunded to customers over a ten-year period beginning October 19, 2016. With respect to Electric Utility, the overcollections are being refunded to ratepayers over a 20-year period effective October 27, 2018.
Deferred fuel and power refunds. Gas Utility’s and Electric Utility’s tariffs contain clauses that permit recovery of all prudently incurred purchased gas and power costs through the application of PGC rates in the case of Gas Utility and DS tariffs in the case of Electric Utility. These clauses provide for periodic adjustments to PGC and DS rates for differences between the total amount of purchased gas and electric generation supply costs collected from customers and recoverable costs incurred. Net undercollected costs are classified as a regulatory asset and net overcollections are classified as a regulatory liability.
Gas Utility uses derivative instruments to reduce volatility in the cost of gas it purchases for retail core-market customers. Realized and unrealized gains or losses on natural gas derivative instruments are included in deferred fuel and power costs or refunds. Net unrealized gains and (losses) on such contracts at September 30, 2020 and 2019 were $8 and $(2), respectively.
State income tax benefits — distribution system repairs. This regulatory liability represents Pennsylvania state income tax benefits, net of federal benefit, resulting from the deduction for income tax purposes of repair and maintenance costs associated with Gas Utility or Electric Utility assets that are capitalized for regulatory and GAAP reporting. The tax benefits associated with these repair and maintenance deductions will be reflected as a reduction to income tax expense over the remaining tax lives of the related book assets.
PAPUC Temporary Rates Order. On May 17, 2018, the PAPUC ordered each regulated utility currently not in a general base rate case proceeding, including UGI Gas, PNG and CPG, to reduce their rates to credit customers any tax savings as a result of the TCJA through the establishment of a negative surcharge. These negative surcharges applied to bills rendered on or after July 1, 2018 and remained in effect until October 11, 2019, the effective date of Gas Utility’s new base rates, subject to a final reconciliation of any over- or under-crediting of the tax savings. The remaining regulatory liability will be returned to customers through an additional temporary negative surcharge from January 1, 2021 through October 10, 2021

In its May 17, 2018 Order, the PAPUC also required Pennsylvania utilities to establish a regulatory liability for tax benefits that accrued during the period January 1, 2018 through June 30, 2018, resulting from the reduced federal tax rate. The rate treatment of this regulatory liability was addressed in Gas Utility’s base rate proceeding filed January 28, 2019 (see “Base Rate Filings” below for further information).

For Pennsylvania utilities that were in a general base rate proceeding, including Electric Utility, no negative surcharge applied. The tax benefits that accrued during the period January 1, 2018 through October 26, 2018, the date before Electric Utility’s base rate case became effective were refunded to Electric Utility ratepayers through a one-time bill credit.
Excess federal deferred income taxes. This regulatory liability is the result of remeasuring UGI Utilities’ federal deferred income tax liabilities on utility plant due to the enactment of the TCJA on December 22, 2017. In order for our utility assets to continue to be eligible for accelerated tax depreciation, current law requires that excess federal deferred income taxes resulting from the remeasurement be amortized no more rapidly than over the remaining lives of the assets that gave rise to the excess federal deferred income taxes, ranging from 1 year to approximately 65 years. This regulatory liability has been increased to
reflect the tax benefit generated by the amortization of the excess deferred federal income taxes and is being amortized and credited to tax expense.
Other. Other regulatory assets and liabilities comprise a number of deferred items including, among others, certain incremental expenses attributable to the ongoing COVID-19 pandemic, certain information technology costs, energy efficiency conservation costs and rate case expenses.
Other Regulatory Matters
Base Rate Filings.  On January 28, 2020, Gas Utility filed a request with the PAPUC to increase its annual base distribution operating revenues by $75 annually. On October 8, 2020, the PAPUC issued a final Order approving a previously filed Joint Petition for Approval of Settlement of all issues (the “Joint Petition”). Under the terms of the Joint Petition, Gas Utility will be permitted to increase its annual base distribution rates by $20, through a phased approach, with $10 beginning January 1, 2021 and an additional $10 beginning July 1, 2021. Additionally, Gas Utility will be authorized to implement a DSIC once Gas Utility total property, plant and equipment less accumulated depreciation reaches $2,875, with this threshold being unchanged from Gas Utility’s 2019 base rate case. The Joint Petition also includes enhanced COVID-19 customer assistance measures, including the establishment of an Emergency Relief Program for a defined set of payment troubled customers (“ERP”). Additionally, the Joint Petition will permit the Gas Utility to establish a regulatory asset for certain incremental expenses attributable to the ongoing COVID-19 pandemic, most notably expenses related to the ERP and uncollectible accounts expense, through the effective date of rates in the next Gas Utility base rate case, to be recovered and amortized over a 10-year period. In accordance with the terms of the Joint Petition, Gas Utility will not be permitted to file a rate case prior to January 1, 2022.

On January 28, 2019, Gas Utility filed a rate request with the PAPUC to increase the base operating revenues for residential, commercial, and industrial customers throughout its Pennsylvania service territory by an aggregate $71. On October 4, 2019, the PAPUC issued a final Order approving a settlement that permitted Gas Utility, effective October 11, 2019, to increase its base distribution revenues by $30 under a single consolidated tariff, approved a plan for uniform class rates, and permitted Gas Utility to extend its Energy Efficiency and Conservation and Growth Extension Tariff programs by an additional term of five years. The PAPUC’s final Order approved a negative surcharge, to return to customers $24 of tax benefits experienced by Gas Utility over the period January 1, 2018 to June 30, 2018, plus applicable interest, in accordance with the May 17, 2018 PAPUC Order, which became effective for a twelve-month period beginning on October 11, 2019, the effective date of Gas Utility’s new base rates, subject to final reconciliation of any over- or under-crediting of the tax savings.

On October 25, 2018, the PAPUC approved a final order providing for a $3 annual base distribution rate increase for Electric Utility, effective October 27, 2018. As part of the final PAPUC Order, Electric Utility provided customers with a one-time billing credit associated with 2018 TCJA tax benefits. On November 26, 2018, the Pennsylvania Office of Consumer Advocate filed an appeal to the Pennsylvania Commonwealth Court challenging the PAPUC’s acceptance of UGI Utilities’ use of a fully projected future test year and handling of consolidated federal income tax benefits. On January 15, 2020, the Pennsylvania Commonwealth Court issued a decision affirming the PAPUC Order adopting UGI Utilities’ position on both issues. No party exercised their right to seek an appeal of the Commonwealth Court decision.