Commitments and Contingencies Commitments and Contingencies
Legal Proceedings
We are involved in various lawsuits, claims, inquiries and other regulatory and compliance matters, most of which are routine to the nature of our business. When it is probable that a loss will be incurred and where a range of the loss can be reasonably estimated, the best estimate within the range is accrued. When the best estimate within the range cannot be determined, the low end of the range is accrued. The ultimate resolution of these claims could affect future results of operations should our exposure be materially different from our estimates or should we incur liabilities that were not previously accrued. Probable insurance reimbursements are not offset against potential liabilities.
Because of the uncertainties associated with claims resolution and litigation, future expenses to resolve legal proceedings could be higher than the liabilities we have accrued. If information were to become available that allowed us to reasonably estimate an amount higher or lower than what we have accrued in the range of potential expenses determine to be probable, we would adjust our accrued liabilities accordingly. Additional lawsuits, claims, inquiries and other regulatory and compliance matters could arise in the future. The range of expenses for resolving any future matters would be assessed as they arise; until then, a range of potential expenses for their resolution cannot be determined. Based upon current information, we believe that the impact of the resolution of legal proceedings would not be, individually or in the aggregate, material to our financial position, results of operations or cash flows.
Environmental Expenditures
Environmental expenditures are generally expensed. When it is probable that a loss will be incurred and where a range of the loss can be reasonably estimated, the best estimate within the range is accrued. When the best estimate within the range cannot be determined, the low end of the range is accrued. The ultimate resolution of these matters could affect future results of operations should our exposure be materially different from our estimates or should we incur liabilities that were not previously accrued. Probable insurance
reimbursements are not offset against potential liabilities. We review our estimates of the costs of complying with environmental laws related to the remediation and cleanup of various sites, including sites in which governmental agencies have designated us as a potentially responsible party (“PRP”). However, environmental expenditures for newly acquired assets and those that extend or improve the economic useful life of existing assets are capitalized and amortized over the shorter of the estimated useful life of the acquired asset or the remaining life of the existing asset.
As of June 28, 2025, we have been designated by the U.S. Environmental Protection Agency (“EPA”) and/or other responsible state agencies as a PRP at ten waste disposal or waste recycling sites that are the subject of separate investigations or proceedings concerning alleged soil and/or groundwater contamination. No settlement of our liability related to any of these sites has been agreed upon. We are participating with other PRPs at these sites and anticipate that our share of remediation costs will be determined pursuant to agreements that we enter into with the EPA or other governmental authorities.
These estimates could change as a result of changes in planned remedial actions, remediation technologies, site conditions, the estimated time to complete remediation, environmental laws and regulations, and other factors. Because of the uncertainties associated with environmental assessment and remediation activities, our future expenses to remediate these sites could be higher than the liabilities we have accrued. If information were to become available that allowed us to reasonably estimate an amount higher or lower than what we have accrued in the range of potential expenses, we would adjust our environmental liabilities accordingly. In addition, we may be identified as a PRP at additional sites in the future. The range of expenses for remediation of any future-identified sites would be addressed as they arise; until then, a range of expenses for their remediation cannot be determined.
The activity related to our environmental liabilities for the six months ended June 28, 2025 is shown below.
(In millions)
Balance at December 28, 2024
$13.0 
Charges, net of reversals.7 
Payments(1.4)
Balance at June 28, 2025
$12.3 