XML 142 R123.htm IDEA: XBRL DOCUMENT v3.6.0.2
COMMITMENTS AND CONTINGENCIES (Narrative) (Details)
$ in Millions
1 Months Ended 12 Months Ended
Jul. 20, 2016
USD ($)
Jun. 30, 2015
USD ($)
a
May 31, 2015
USD ($)
a
Dec. 31, 2016
USD ($)
bbl
Dec. 31, 2015
USD ($)
Dec. 31, 2014
USD ($)
Mar. 31, 2015
USD ($)
Sep. 09, 2014
bbl
Feb. 25, 2014
bbl
Mar. 31, 2013
USD ($)
Sep. 09, 2010
bbl
Jul. 26, 2010
Miles
bbl
Site Contingency [Line Items]                        
Remaining liabilities       $ 99.9 $ 95.8 $ 6.3            
Accrual for environmental loss contingencies       50.8 64.0              
Government fines and penalties $ 61.0                      
Aggregate insurance coverage limit       650.0                
Insurance recoveries, since inception       547.0                
Remaining aggregate insurance coverage                   $ 145.0    
Remaining expected insurance recoveries       $ 103.0     $ 85.0          
Natural gas volumes purchased on contractual basis (in percentage)       40.00%                
Rent expense       $ 13.0 14.9 18.2            
Estimated total loss of crude oil release       $ 1,215.0                
Natural gas volumes in custody (in barrels) | bbl       30.0                
Natural gas volumes in custody (in barrels) | bbl       66.1                
Additional Insurance Recoveries       $ 10.0                
Rights Of Way [Member]                        
Site Contingency [Line Items]                        
Rent expense       2.6 2.7 3.6            
Disputes with Insurers for Which Partial Payment Was Received [Member]                        
Site Contingency [Line Items]                        
Insurance recoveries       42.0                
Dispute with One Particular Insurer [Member]                        
Site Contingency [Line Items]                        
Remaining expected insurance recoveries       85.0                
Disputes with Remaining Insurers [Member]                        
Site Contingency [Line Items]                        
Remaining expected insurance recoveries       18.0                
Liability Program [Member]                        
Site Contingency [Line Items]                        
Aggregate insurance coverage limit       900.0                
Line 6A Crude Oil Release [Member]                        
Site Contingency [Line Items]                        
Government fines and penalties 1.0                      
Consent Decree [Member]                        
Site Contingency [Line Items]                        
Accrual for environmental loss contingencies 110.0                      
Civil Penalties [Member]                        
Site Contingency [Line Items]                        
Government fines and penalties $ 62.0                      
Line Six Marshall Leak [Member]                        
Site Contingency [Line Items]                        
Remaining liabilities       138.8 149.8              
Crude oil released (in barrels) | bbl                       20,000
Area Impacted By Crude Oil Release | Miles                       38
Costs paid associated with crude oil release       20.8 37.2 $ 141.4            
Government fines and penalties       $ 68.5                
Loss contingency, pending claims (in claims)       2                
Estimated total loss of crude oil release       $ 1.2                
Accrual for Environmental Loss Contingencies, Period Increase (Decrease), Total         15.0              
Line Six Marshall Leak [Member] | Civil Penalties Related to Clean Water Act [Member]                        
Site Contingency [Line Items]                        
Government fines and penalties       61.0                
Line Six Marshall Leak [Member] | May 2015 Settlement [Member]                        
Site Contingency [Line Items]                        
Costs paid associated with crude oil release     $ 5.0                  
Area of remediation site (in acres) | a     300                  
Line Six Marshall Leak [Member] | June 2015 Agreement [Member]                        
Site Contingency [Line Items]                        
Accrual for environmental loss contingencies   $ 3.9                    
Area of remediation site (in acres) | a   175                    
Line Six Romeoville Leak [Member]                        
Site Contingency [Line Items]                        
Crude oil released (in barrels) | bbl               9,000        
Costs paid associated with crude oil release         $ 0.6              
Estimated total loss of crude oil release       $ 53.0                
Crude oil recovered (in barrels) | bbl                     1,400  
Griffith Terminal Leak [Member]                        
Site Contingency [Line Items]                        
Crude oil released (in barrels) | bbl                 975