XML 25 R16.htm IDEA: XBRL DOCUMENT v3.24.3
COMMITMENTS AND CONTINGENCIES:
3 Months Ended
Sep. 30, 2024
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES:

8.       COMMITMENTS AND CONTINGENCIES:

 

A: Employment/Consulting (and related) agreements:

 

Stephen Craig Scott (“Scott”) was appointed interim CEO effective June 1, 2024. Scott had previously been working with the Company as an employee/consultant since 1993 in various positions including Director of Communications, SVP- Capital Markets and Head of Business Development. On October 25, 2023, Scott entered into an agreement with the Company which included provisions for a monthly salary of $14,000 of which $2,000 is deferred. During the year ended June 30, 2024 and three months ended September 30, 2024, Scott deferred substantial portions of his monthly salary to help the Company conserve cash. For the three months ended September 30, 2024 and 2023, Scott was paid nil and $36,000 respectively.

 

William O’Neill (“O’Neill”) was hired as the Company’s Chief Executive Officer (“CEO”) effective May 1, 2022 and he elected not to complete his contractual term and ended his service with the Company effective May 31, 2024.  O’Neill had previously been working with the Company as a consultant and had been employed by the Company as its CEO during 2010-2011. (Upon the hiring of O’Neill, Bassani, CEO of the Company from 2011, assumed the position of COO while retaining existing operational management responsibilities and working with O’Neill on ‘commercialization’ of the Company’s technology and work related to JVs (and other transactions) based on the Company’s Gen3 Technology and related matters until his recent death. Bassani’s compensation arrangements with the Company were not altered in the context of the change of positions.) The Company and O’Neill entered into a thirty-seven (37) month employment agreement with compensation of $25,000 cash and $10,000 deferred compensation per month. The cash payment is paid $12,500 to O’Neill and $12,500 to an entity affiliated with O’Neill. An entity affiliated with O’Neill was issued 1,000,000 Incentive Warrants exercisable at $1.00 per share (a 75% exercise price adjustment provision if the terms set forth therein are met) until April 30, 2026 of which up to 304,743 Incentive Warrants have been cancelled due to O’Neill’s failure to serve the entire contract term. O’Neill was not paid, from October 31, 2023 until his resignation, deferring part or all of his cash compensation due to the Company’s financial crisis described in multiple places herein, and $157,500 was accrued during that period.

 

Until his retirement on July 31, 2024, Smith held the positions of Director, President, Interim Chief Financial Officer and General Counsel of Company (and its subsidiaries) under various agreements (and extensions) and terms since March 2003. On October 10, 2016, the Company approved a month-to-month contract extension with Smith which included provisions for i) a monthly salary of $18,000 (deferred until the Board of Directors re-instated cash payments to all employees and consultants who are deferring compensation), ii) the right to convert up to $300,000 of his deferred compensation, at his sole election, at $0.75 per share, until December 31, 2024, and iii) the right to convert his deferred compensation in whole or in part, at his sole election, at any time in any amount at “market” or into securities sold in the Company’s current/most recent private offering at the price of such offering to third parties. Smith agreed effective July 29, 2018 to continue to serve the Company under the same basic terms on a month-to-month basis. On May 1, 2022 Smith’s compensation was increased to $25,000 per month of which $5,000 per month was deferred. Smith deferred substantial portions of his monthly compensation to help the Company conserve cash. For the three months ended September 30, 2024 and 2023, Smith was paid nil and $15,000, respectively, of cash compensation. Smith was paid, deferring part or all of his cash compensation, since October 31, 2023, due to the Company’s financial crisis described in multiple places herein and $135,000 has been accrued during that period until September 30, 2024.

 

From no later than March 31, 2005, the Company had various agreements with Dominic Bassani (and/or Brightcap which provided his services during some of the years) (NOTE: Dominic Bassani passed away on November 11, 2023.) who was serving as the Company’s Chief Operating Officer (‘COO’) at the time of his passing and formerly served as the Company’s Chief Executive Officer (‘CEO’) for the prior decade (any reference to Brightcap or Bassani for all purposes are referring to the same individual). The Board appointed Bassani as the Company's CEO effective May 13, 2011. On February 10, 2015, the Company executed an Extension Agreement with Bassani pursuant to which Bassani extended the term of his service to the Company to December 31, 2017 (with the Company having an option to extend the term an additional six months.) Pursuant to the Extension Agreement, Bassani continued to defer his cash compensation ($31,000 per month) until the Board of Directors re-instated cash payments to all employees and consultants who were deferring their compensation. During October 2016 Bassani was granted the right to convert up to $125,000 of his deferred compensation, at his sole election, at $0.75 per share, until March 15, 2018 (which was expanded on April 27, 2017, to the right to convert up to $300,000 of his deferred compensation, at his sole election, at $0.75 per share, until June 30, 2024 (including extensions). During February 2018, the Company agreed to the material terms for a binding two-year extension agreement for Bassani’s services as CEO. Bassani’s salary remained $31,000 per month, which accrued in part during periods when the Board determined there was not adequate cash available. Additionally, the Company agreed to pay or accrue $2,000 per month to be applied to life insurance premiums (which sums were accrued as liabilities). On August 1, 2018, in the context of extending his agreement to provide services to the Company on a full-time basis through December 31, 2022) plus 2 years after that on a part-time basis, the Company received an interest bearing secured promissory note for $300,000 from Bassani as consideration to purchase warrants to purchase 3,000,000 shares of the Company’s restricted common stock, which warrants are exercisable at $0.60 and have expiry dates of June 30, 2025. The promissory note is secured by a portion of Bassani’s 2020 Convertible Obligations and, as of June 30, 2024, the principal and accrued interest was $373,099. For the three months ended September 30, 2024 and 2023, Brightcap was paid nil and $15,000, respectively, of cash compensation.

 

Effective April 1, 2024 the Company entered into two material definitive agreements regarding voluntary surrender for cancellation of securities of the Company (and related matters) by: a) members of the family of Dominic Bassani, recently deceased former Chief Executive Officer and (with his family) the Company’s largest shareholder (collectively “Bassani Family”)(“Bassani Family Agreement”), and b) Mark A. Smith, President of the Company and a director (“MAS”) (“MAS Agreement”), as described in multiple places herein.

 

B: Initial Project:

 

On January 28, 2022 Bion Environmental Technologies, Inc. (‘Bion’), on behalf of Bion 3G1 LLC (‘3G1’), a wholly-owned subsidiary, entered into a Purchase Order Agreement with Buflovak and Hebeler Process Solutions (collectively ‘Buflovak’) in the amount of $2,665,500 (and made the initial 25% payment ($666,375) for the core of the ‘Bion System’ portion (without the crystallization modules which will be ordered and fabricated pursuant to subsequent agreements) of the previously announced 3G Tech Initial Project. This Purchase Order encompassed the core of Bion’s 3G Technology. The Company received progress billing in March 2022 and June 2022 for the second and third 25% installments, both of which have been paid as of the filing date. On January 17, 2023 the Company received an invoice from Buflovak for $533,100 which was paid on March 1, 2023 and on April 24, 2023 the Company received an invoice from Buflovak for $83,275 which was paid on May 2, 2023 bringing the aggregate payments to $2,615,500 as of the date of this filing. On July 26, 2023 the Company received the final invoice for $50,000, $16,666 was paid on January 2, 2024 leaving a balance of $33,334. In addition to the Purchase Order, through September 30, 2024 the Company has incurred additional costs of $6,794,925 on the Initial Project for capitalized interest and costs, non-cash compensation, equipment and consulting fees. $7,369,529 has been paid and $1,681,105 has been billed and not yet paid.

 

Buflovak (a division of Hebeler Process Solutions) has worked with the Company on design and testing of its 3G Tech over several years. The basic design for the Initial Project’s ARS System, fabrication and delivery of equipment from Buflovak, and assembly/construction were completed in July 2023, followed by system startup. Steady-state operations were achieved in September 2023, after which time we began optimization of the ARS in preparation for providing final design for full-scale systems, as well as demonstrating its performance and economics for an independent engineering report. Due to delays and interruptions in our ability to operate the system (as below), those efforts have continued to date. We worked in concert with Integrated Engineering Services, the primary site engineering firm for the facility, on the integration of all project components/modules at the Initial Project site during assembly/construction. Additional agreements were entered into with various professional services providers (engineers, surveyors, utilities, etc.) for work related to the Initial Project. The Company has incurred costs of $8,406,434 on the Initial Project, not including capitalized labor and interest.

 

Management previously believed that the Initial Project had reached the point where it could be appropriately deemed ‘placed in service’ at January 1, 2024. However, discussions with the key technical and engineering personnel involved at the Initial Project during the recently concluded quarter convinced management that such a characterization was premature as some key modules had not yet been completed and/or fully tested. Additionally, due to some recent equipment break-downs, the Initial Project was in maintenance mode at that time (and not conducting operations), while the Company awaited required replacement parts and subsequent repairs. This process was slowed by the Company’s ongoing difficulties in raising needed funds for its activities. The Company’s Board of Directors re-evaluated the classification/status of the Initial Project as part of the Company’s annual review process and determined that the Initial Project had been ‘placed in service’ at the June 30, 2024, fiscal year end. Further, after extensive discussion, it was determined that the ‘carrying value’ of the Initial Project on the Company balance sheet as of that date be reduced to $0 in order to conform to accepted accounting practices, because the Initial Project was recently reclassified as largely a research & development facility and is located on land subject to a short term lease (as described below in Item 2, Management’s Discussion and Analysis). As a result, a large ‘one time/non-recurring’ ‘non-cash’ charge of $9,460,425 has been taken by the Company at that date which charge reduced the Company shareholders’ equity to ($5,808,501) and resulted in a loss of $11,691,115 for the 2024 fiscal year. 

 

C: Lease:

 

The Company entered into an agreement on September 23, 2021, to lease approximately four acres of land near Fair Oaks, Indiana, for the development site of its Initial Project.

 

The future minimum lease payment under noncancelable operating lease with terms greater than one year as of September 30, 2024:

    
From July 2024 to December 2024   18,750 
Undiscounted cash flow   18,750 
Less imputed interest   (308)
Total   18,442 

  

 

The weighted average remaining lease term and discounted rate related to the Company’s lease liability as of September 30, 2024 were 0.25 years and 10%, respectively. The Company’s lease discount rate is generally based on the estimates of its incremental borrowing rate as the discount rates implicit in the Company’s lease cannot be readily determined.

 

The Company has not made lease payments since October 16, 2023 and owes $68,750 in lease payments at September 30, 2024.

 

D: Litigation (and related matters):

 

The Company currently is not involved in any other material litigation or similar events.