XML 74 R16.htm IDEA: XBRL DOCUMENT v2.3.0.15
Property, Plant and Equipment
9 Months Ended
Sep. 30, 2011
Property, Plant and Equipment [Abstract] 
Property, Plant and Equipment
 
11.   Property, Plant and Equipment
 
Property, plant and equipment are recorded at historical cost, net of accumulated depreciation. Accumulated depreciation on property, plant and equipment was $749.1 million and $767.2 million as of September 30, 2011 and December 31, 2010, respectively.
 
San Diego Facility
 
On October 1, 2010, we sold the San Diego facility for cash proceeds, net of transaction costs, of approximately $127.0 million. As part of this transaction, we agreed to lease back the San Diego facility for a period of 15 months. We accounted for this transaction as a financing arrangement as we determined that the transaction did not qualify as a sale due to our continuing involvement under the leaseback terms. Accordingly, we recorded an obligation for the proceeds received in October 2010 and the facility assets remained classified as held for use with the carrying value of the facility continued to be reflected as a component of property, plant and equipment, net within our condensed consolidated balance sheets.
 
In the first quarter of 2011, we entered into an agreement to terminate our 15 month lease of the San Diego facility effective August 31, 2011. We have had no continuing involvement or remaining obligation after August 31, 2011 and have accounted for this transaction as a sale of property as of that date. No significant gain on sale was recognized and we did not recognize any impairment charges related to the San Diego facility.
 
Hillerød, Denmark Facility
 
As of September 30, 2011 and December 31, 2010, the construction in progress balance related to the construction of our large-scale biologic manufacturing facility in Hillerød, Denmark totaled $481.7 million and $440.2 million, respectively. This facility is intended to manufacture large molecule products, including TYSABRI. In connection with our construction of this facility, we capitalized interest costs totaling approximately $7.3 million and $21.7 million for the three and nine months ended September 30, 2011, respectively.
 
New Cambridge Leases
 
In July 2011, we executed leases for two office buildings to be built in Cambridge, Massachusetts. We expect construction to begin in late 2011, with a planned occupancy during the second half of 2013. These buildings, totaling approximately 500,000 square feet, will serve as the future location of our corporate headquarters and commercial operations. These buildings will also provide additional general and administrative and research and development office space. The leases both have 15 year terms and we have options to extend the term of each lease for two additional five-year terms. Future minimum rental commitments under these leases will total approximately $340.0 million over the initial 15 year lease terms. In addition to rent, the leases require us to pay additional amounts for taxes, insurance, maintenance and other operating expenses.
 
In accordance with accounting guidance applicable to entities involved with the construction of an asset that will be leased when the construction is completed, we are considered the owner, for accounting purposes, of these properties during the construction period. Accordingly, we will record an asset along with a corresponding financing obligation on our consolidated balance sheet for the amount of total project costs incurred related to the construction-in-progress for these buildings through completion of the construction period. Upon completion of the buildings, we will assess and determine if the assets and corresponding liabilities should be derecognized. As of September 30, 2011, cost incurred in relation to the construction of these buildings was insignificant.