Minimum Annual Purchase Commitments
The minimum annual purchase commitments for all interconnection agreements for 2025 through 2029, calculated at the noticed rates, are as follows:

In thousands
     
2025
 
$
928
 
2026
   
943
 
2027
   
57
 
2028
   
57
 
2029
   
57
 
   
$
2,042
 
Budgeted Mandatory Utility Plant Expenditures
Budgeted mandatory utility plant expenditures, due to planned governmental highway projects, which require the relocation of Artesian Water’s water service mains, expected to be incurred in 2025 through 2027 are as follows:

In thousands
     
2025
 
$
4,050
 
2026
   
13,715
 
2027
   
2,400
 
   
$