REGULATORY PROCEEDINGS (Details) - USD ($)
$ in Millions
3 Months Ended
Apr. 28, 2023
Nov. 20, 2020
Mar. 31, 2024
Mar. 31, 2023
Rate Proceedings [Abstract]        
Percentage of revenue increase requested for new rates 22.66%      
Annual revenue performance obligation $ 16.7      
Percentage of distribution system infrastructure charge 7.50%      
Percentage of DSIC rate upon implementation of temporary increase in base rates charged to customers 15.16%      
Percentage of temporary rates permitted 15.00%      
Amount of temporary rates permitted $ 2.5      
Term of statutory resolve timeframe     7 months  
Period permitted to implement temporary rates     60 days  
Other Proceedings [Abstract]        
Cumulative DSIC Rate   7.50%    
Net Eligible Plant Improvements - Cumulative Dollars   $ 43.1    
Maximum [Member]        
Rate Proceedings [Abstract]        
Percentage of gross water sales in temporary rate increase placed into effect until new rates approved 15.00%      
Delaware [Member]        
Rate Proceedings [Abstract]        
Percentage of gross water sales     15.00%  
Period to complete rate case by law     7 months  
Delaware [Member] | Maximum [Member]        
Rate Proceedings [Abstract]        
Temporary annual rate increase subject to 15% gross water sales limitation     $ 2.5  
Percentage of rate relief allowed should a rate case not complete     15.00%  
Other Proceedings [Abstract]        
Distribution System Improvement Charge rate increase applied between base rate filings     7.50%  
Distribution System Improvement Charge rate increase within a 12-month period     5.00%  
Artesian Water [Member]        
Rate Proceedings [Abstract]        
Amount held in reserve related to temporary base rate increase     $ 0.0  
Other Proceedings [Abstract]        
Revenue earned in DSIC rate increases       $ 1.2