XML 68 R55.htm IDEA: XBRL DOCUMENT v3.22.4
COMMITMENTS AND CONTINGENCIES (Details)
gal in Millions
1 Months Ended 12 Months Ended
Sep. 30, 2022
USD ($)
Apr. 30, 2021
USD ($)
Dec. 31, 2022
USD ($)
a
gal / d
Agreement
gal
Dec. 31, 2021
USD ($)
Dec. 31, 2020
USD ($)
Summary of minimum annual payments related to easement agreements [Abstract]          
2023     $ 25,000    
2024     26,000    
2025     26,000    
2026     26,000    
2027     26,000    
2028 through 2043     1,406,000    
Total     1,535,000    
Summary of minimum annual purchase commitments for all interconnection agreements [Abstract]          
2023     809,000    
2024     798,000    
2025     770,000    
2026     770,000    
2027     0    
Total     3,147,000    
Expenses for purchased water     $ 1,800,000 $ 4,300,000 $ 4,300,000
Artesian Water [Member]          
Interconnections [Abstract]          
Number of water service interconnection agreements | Agreement     2    
Number of expired water service interconnection agreements | Agreement     1    
Term of renewal for water service interconnection agreements     5 years    
Multiplier to estimate minimum purchase requirements for the year | gal     3    
Minimum purchase requirements of water | gal / d     0.5    
Other Commitments [Abstract]          
Agreement period 4 years 3 years      
Expenditure from short term agreement         100,000
Commitment amount $ 2,200,000 $ 1,200,000      
Tank painting expense     $ 531,000 222,000 155,000
Summary of other commitment [Abstract]          
2023     2,218,000    
2024     8,780,000    
2025     5,170,000    
Total     $ 16,168,000    
Artesian Water Pennsylvania [Member]          
Easements [Abstract]          
Easement agreement period     40 years    
Easement payments     $ 43,000 42,000 41,000
Summary of minimum annual payments related to easement agreements [Abstract]          
2023     60,000    
2024     39,000    
2025     40,000    
2026     41,000    
2027     43,000    
2028 through 2043     782,000    
Total     $ 1,005,000    
Artesian Wastewater [Member]          
Easements [Abstract]          
Area of land use as per perpetual agreement (in acres) | a     460    
Minimum rentals payment per year     $ 40,000    
Termination Period     180 days    
Rental payments     $ 113,000 $ 65,000 $ 44,000
Artesian Water Maryland [Member]          
Interconnections [Abstract]          
Number of water service interconnection agreements | Agreement     1    
Minimum purchase requirements of water | gal / d     35,000