On January 18, 2018 Barrick reported that it is analyzing a revised sanction related to the Pascua-Lama project issued by Chile’s Superintendencia del Medio Ambiente (“SMA”) on January 17, 2018.  The sanction is part of a re-evaluation process ordered by Chile’s Environmental Court in 2014 and relates to historical compliance matters at the Pascua-Lama project.  According to Barrick, the SMA has not revoked Pascua-Lama’s environmental permit, but has ordered the closure of existing facilities on the Chilean side of the project, in addition to certain monitoring activities.

 

Barrick also reported that closure of existing surface facilities in Chile is consistent with its plan to advance a prefeasibility study for underground mining operations at Pascua-Lama, which would address a number of community concerns by reducing the overall environmental impact of the project.  Barrick reported that it is currently undertaking a number of optimization studies in order to complete the prefeasibility study.

 

On February 6, 2018, in light of the SMA order to close surface facilities in Chile, and current plans to evaluate an underground mine, Barrick announced it is reclassifying Pascua-Lama’s proven and probable gold reserves of approximately 14 million ounces, which are based on an open pit mine plan, as mineralized material.  Barrick reported that it will include further details in its year-end results release on February 14, 2018 and an update on the Pascua-Lama project at its February 22, 2018 Investor Day. 

 

The Company owns a 0.78% to 5.45% sliding-scale net smelter return (“NSR”) gold royalty and a 1.09% NSR copper royalty on the Pascua-Lama project.  Our royalty interests are applicable to all gold and copper production from the portion of the Pascua-Lama project lying on the Chilean side of the border.  The Company’s carrying value for its royalty interests at Pascua-Lama is approximately $416.8 million as of December 31, 2017. 

 

The Company routinely assesses whether impairment indicators are present for its long-lived assets.  A significant reduction in reserves or mineralized material is an indicator of potential impairment.  As part of our fiscal 2018 third quarter procedures, we will be evaluating Barrick’s reserves reclassification to assess the recoverability of our carrying value at Pascua-Lama.  The Company will also consider further updates from Barrick, including those expected on February 14 and February 22, 2018, as part of our recoverability analysis.  Upon completion of our process, the Company may determine an impairment is necessary.