Commitments and Contingent Liabilities (Tables)
9 Months Ended
Sep. 30, 2014
Commitments and Contingencies Disclosure [Abstract]  
Status of Company's Rigs under Construction
The following table presents the status of the Company’s ultra-deepwater drillship construction program as of September 30, 2014.  Amounts include capitalized interest and an estimate for project contingencies (in millions):

 
Actual/scheduled delivery date
 
Total estimated project costs
 
Total costs incurred through September 30, 2014
 
Projected costs for the remainder of 2014
 
Projected costs in 2015
 
Total future costs
 
 
 
 
 
 
 
 
 
 
 
 
Rowan Resolute
July 2014
 
$
723

 
$
682

 
$
41

 
$

 
$
41

Rowan Reliance
November 2014
 
742

 
277

 
458

 
7

 
465

Rowan Relentless
March 2015
 
755

 
232

 
38

 
485

 
523

 
 
 
$
2,220

 
$
1,191

 
$
537

 
$
492

 
$
1,029