XML 45 R45.htm IDEA: XBRL DOCUMENT v2.4.0.8
COMMITMENTS AND CONTINGENT LIABILITIES (Details) (USD $)
12 Months Ended
Dec. 31, 2013
lawsuit
Dec. 31, 2012
Dec. 31, 2011
Dec. 31, 2009
Commitments and Contingencies Disclosure [Abstract]        
Rental expense attributable to continuing operations $ 9,300,000 $ 8,000,000 $ 5,600,000  
Document Fiscal Year Focus 2013      
Future minimum payments to be made under noncancelable operating leases [Abstract]        
2014 7,099,000      
2015 5,470,000      
2016 4,984,000      
2017 4,857,000      
2018 4,798,000      
Later years 20,876,000      
Total 48,084,000      
Status of company's rigs under construction [Abstract]        
Total estimated project costs 2,947,000,000      
Total costs incurred through December 31, 2013 970,000,000      
Projected costs in 2014 1,522,000,000      
Projected costs in 2015 455,000,000      
Total future costs 1,977,000,000      
Expected capital expenditures in 2013 205,000,000      
Purchase obligations 190,000,000      
Outstanding letters of credit 27,200,000      
Income tax expense (benefit) 8,663,000 (19,829,000) (5,659,000) 25,400,000
Number of Asbestos related law suits 27      
Rowan Renaissance [Member]
       
Status of company's rigs under construction [Abstract]        
Actual/scheduled delivery date Jan. 01, 2014      
Total estimated project costs 729,000,000      
Total costs incurred through December 31, 2013 290,000,000      
Projected costs in 2014 439,000,000      
Projected costs in 2015 0      
Total future costs 439,000,000      
Rowan Resolute [Member]
       
Status of company's rigs under construction [Abstract]        
Actual/scheduled delivery date Jun. 01, 2014      
Total estimated project costs 741,000,000      
Total costs incurred through December 31, 2013 285,000,000      
Projected costs in 2014 456,000,000      
Projected costs in 2015 0      
Total future costs 456,000,000      
Rowan Reliance [Member]
       
Status of company's rigs under construction [Abstract]        
Actual/scheduled delivery date Oct. 01, 2014      
Total estimated project costs 730,000,000      
Total costs incurred through December 31, 2013 207,000,000      
Projected costs in 2014 519,000,000      
Projected costs in 2015 4,000,000      
Total future costs 523,000,000      
Rowan Relentless [Member]
       
Status of company's rigs under construction [Abstract]        
Actual/scheduled delivery date Mar. 01, 2015      
Total estimated project costs 747,000,000      
Total costs incurred through December 31, 2013 188,000,000      
Projected costs in 2014 108,000,000      
Projected costs in 2015 451,000,000      
Total future costs $ 559,000,000