Commitments and Contingent Liabilities (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended 12 Months Ended
Jun. 30, 2013
drilling_unit
lawsuit
Dec. 31, 2009
Status of company's rigs under construction [Abstract]    
Total estimated project costs $ 2,953  
Total costs incurred through June 30, 2013 867  
Projected costs for the remainder of 2013 590  
Projected costs in 2014 1,046  
Projected costs in 2015 450  
Total future costs 2,086  
Capital expenditures for the remainder of 2013 49  
Number of ultra-deepwater drill ships under construction 4  
Outstanding letters of credit 28.1  
Tax benefit recognized   25.4
Number of asbestos related lawsuits 24  
Rowan Renaissance [Member]
   
Status of company's rigs under construction [Abstract]    
Scheduled delivery date Dec. 31, 2013  
Total estimated project costs 729  
Total costs incurred through June 30, 2013 232  
Projected costs for the remainder of 2013 486  
Projected costs in 2014 11  
Projected costs in 2015 0  
Total future costs 497  
Rowan Resolute [Member]
   
Status of company's rigs under construction [Abstract]    
Scheduled delivery date Jun. 30, 2014  
Total estimated project costs 737  
Total costs incurred through June 30, 2013 261  
Projected costs for the remainder of 2013 44  
Projected costs in 2014 432  
Projected costs in 2015 0  
Total future costs 476  
Rowan Reliance [Member]
   
Status of company's rigs under construction [Abstract]    
Scheduled delivery date Oct. 31, 2014  
Total estimated project costs 732  
Total costs incurred through June 30, 2013 194  
Projected costs for the remainder of 2013 34  
Projected costs in 2014 500  
Projected costs in 2015 4  
Total future costs 538  
Rowan Relentless [Member]
   
Status of company's rigs under construction [Abstract]    
Scheduled delivery date Mar. 31, 2015  
Total estimated project costs 755  
Total costs incurred through June 30, 2013 180  
Projected costs for the remainder of 2013 26  
Projected costs in 2014 103  
Projected costs in 2015 446  
Total future costs $ 575