Commitments and Contingent Liabilities (Tables)
6 Months Ended
Jun. 30, 2013
Commitments and Contingencies Disclosure [Abstract]  
Status of Company's Rigs under Construction
The following table presents the status of the Company’s rigs under construction as of June 30, 2013.  Amounts include capitalized interest and an estimate for project contingencies (in millions):

 
Scheduled delivery date
 
Total estimated project costs
 
Total costs incurred through June 30, 2013
 
Projected costs for the remainder of 2013
 
Projected costs in 2014
 
Projected costs in 2015
 
Total future costs
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Rowan Renaissance
December 2013
 
$
729

 
$
232

 
$
486

 
$
11

 
$

 
$
497

Rowan Resolute
June 2014
 
737

 
261

 
44

 
432

 

 
476

Rowan Reliance
October 2014
 
732

 
194

 
34

 
500

 
4

 
538

Rowan Relentless
March 2015
 
755

 
180

 
26

 
103

 
446

 
575

 
 
 
$
2,953

 
$
867

 
$
590

 
$
1,046

 
$
450

 
$
2,086