COMMITMENTS AND CONTINGENT LIABILITIES (Details) (USD $)
12 Months Ended
Dec. 31, 2012
Dec. 31, 2011
Dec. 31, 2010
Dec. 31, 2009
COMMITMENTS AND CONTINGENT LIABILITIES [Abstract]        
Rental expense attributable to continuing operations $ 8,000,000 $ 5,600,000 $ 3,700,000  
Future minimum payments to be made under noncancelable operating leases [Abstract]        
2013 5,120,000      
2014 4,778,000      
2015 4,243,000      
2016 4,250,000      
2017 4,080,000      
Later years 11,359,000      
Total 33,830,000      
Status of company's rigs under construction [Abstract]        
Total estimated project costs 2,959,000,000      
Total costs incurred through December 31, 2012 746,000,000      
Projected costs in 2013 751,000,000      
Projected costs in 2014 1,014,000,000      
Projected costs in 2015 448,000,000      
Total future costs 2,213,000,000      
Expected capital expenditures in 2013 75,000,000      
Outstanding letters of credit 32,900,000      
Estimated cost to decommission well 17,000,000      
Repair expense on damaged rig 12,000,000      
Post-casualty rig valuation 25,000,000      
Income tax expense (benefit) (19,829,000) (5,659,000) 91,934,000 25,400,000
Number of Asbestos related law suits 18      
Rowan Renaissance [Member]
       
Status of company's rigs under construction [Abstract]        
Expected or actual delivery date Dec-13      
Total estimated project costs 730,000,000      
Total costs incurred through December 31, 2012 202,000,000      
Projected costs in 2013 516,000,000      
Projected costs in 2014 12,000,000      
Projected costs in 2015 0      
Total future costs 528,000,000      
Rowan Resolute [Member]
       
Status of company's rigs under construction [Abstract]        
Expected or actual delivery date Jun-14      
Total estimated project costs 738,000,000      
Total costs incurred through December 31, 2012 186,000,000      
Projected costs in 2013 144,000,000      
Projected costs in 2014 408,000,000      
Projected costs in 2015 0      
Total future costs 552,000,000      
Rowan Reliance [Member]
       
Status of company's rigs under construction [Abstract]        
Expected or actual delivery date Oct-14      
Total estimated project costs 731,000,000      
Total costs incurred through December 31, 2012 188,000,000      
Projected costs in 2013 48,000,000      
Projected costs in 2014 491,000,000      
Projected costs in 2015 4,000,000      
Total future costs 543,000,000      
Rowan Relentless [Member]
       
Status of company's rigs under construction [Abstract]        
Expected or actual delivery date Mar-15      
Total estimated project costs 760,000,000      
Total costs incurred through December 31, 2012 170,000,000      
Projected costs in 2013 43,000,000      
Projected costs in 2014 103,000,000      
Projected costs in 2015 444,000,000      
Total future costs $ 590,000,000