Status of company's rigs under construction
The following table presents the status of the Company's rig construction program as of March 31, 2012.  Amounts include capitalized interest and an estimate for project contingencies (in millions):


 
Expected or actual delivery date
 
Total estimated project costs
  
Total costs incurred through March 31, 2012
  
Projected costs for the remainder of 2012
  
Projected costs in 2013
  
Projected costs in 2014
  
Total future costs
 
                      
Rowan Renaissance
Dec-13
 $748  $182  $53  $497  $16  $566 
Rowan Resolute
Jun-14
  742   178   21   146   398   564 
Rowan Reliance
Dec-14
  728   119   67   50   492   609 
     $2,218  $479  $141  $693  $906  $1,739