LEASES
9 Months Ended
Sep. 30, 2021
LEASES  
LEASES

(7)   LEASES

The Company categorize leases at their inception as either operating or financing leases. Leases include various office and warehouse facilities which have been categorized as operating leases while certain equipment is leased under financing leases.

The Company entered into a sublease agreement on April 9, 2021 with Cognizant Trizetto Software Group, Inc. for up to approximately 110,754 square feet of office space as its new corporate headquarters. The term of the sublease began on May 1, 2021 and will run through April 29, 2028. The Company is entitled to rent credits equal to twenty-one months of base rent at the initial rate. During the first thirty-three months of the sublease, the rent per square foot is $26.50. The price per square foot increases by an additional $0.50 during each subsequent twelve-month period of the sublease. Upon lease commencement, the Company recorded an operating lease liability and a corresponding right-of-use asset for $13.4 million each. The remaining lease term was 6.5 years at September 30, 2021.

The Company’s operating leases do not provide an implicit rate, and therefore the Company uses its incremental borrowing rate as the discount rate when measuring the lease liability. The incremental borrowing rate represents an estimate of the interest rate the Company would incur at lease commencement to borrow an amount equal to the lease payments on a collateralized basis over the term of a lease. The Company’s weighted average borrowing rate was determined to be 4.12% for its operating lease liabilities. The Company’s equipment lease agreements have a weighted average rate of 9.37% which was used to measure its finance lease liability.

As of September 30, 2021, the maturities of the Company’s future minimum lease payments were as follows:

Operating lease liability

Finance lease liability

    

(in thousands)

    

(in thousands)

October 1, 2021 through December 31, 2021

$

599

$

38

2022

 

3,569

 

154

2023

 

2,982

 

143

2024

 

3,496

 

80

2025

 

3,567

 

76

2026 and thereafter

7,576

15

Total undiscounted future minimum lease payments

 

$

21,789

 

$

506

Less: Difference between undiscounted lease payments and discounted lease liabilities:

 

(2,672)

 

(44)

Total lease liabilities

$

19,117

$

462

The components of lease expenses were as follows:

Three Months Ended

Nine Months Ended

September 30,

September 30,

    

2021

2020

2021

2020

Lease cost:

  

  

  

  

Operating lease cost:

 

  

 

  

 

  

 

  

Total operating lease expense

$

1,072

$

419

$

2,415

$

1,181

Finance lease cost:

 

  

 

  

 

  

 

  

Total amortization of leased assets

 

29

 

16

 

78

 

44

Interest on lease liabilities

 

11

 

5

 

31

 

14

Total net lease cost

$

1,112

$

440

$

2,524

$

1,239