Gabon

Note 8 – Gabon

We are the operator of the Dussafu PSC with a 66.667 percent ownership interest. Located offshore Gabon, adjacent to the border with the Republic of Congo, the Dussafu PSC covers an area of 680,000 acres with water depths up to 1,650 feet.

The Dussafu PSC partners and the Republic of Gabon, represented by the Ministry of Mines, Energy, Petroleum and Hydraulic Resources, entered into the third exploration phase of the Dussafu PSC with an effective date of May 28, 2012. The Direction Generale Des Hydrocarbures (“DGH”) agreed to lengthen the third exploration phase to four years until May 27, 2016.

During 2011, we drilled our first exploratory well, Dussafu Ruche Marin-1 (“DRM-1”), and two appraisal sidetracks. DRM-1 and sidetracks discovered oil of approximately 149 feet of pay within the Gamba and Middle Dentale Formations. DRM-1 and sidetracks are currently suspended pending further exploration and development activities. Operational activities during 2012 included completion of the time processing of 545 square kilometers of seismic, which was acquired in the fourth quarter of 2011, and well planning.

Well planning progressed during 2012 to drill an exploration well in the fourth quarter of 2012 on the Tortue prospect. DTM-1 well was spud November 19, 2012. DTM-1 was drilled with the Scarabeo 3 semi-submersible drilling unit. On January 4, 2013, we announced that DTM-1 had reached the Dental Formation and discovered oil in both the Gamba and Dentale formations. The first appraisal sidetrack of DTM-1 (“DTM-1ST1”) was spud in January 12, 2013 and drilled to a total depth of 11,385 feet in the Dentale Formation and found 65 feet of pay in the primary Dentale reservoir. Work on DTM-1 and DTM-1ST1 was suspended pending future appraisal and development activities.

Geoscience, reservoir engineering and economic studies have progressed and a field development plan is being prepared for a cluster field development of both the Ruche and Tortue discoveries along with existing pre-salt discoveries at Walt Whitman and Moubenga. Planning and contracting for a 3D seismic acquisition survey over the outer half of the license took place. Acquisition of a 1,260 square kilometer survey commenced in October 2013, and the first high quality seismic products are expected to be available during the second quarter of 2014. The new 3D seismic data should also enhance the placement of future development wells in the Ruche and Tortue development program.

See Note 13 – Commitments and Contingencies for a discussion of legal matters related to our Gabon operations.

The Dussafu PSC represents $103.4 million of unproved oil and gas properties including inventory on our December 31, 2013 balance sheet ($76.4 million at December 31, 2012).